ML060190602
| ML060190602 | |
| Person / Time | |
|---|---|
| Site: | Point Beach (DPR-024, DPR-027) |
| Issue date: | 01/17/2006 |
| From: | Koehl D Nuclear Management Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| BL-03-001, NRC 2006-0013 | |
| Download: ML060190602 (2) | |
Text
a NMC Committed to NuclearExcell Point Beach Nuclear Plant Operated by Nuclear Management Company, LLC January 17, 2006 NRC 2006-0013 BL 2003-01 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington DC 20555 Point Beach Nuclear Plant, Units I and 2 Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Supplement to 60-Day Response to Bulletin 2003-01, "Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors"
References:
1) 2)
3) 4)
5)
Letter from NMC to NRC dated August 8, 2003 (NRC 2003-0068)
Letter from NMC to NRC dated May 14, 2004 (NRC 2004-0050)
Letter from NMC to NRC dated August 19, 2005 (NRC 2005-0106)
Letter from NMC to NRC dated October 18, 2005 (NRC 2005-0134)
Letter from NMC to NRC dated December 19, 2005 (NRC 2005-0155)
In Reference 1, Nuclear Management Company, LLC (NMC), provided the 60-day response to Bulletin (BL) 2003-01, "Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized-Water Reactors," for the Point Beach Nuclear Plant (PBNP). References 2 though 4 supplemented the response. Reference 5 committed to providing a supplement to the 60-day response by January 21, 2006.
On January 10, 2006, NMC received a request for additional information (RAI) associated with a 10 CFR 50.46 emergency core cooling system long-term cooling effects event notification reported to the Commission via Emergency Notification EN 42129.
The 60-day Licensee Event Report (Reference 5) was submitted on December 19, 2005. As a result of the receipt of this information request, it is appropriate that the NMC response to both requests be coordinated as the issues are inter-related. Accordingly, the BL 2003-01 supplemental response commitment date is modified as noted below.
6610 Nuclear Road
- Two Rivers, Wisconsin 54241 A
l)3 Telephone 920.755.2321
Document Control Desk Page 2 Summary of Commitments This letter contains one revised regulatory commitment as follows:
NMC will supplement the 60-day response to NRC Bulletin 2003-01 by February 24, 2006.
If you have any questions or desire further information regarding the subject matter of this letter, please contact me at (920)755-7624.
Dennis L. Koehl Site Vice-President, Point Beach Nuclear Plant Nuclear Management Company, LLC Enclosure cc:
Administrator, Region 1II, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW