Site: Perry FirstEnergy icon.png
Issue date: 10/20/2005
From: Eric Duncan
NRC/RGN-III/DRP/RPB6
To: Richard Anderson
FirstEnergy Nuclear Operating Co
References
Download: ML052930242 (6)


Text

October 20, 2005 Mr. R. Anderson Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road, A290 Perry, OH 44081

SUBJECT:

UPCOMING PERRY NUCLEAR POWER PLANT PERFORMANCE IMPROVEMENT INITIATIVE PHASE 2 REVIEW

Dear Mr. Anderson:

On November 7, 2005, the NRC will begin a review of your Phase 2 Perry Performance Improvement Initiative at your Perry Nuclear Power Plant as part of our Confirmatory Action Letter followup activities.

In order to minimize the impact that the inspection has on the site and to ensure a productive inspection, we have enclosed a request for documents needed for the inspection. The documents should be ready for NRC review by October 28, 2005.

If there are any questions about the material requested, or the inspection in general, please call Eric Duncan at (630) 829-9628.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Eric R. Duncan, Chief Branch 6 Division of Reactor Projects Docket No. 50-440 License No. NPF-58

Enclosure:

Request for Information Regarding Performance Improvement Initiative Phase 2 Review See Attached Distribution

DOCUMENT NAME:E:\Filenet\ML052930242.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME DJones:dtp EDuncan DATE 10/20/05 10/20/05 OFFICIAL RECORD COPY

R. Anderson cc w/encl: G. Leidich, President - FENOC J. Hagan, Chief Operating Officer, FENOC D. Pace, Senior Vice President Engineering and Services, FENOC Director, Site Operations Director, Regulatory Affairs M. Wayland, Director, Maintenance Department Manager, Regulatory Compliance T. Lentz, Director, Performance Improvement J. Shaw, Director, Nuclear Engineering Department D. Jenkins, Attorney, First Energy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health

R. Anderson ADAMS Distribution:

GYS WAM1 RidsNrrDipmIipb GEG KGO RJP DRPIII DRSIII PLB1 JRK1 WDL (IRs only)

Requested Information to Support Performance Improvement Initiative Phase 2 Review

1. Three (3) copies of the most recent revision to the Phase 2 Performance Improvement Initiative (PII); including the Detailed Action and Monitoring Plan (DAMP).
2. Three (3) copies of all procedures associated with the PII process.
3. A list of the Key Performance Indicators (KPIs) used to monitor PII results, including any available data, to date.
4. Three (3) copies of the recently completed licensee root cause evaluations associated with the human performance (Root Cause Report 05-02517) and corrective action program (Root Cause Report 05-03986) areas.
5. A list, including contact information, of principal staff members associated with the PII.