December 7, 2005 DOCKETED UNITED STATES OF AMERICA USNRC NUCLEAR REGULATORY COMMISSION December 7, 2005 (9:06am)
Before the Atomic Safety and Licensing Board OFFICE OF SECRETARY RULEMAKINGS AND
)
-ADJUDICATIONS STAFF In the Matter of
)
)
Docket No. 50-271 ENTERGY NUCLEAR VERMONT
)
YANKEE, LLC and ENTERGY
)
ASLBP No. 04-832-02-OLA NUCLEAR OPERATIONS, INC.
)
(Operating License Amendment)
(Vermont Yankee Nuclear Power Station)
)
ENTERGY'S MOTION TO SET SCHEDULE Pursuant to 10 C.F.R. §2.323, Applicants Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc. (collectively "Entergy") hereby file this motion requesting that the Atomic Safety and Licensing Board ("Board") set a schedule for the filing of a Motion for Summary Disposition of New England Coalition ("NEC") Modified Contention 4, which was admitted by the Board on December 2, 2005. Memorandum and Order (Admitting Intervenor's New Contention), LBP-05-32, 62 NRC (2005).
The Board's Initial Scheduling Order in this proceeding set as the deadline filing motions for summary disposition 30 days after the issuance by the Staff of the Draft Safety Evaluation Report ("Draft SER") for the extended power uprate sought by Entergy. Initial Scheduling Order (Feb. 1, 2005) at 3. The Initial Scheduling Order, however, did not establish a schedule for filing motions for summary disposition for contentions, such as NEC Modified Contention 4, which are admitted 30 days or more after the issuance of the Draft SER.'
On the other hand, the applicable provision in Subpart L of 10 C.F.R. Part 2 states: "(a) Unless the presiding officer The Draft SER was posted on ADAMS on November 2, 2005 (Accession Number ML053010167).
I lp/az$esecv-o4I secV-of
or the Commission directs otherwise, motions for summary disposition may be submitted to the presiding officer by any party no later than forty-five (45) days before the commencement of hearing." 10 C.F.R. §2.1205(a).
Entergy hereby respectfully requests that the Board set the deadline for filing a motion for summary disposition of NEC Modified Contention 4 as: 20 days after the issuance of the Final Safety Evaluation Report. The deadline for filing answers, either supporting or opposing the motion, would remain as set forth in 10 C.F.R. §2.1205(b), i.e., 20 days after service of the motion.
CONCLUSION For the reasons stated above, Entergy requests that the Board issue the schedule requested herein.
CERTIFICATION In accordance with 10 C.F.R. §2.323(b), counsel for Entergy has discussed this motion with counsel for the other parties in this proceeding in an attempt to resolve this issue. Counsel for the NRC Staff indicated that the Staff would not object to the relief requested. NEC's representative stated that NEC could not take a position on this motion at this time.
Respectfully submitted, Jay
. NIberg Matias P. Travieso-Diaz PILLSBURY WINTHROP SHAW PITTMAN LLP 2300 N Street, N.W.
Washington, DC 20037-1128 Tel. (202) 663-8063 Counsel for Entergy Nuclear Vermont Yankee, LLC and Entergy Nuclear Operations, Inc.
Dated: December 7, 2005 2
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of ENTERGY NUCLEAR VERMONT YANKEE, LLC and ENTERGY NUCLEAR OPERATIONS, INC.
(Vermont Yankee Nuclear Power Station)
)
)
)
)
)
)
)
)
Docket No. 50-271 ASLBP No. 04-832-02-OLA (Operating License Amendment)
CERTIFICATE OF SERVICE I hereby certify that copies of "Entergy's Motion to Set Schedule" were served on the persons listed below by deposit in the U.S. Mail, first class, postage prepaid, and where indicated by an asterisk by electronic mail, this 7th day of December, 2005.
- Administrative Judge Alex S. Karlin, Chair Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 ask2(.nrc.gov
- Administrative Judge Dr. Anthony J. Baratta Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 aib5(&nrc.gov
- Secretary Att'n: Rulemakings and Adjudications Staff Mail Stop 0-16 CI U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 secyainrc.aov, hearingdocket()nrc.gov
- Administrative Judge Lester S. Rubenstein 4760 East Country Villa Drive Tucson AZ 85718 lesrrr(mcomcast.net Atomic Safety and Licensing Board Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Office of Commission Appellate Adjudication Mail Stop 0-16 CI U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
- Sarah Hofmann Special Counsel Department of Public Service 112 State Street - Drawer 20 Montpelier, VT 05620-2601 Sarah.Hofmann(astate.vt-us
- Anthony Z. Roisman National Legal Scholars Law Firm 84 East Thetford Rd.
Lyme, NH 03768 aroisman(~nationallegalscholars.com
- Sherwin E. Turk, Esq.
- Robert Weisman, Esq.
- Jason C. Zorn, Esq.
Office of the General Counsel Mail Stop 0-15 D21 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 set(amnrc.gov rmw()nrc.gov icz(inrc.gov
- Raymond Shadis New England Coalition P.O. Box 98 Shadis Road Edgecomb ME 04556 shadis(prexar.com
- Jonathan Rund Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 imr30.nrc. iov
- Jered Lindsay Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 JJL5(inrc.2ov 4AA 0'r r.- i Matias F. Travieso-Diaz 2