MONTHYEARIR 05000275/20230042024-02-0909 February 2024 Integrated Inspection Report 05000275/2023004 and 05000323/2023004 ML24002B1802024-01-29029 January 2024 LRA Audit Plan DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel ML24018A0152024-01-29029 January 2024 License Renewal Application Review Schedule Letter ML24017A2492024-01-24024 January 2024 Letter to Neil Peyron, Chairman, Tule River Tribe, Re. Diablo Canyon ML24024A1752024-01-24024 January 2024 Letter to Tribal Council San Luis Obispo County Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24003A8902024-01-24024 January 2024 Letter to P. Gerfen - Diablo Canyon Notice of Intent to Conduct Scoping and Prepare an Environmental Impact Statement ML24012A1582024-01-24024 January 2024 Letter to Hon. Violet Sage Walker, Chairwoman Northern Chumash Tribal Council on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0062024-01-24024 January 2024 Achp Scoping Letter for Diablo Canyon License Renewal ML24012A0552024-01-24024 January 2024 Letter to J. Polanco, Shpo, on Request to Initiate Section 106 Consultation and Scooping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1562024-01-24024 January 2024 Letter to Hon. Gabe Frausto, Coastal Band of Chumash Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1652024-01-24024 January 2024 Letter to Hon. Mona Olivas Tucker, Yak Tityu Tityu Yak Tilhini Northern Chumas Indians on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24024A1612024-01-24024 January 2024 Letter Hon. Gary Pierce, Salian Tribe of Monterey and San Luis Obispo Counties on Section 106 Consultation and Scoping Process for the Environmental Review of Diablo Canyon Nuclear Plant, Unit 1 and 2 License Renewal Application ML24012A0362024-01-24024 January 2024 Request to Initiate Section 106 Consultation and Scoping Process for the Environmental Review License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b IR 05000275/20230112024-01-12012 January 2024 NRC License Renewal Phase 1 Inspection Report 05000275/2023011 DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel ML23326A0122023-12-21021 December 2023 12-21-23 Letter to the Honorable Byron Donalds from Chair Hanson Responds to Letter Regarding 2.206 Petition to Close Diablo Canyon Nuclear Power Plant, Unit 1 ML23341A0042023-12-19019 December 2023 LRA Acceptance Letter ML23352A2342023-12-18018 December 2023 Notification of Age-Related Degradation Inspection (05000275/2024014 and 05000323/2024014) and Request for Information DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update ML23355A0952023-12-0808 December 2023 License Renewal Application Online Reference Portal DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 ML23291A2702023-11-28028 November 2023 Letter to Nakia Zavalla, Shpo, the Santa Ynez Band of Chumash Indians; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23320A2442023-11-28028 November 2023 Letter to Kerri Vera, Director of Department of Environmental Protection, Tule River Tribe; Re., Diablo Canyon ISFSI Initiating Section 106 Consultation ML23325A1382023-11-27027 November 2023 ISFSI Tribal Letter to San Luis Obispo County Chumash Indians ML23325A1322023-11-27027 November 2023 ISFSI Tribal Letter to Salian Tribe of Montgomery, San Luis Obispo ML23325A1332023-11-27027 November 2023 ISFSI Tribal Letter to Yak Tityu Tityu Northern Chumash Indians ML23307A0062023-11-27027 November 2023 ISFSI Tribal Letter to Northern Chumash Tribal Council ML24003A7242023-11-27027 November 2023 Independent Safety Committee; Diab Lo Canyon Nuclear Power Plant Operations, Thirty-Third Annual Report on the Safety ML23325A1292023-11-27027 November 2023 ISFSI Tribal Letter to Coastal Band of Chumash ML23320A1502023-11-17017 November 2023 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License, Proposed No Significant Hazards Consideration Determination, & Opportunity for Hearing (Exigent Circumstances) (EPID L-2023-LLA-0155) - LTR DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System ML23296A0982023-11-15015 November 2023 Notification and Request for Consultation Regarding Pacific Gas and Electric Diablo Canyon Independent Spent Fuel Storage Installation Material License Renewal Request (Docket Number: 72-26) DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System ML23293A1052023-11-14014 November 2023 Receipt and Availability of License Renewal Application IR 05000275/20230032023-11-13013 November 2023 Integrated Inspection Report 05000275/2023003 and 05000323/2023003 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application ML23318A2102023-10-31031 October 2023 Independent Safety Committee; Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System IR 05000275/20240152023-10-10010 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection (050002752024015 and 050003232024015) 2024-02-09
[Table view] |
Text
November 10, 2005 Mr. David H. Oatley Acting Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P. O. Box 56 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 RE: ASSIGNMENTS OF NUCLEAR REGULATORY COMMISSION PROJECT MANAGER (PM) AND BRANCH CHIEF AS A RESULT OF REORGANIZATION OF THE OFFICE OF NUCLEAR REACTOR REGULATION
Dear Mr. Oatley:
The Office of Nuclear Reactor Regulation (NRR) is being reorganized to support anticipated new-reactor licensing, risk-informed regulation, and generally improve the effectiveness and efficiency of NRR's programs and processes. The new organization became effective on October 31, 2005.
