FPL Florida Power & Light Company, 6501 S. Ocean Drive, Jensen Beach, FL 34957 December 8, 2005 L-2005-248 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Re:
St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Monthly Operating Report Pursuant to Technical Specification 6.9.1.6, and the guidance of Generic Letter 97-02, attached are the November 2005 Operating Data Reports, Summary of Operating Experience Reports, and Unit Shutdowns for St. Lucie Units 1 and 2.
Please contact us should there be any questions regarding this information.
Very truly yours, William Jdffersi Vice President St. Lucie Plant WJ/KWF Attachment Of.-
-s'
-i an FPL Group company
t a
L-2005-248 Attachment Page 1 of 2 OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIC 50-335 SIt.Lucie I December 04, 2005 K. R. Boller (772) 467-7465 November 2005
- 1. Design Electrical Rating
- 2.
Maximum Dependable Capacity (MWe-Net) 830.00 839.00
- 3.
Number of Hours the Reactor was Critical
- 4.
Number of Hours Generator On-line
- 5.
Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWHrs)
This Month 0.00 0.00 0.00 0.00 Yr-to-Date 6,928.00 6,928.00 0.00 5,871,168.00 Cumulative 208,056.12 206,157.85 0.00 169,296,410.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No.
Date S: Scheduled (Hours) Reason 1 Down 2 Comments 001 10/16/2005 S
720.00 C
4 Scheduled SL1-20 refueling outage.
SUMMARY
- St. Lucie remained offline for SL1-20 scheduled maintenance and refueling activities. In accordance with Technical Specification 6.9.1.6 there were no challenges to the power operated relief valves or safety valves during the report period.
I Reason:
A Equipment Failure (Explain)
B Maintenance or Test C
Refueling D
Regulatory Restriction E
Operator Training & License Examination F
Administration G
Operational Error (Explain)
H Other (Explain) 2 Method:
I Manual 2
Manual Trip/Scram 3
Automatic Trip/Scram 4
Continuation 5
Other (Explain)
L-2005-248 Attachment Page 2 of 2 OPERATING DATA REPORT DOCKET NO.
UNIT NAME DATE COMPLETED BY TELEPHONE REPORTING PERIO 50-389 St. Lucie 2 December 04, 2005 K. R. Boller (772) 467-7748 November 2005
- 1. Design Electrical Rating
- 2. Maximum Dependable Capacity (MWe-Net) 830.00 839.00
- 3.
Number of Hours the Reactor was Critical
- 4.
Number of Hours Generator On-line
- 5.
Reserve Shutdown Hours
- 6.
Net Electrical Energy Generated (MWHrs)
This Month 720.00 720.00 0.00 603,304.00 Yr-to-Date 6,929.69 6,859.22 0.00 5,657,430.00 Cumulative 171,067.91 169,042.09 0.00 139,485,840.0 UNIT SHUTDOWNS Type Method of N F: Forced Duration Shutting Cause & Corrective Action No.
Date S: Scheduled (Hours)
Reason 1
Down 2 Comments
SUMMARY
- St. Lucie Unit 2 operated in Mode I for the entire reporting period. In accordance with Technical Specification 6.9.1.6 there were no challenges to the power operated relief valves or safety valves during the report period.
I 2
Reason:
A Equipment Failure (Explain)
B Maintenance or Test C
Refueling D
Regulatory Restriction E
Operator Training & License Examination F
Administration G
Operational Error (Explain)
H Other (Explain)
Method:
I Manual 2
Manual Trip/Scram 3
Automatic Trip/Scram 4
Continuation 5
Other (Explain)