Summary of the Public Exit Meeting to Discuss the Results of the NRCs Review of Perrys Phase 2 Performance Improvement Initiative (PII)
ML053500162
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/15/2005
From: Eric Duncan
NRC/RGN-III/DRP/RPB6
To:
NRC/RGN-III
References
Download: ML053500162 (5)


Text

December 15, 2005 LICENSEE:

FirstEnergy Nuclear Operating Company FACILITY:

Perry Nuclear Power Plant, Unit 1

SUBJECT:

SUMMARY

OF THE DECEMBER 14, 2005, PUBLIC EXIT MEETING TO DISCUSS THE RESULTS OF THE NRCS REVIEW OF PERRYS PHASE 2 PERFORMANCE IMPROVEMENT INITIATIVE (PII)

On December 14, 2005, the Nuclear Regulatory Commission (NRC) held a public meeting at the Renaissance Quail Hollow Resort in Painesville, Ohio. The meeting was between the NRC and FirstEnergy Nuclear Operating Company (FENOC) management to discuss the results of the NRCs review of Perrys Phase 2 Performance Improvement Initiative. The meeting notice can be found in ADAMS as ML053210385. A list of principal NRC and licensee meeting participants as well as the NRCs and licensees presentation slides can be found in the attached enclosures.

The NRC began the meeting with an overview of Perrys performance history. This was followed by an overview of the current and future Confirmatory Action Letter activities, and a discussion of the results of the NRCs review of Perrys Phase 2 PII.

The licensees presentation included a discussion of the status of the individual PII Initiatives.

At the conclusion of the meeting, time was allotted for public comments and questions.

Sincerely,

/RA/

Eric R. Duncan, Chief Branch 6 Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosures:

As Stated See Attached Distribution

December 15, 2005 LICENSEE:

FirstEnergy Nuclear Operating Company FACILITY:

Perry Nuclear Power Plant, Unit 1

SUBJECT:

SUMMARY

OF THE DECEMBER 14, 2005, PUBLIC EXIT MEETING TO DISCUSS THE RESULTS OF THE NRCS REVIEW OF PERRYS PHASE 2 PERFORMANCE IMPROVEMENT INITIATIVE (PII)

On December 14, 2005, the Nuclear Regulatory Commission (NRC) held a public meeting at the Renaissance Quail Hollow Resort in Painesville, Ohio. The meeting was between the NRC and FirstEnergy Nuclear Operating Company (FENOC) management to discuss the results of the NRCs review of Perrys Phase 2 Performance Improvement Initiative. The meeting notice can be found in ADAMS as ML053210385. A list of principal NRC and licensee meeting participants as well as the NRCs and licensees presentation slides can be found in the attached enclosures.

The NRC began the meeting with an overview of Perrys performance history. This was followed by an overview of the current and future Confirmatory Action Letter activities, and a discussion of the results of the NRCs review of Perrys Phase 2 PII.

The licensees presentation included a discussion of the status of the individual PII Initiatives.

At the conclusion of the meeting, time was allotted for public comments and questions.

Sincerely,

/RA/

Eric R. Duncan, Chief Branch 6 Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosures:

As Stated See Attached Distribution DOCUMENT NAME:E:\\Filenet\\ML053500162.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII N RIII N

NAME RRuiz:dtp EDuncan DATE 12/15/05 12/15/05 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encls:

G. Leidich, President - FENOC J. Hagan, Chief Operating Officer, FENOC D. Pace, Senior Vice President Engineering and Services, FENOC Director, Site Operations Director, Regulatory Affairs M. Wayland, Director, Maintenance Department Manager, Regulatory Compliance T. Lentz, Director, Performance Improvement J. Shaw, Director, Nuclear Engineering Department D. Jenkins, Attorney, First Energy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health

FirstEnergy Nuclear Operating Company ADAMS Distribution:

GYS KNJ RidsNrrDirsIrib GEG KGO RJP DRPIII DRSIII PLB1 JRK1 Principal Meeting Participants NRC K. Jabbour, Perry Project Manager, NRR M. Satorius, Division Director, DRP, RIII E. Duncan, Branch Chief, DRP, RIII M. Franke, Resident Inspector, Perry FirstEnergy Nuclear Operating Company W. Pearce, Acting Vice President, Perry F. von Ahn, Plant Manager, Perry T. Lentz, Director, Performance Improvement, Perry F. Cayia, Director, Performance Improvement, Perry M. Wayland, Manager, Maintenance, Perry J. Shaw, Director, Engineering, Perry