The former five large divisions in NRR have been expanded to nine smaller divisions. Each division is headed by a division director and one or two deputy directors. The former Division of Licensing Project Management is now designated as the Division of Operating Reactor Licensing (DORL) and will focus primarily on licensing activities. Generic and programmatic issues are now managed by the Division of Policy and Rulemaking. In the new DORL, the former first-line supervisors, Section Chiefs, are re-designated as Branch Chiefs.
In the new DORL, the Licensing PM for your facility is Mr. Alan B. Wang. Mr. Wang may be contacted at (301) 415-1445 or via email at abw@nrc.gov. I am the assigned Branch Chief for your facility and may be contacted at (301) 415-3317 or via email at dxt@nrc.gov.
Sincerely,
/RA by Jack Donohew for/
David Terao, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: See next page
November 10, 2005 Mr. David H. Oatley Acting Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P. O. Box 56 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 RE: ASSIGNMENTS OF NUCLEAR REGULATORY COMMISSION PROJECT MANAGER (PM) AND BRANCH CHIEF AS A RESULT OF REORGANIZATION OF THE OFFICE OF NUCLEAR REACTOR REGULATION
Dear Mr. Oatley:
The Office of Nuclear Reactor Regulation (NRR) is being reorganized to support anticipated new-reactor licensing, risk-informed regulation, and generally improve the effectiveness and efficiency of NRR's programs and processes. The new organization became effective on October 31, 2005.
The former five large divisions in NRR have been expanded to nine smaller divisions. Each division is headed by a division director and one or two deputy directors. The former Division of Licensing Project Management is now designated as the Division of Operating Reactor Licensing (DORL) and will focus primarily on licensing activities. Generic and programmatic issues are now managed by the Division of Policy and Rulemaking. In the new DORL, the former first-line supervisors, Section Chiefs, are re-designated as Branch Chiefs.
In the new DORL, the Licensing PM for your facility is Mr. Alan B. Wang. Mr. Wang may be contacted at (301) 415-1445 or via email at abw@nrc.gov. I am the assigned Branch Chief for your facility and may be contacted at (301) 415-3317 or via email at dxt@nrc.gov.
Sincerely,
/RA by Jack Donohew for/
David Terao, Chief Plant Licensing Branch IV Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323 cc: See next page DISTRIBUTION:
PUBLIC LPLIV R/F RidsNrrPMGShukla RidsNrrPMAWang RidsNrrPMFields RidsNrrLALFeizollahi RidsNrrDlpmLpdiv1 (DTerao) RidsOgcMailCenter RidsAcrsAcnwMailCenter RidsRgn4MailCenter (BJones) JDyer/WBorchardt BBoger LBerry (Concurrence block for change in PM and BC)
ADAMS Accession Number: ML053190466 NRR-106 OFFICE LPLIV/PM LPLIV/LA LPLIV/BC DORL/D NAME AWang LFeizollahi JDonohew for CHaney DTerao DATE 11/9/05 11/9/05 11/9/05 11/10/05 OFFICIAL RECORD COPY G:/ADRO/DORL/LPLG/Diablo Canyon/reorgassignmentltr.wpd
Diablo Canyon Power Plant, Units 1 and 2 cc:
NRC Resident Inspector Diablo Canyon Power Plant Richard F. Locke, Esq.
c/o U.S. Nuclear Regulatory Commission Pacific Gas & Electric Company P.O. Box 369 P.O. Box 7442 Avila Beach, CA 93424 San Francisco, CA 94120 Sierra Club San Lucia Chapter City Editor c/o Henriette Groot The Tribune 1000 Montecito Road 3825 South Higuera Street Cayucos, CA 93430 P.O. Box 112 San Luis Obispo, CA 93406-0112 Ms. Nancy Culver San Luis Obispo Mr. Ed Bailey, Chief Mothers for Peace Radiologic Health Branch P.O. Box 164 State Department of Health Services Pismo Beach, CA 93448 P.O. Box 997414 (MS 7610)
Sacramento, CA 95899-7414 Chairman San Luis Obispo County Board of Mr. James D. Boyd, Commissioner Supervisors California Energy Commission Room 370 1516 Ninth Street (MS 31)
County Government Center Sacramento, CA 95814 San Luis Obispo, CA 93408 Mr. James R. Becker, Vice President Mr. Truman Burns Diablo Canyon Operations Mr. Robert Kinosian and Station Director California Public Utilities Commission Diablo Canyon Power Plant 505 Van Ness, Room 4102 P.O. Box 3 San Francisco, CA 94102 Avila Beach, CA 93424 Diablo Canyon Independent Safety Jennifer Tang Committee Field Representative ATTN: Robert R. Wellington, Esq. United States Senator Barbara Boxer Legal Counsel 1700 Montgomery Street, Suite 240 857 Cass Street, Suite D San Francisco, CA 94111 Monterey, CA 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavillion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 October 2005