Site: Seabrook NextEra Energy icon.png
Issue date: 10/20/2005
From: Darrell Roberts
NRC/NRR/DLPM/LPD1
To: Peschel J, St.Pierre G
Florida Power & Light Energy Seabrook
Miller G, NRR/DLPM, 415-2481
References
Download: ML052930126 (4)


Text

October 20, 2005 Mr. Gene F. St. Pierre Site Vice President c/o James M. Peschel Seabrook Station PO Box 300 Seabrook, NH 03874

SUBJECT:

PROJECT MANAGER REASSIGNMENT - SEABROOK STATION

Dear Mr. St. Pierre:

Effective October 20, 2005, Mr. G. Edward Miller has replaced Mr. Victor Nerses as the Project Manager for Seabrook Station. Mr. Miller can be reached by telephone at 301-415-2481. His mailstop is O-8B-1.

Sincerely,

/RA/

Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-443 cc: See next page

October 20, 2005 Mr. Gene F. St. Pierre Site Vice President c/o James M. Peschel Seabrook Station PO Box 300 Seabrook, NH 03874

SUBJECT:

PROJECT MANAGER REASSIGNMENT - SEABROOK STATION

Dear Mr. St. Pierre:

Effective October 20, 2005, Mr. G. Edward Miller has replaced Mr. Victor Nerses as the Project Manager for Seabrook Station. Mr. Miller can be reached by telephone at 301-415-2481. His mailstop is O-8B-1.

Sincerely,

/RA/

Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-443 cc: See next page DISTRIBUTION:

PUBLIC PDI-2 Reading File J. Dyer B. Sheron G. Miller C. Raynor C. Holden D. Roberts OGC ACRS/ACNW P. Krohn, RG1 L. Berry V. Nerses ACCESSION NO: ML052930126 OFFICE PDI-2/PM PDI-2/LA PDI-2/SC PDI/D NAME GMiller CRaynor DRoberts CHolden DATE 10/19/05 10/19/05 10/19/05 10/20/05 OFFICIAL RECORD COPY

Seabrook Station, Unit No. 1 cc:

Mr. J. A. Stall Senior Vice President, Nuclear and Chief Nuclear Officer Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Peter Brann Assistant Attorney General State House, Station #6 Augusta, ME 04333 Resident Inspector U.S. Nuclear Regulatory Commission Seabrook Nuclear Power Station P.O. Box 1149 Seabrook, NH 03874 Town of Exeter 10 Front Street Exeter, NH 03823 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Office of the Attorney General One Ashburton Place, 20th Floor Boston, MA 02108 Board of Selectmen Town of Amesbury Town Hall Amesbury, MA 01913 Ms. Deborah Bell Federal Emergency Management Agency Region I J.W. McCormack P.O. &

Courthouse Building, Room 401 Boston, MA 02109 Mr. Tom Crimmins Polestar Applied Technology One First Street, Suite 4 Los Altos, CA 94019 Mr. Stephen McGrail, Director ATTN: James Muckerheide Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702-5399 Philip T. McLaughlin, Attorney General Steven M. Houran, Deputy Attorney General 33 Capitol Street Concord, NH 03301 Mr. Bruce Cheney, Director New Hampshire Office of Emergency Management State Office Park South 107 Pleasant Street Concord, NH 03301 Mr. Gene F. St. Pierre Station Director Seabrook Station FPL Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Mr. M. S. Ross, Managing Attorney Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Mr. Rajiv S. Kundalkar Vice President - Nuclear Engineering Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 James M. Peschel Regulatory Programs Manager Seabrook Station FPL Energy Seabrook, LLC PO Box 300 Seabrook, NH 03874

Seabrook Station, Unit No. 1 cc:

David Moore Vice President, Nuclear Operations Support Florida Power & Light Company P.O. Box 14000 Juno Beach, FL 33408-0420 Marjan Mashhadi Senior Attorney Florida Power & Light Company 801 Pennsylvania Ave., NW Suite 220 Washington, DC 20004