Letter Sequence Other |
---|
TAC:MC6878, Control Rod SCRAM Time Testing Frequency (Approved, Closed) |
|
MONTHYEARML0511902702005-04-19019 April 2005 License Amendment Request, Application for Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency Using the Consolidated Line Item Improvement Process (Clip) Project stage: Request ML0527300232005-09-29029 September 2005 Tech Spec Pages for Amendment 194 Regarding Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency Using the Consolidated Line Item Improvement Process Project stage: Other ML0516001232005-09-29029 September 2005 Issuance of License Amendment 194 Regarding Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency Using the Consolidated Line Item Improvement Process Project stage: Approval 2005-04-19
[Table View] |
|
---|
Category:Technical Specifications
MONTHYEARML24128A2242024-05-31031 May 2024 Issuance of Amendment No. 274 to Revise Technical Specifications to Adopt TSTF-584, Eliminate Automatic RWCU System Isolation on SLC Initiation ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position ML22308A0962022-12-15015 December 2022 Issuance of Amendment No. 269 License Amendment to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors ML21053A3162021-03-0303 March 2021 Issuance of Amendment No. 264 to Revise Technical Specification to Adopt Traveler TSTF-582, Revision 0, Reactor Pressure Vessel Water Inventory Control (RPV WIC) Enhancements ML21005A1782021-01-25025 January 2021 Issuance of Amendment No. 263 to Revise Technical Specifications to Adopt TSTF-566, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Using the Consolidated Line Item Improvement Process ML20242A0022020-09-0404 September 2020 Issuance of Amendment No. 261 Revise Technical Specification 3.8.7, Distribution Systems - Operating (Exigent Circumstances) ML20135H0842020-06-29029 June 2020 Issuance of Amendment No. 260 Revise Technical Specifications to Adopt TSTF-563, Revision 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program ML20125A0802020-05-12012 May 2020 Issuance of Amendment No. 258 Changes to Technical Specification Limiting Conditions for Operation 3.8.4 and 3.8.7 (Exigent Circumstances) ML18100A1992018-05-0202 May 2018 Issuance of Amendment No. 249 Change to Technical Specification 3.5.1 ECCS - Operating (CAC No. MG0015; EPID L-2017-LLA-0277) GO2-17-124, Final Technical Specification Markup and Clean Pages for Application to Revise Technical Specifications to Adopt TSTF-545, Revision 32017-07-0505 July 2017 Final Technical Specification Markup and Clean Pages for Application to Revise Technical Specifications to Adopt TSTF-545, Revision 3 ML0531303192017-07-0505 July 2017 Current Facility Operating License NPF-21, Technical Specifications, Revised 11/01/2017 ML17095A1172017-05-11011 May 2017 Columbia Generating Station - Issuance Of Amendment No. 241 Re: Measurement Uncertainty Recapture (CAC No. MF8060) GO2-16-071, Final Technical Specification Markup and Clean Pages for License Amendment Request to Adopt Technical Specification Task Force (TSTF)-425, Revision 3 to Relocate Specific Surveillance Frequencies to a Licensee Controlled Program2016-05-11011 May 2016 Final Technical Specification Markup and Clean Pages for License Amendment Request to Adopt Technical Specification Task Force (TSTF)-425, Revision 3 to Relocate Specific Surveillance Frequencies to a Licensee Controlled Program ML15216A2662016-02-0303 February 2016 Issuance of Amendment No. 236, Adoption of Technical Specification Task Force Traveler TSTF-423, Revision 1, Technical Specifications End States, as Part of Consolidated Line Item Improvement Process GO2-15-173, Supplement to Response to Second Request for Additional Information on License Amendment Request for Adoption of Technical Specification Task Force (TSTF)-425, Revision 32015-12-28028 December 2015 Supplement to Response to Second Request for Additional Information on License Amendment Request for Adoption of Technical Specification Task Force (TSTF)-425, Revision 3 ML15154A8002015-06-11011 June 2015 Issuance of Amendment No. 235, Extension of Implementation Period for Amendment 232 Changing Technical Specification Table 3.3.1.1-1, Function 7, Scram Discharge Volume Water Level - High (Exigent Circumstances) ML15076A1222015-04-15015 April 2015 Issuance of Amendment No. 233, Request to Revise Technical Specification Surveillance Requirement 3.7.1.1 Related to the Ultimate Heat Sink ML15030A5012015-02-0101 February 2015 Issuance of Amendment No. 230, Revise Technical Specifications for One-Time Extension of Completion Time Required Actions Related to Residual Heat Removal System B Inoperability (Emergency Circumstances) ML15031A0022015-01-30030 January 2015 Emergency License Amendment Associated with Technical Specifications 3.5.1.A, 3.6.1.5.A, and 3.6.2.3.A, Request for CT Extension on RHR-B Inoperability ML14335A1892015-01-0707 January 2015 Redacted, Issuance of Amendment No. 229, Revise Emergency Core Cooling Systems Surveillance Requirements for Low Pressure Core Spray and Low Pressure Coolant Injection Pump Flows ML14290A3602014-11-12012 November 2014 Issuance of Amendment No. 228, Request to Adopt Technical Specification Task Force (TSTF)-535, Revision 0, Revise Shutdown Margin Definition to Address Advanced Fuel Designs ML14127A4002014-06-13013 June 2014 Request for Technical Specification Interpretation Regarding the Offsite Power Supplies to the Onsite Class 1E Alternating Current Power Distribution System GO2-14-043, License Amendment Request for Changing Technical Specification Table 3.3.1.1-1 Function 7, Scram Discharge Volume Water Level-High2014-03-24024 March 2014 License Amendment Request for Changing Technical Specification Table 3.3.1.1-1 Function 7, Scram Discharge Volume Water Level-High GO2-12-104, Response to Request for Additional Information for License Amendment Request to Make Administrative and Editorial Changes to Technical Specifications and the Operating License2012-07-30030 July 2012 Response to Request for Additional Information for License Amendment Request to Make Administrative and Editorial Changes to Technical Specifications and the Operating License GO2-12-003, License Amendment Request to Make Administrative and Editorial Changes to Technical Specifications and the Operating License2012-01-0909 January 2012 License Amendment Request to Make Administrative and Editorial Changes to Technical Specifications and the Operating License GO2-10-098, Request for Approval of the Cyber Security Plan2010-07-22022 July 2010 Request for Approval of the Cyber Security Plan ML1013903692010-05-11011 May 2010 Columbia Generating Station, License Amendment Request to Change Technical Specifications in Support of Prnm/Arts/Mella Implementation GO2-10-024, License Amendment Request to Change Technical Specifications Relating to Control Rod Operability and Control Rod Scram Accumulators2010-02-0808 February 2010 License Amendment Request to Change Technical Specifications Relating to Control Rod Operability and Control Rod Scram Accumulators GO2-09-043, Independent Spent Fuel Storage Installation - Offsite Dose Calculation Manual, Including Revision Made During 20082009-02-27027 February 2009 Independent Spent Fuel Storage Installation - Offsite Dose Calculation Manual, Including Revision Made During 2008 ML0823800182008-09-16016 September 2008 Tech Spec Pages for Amendment No. 209 TSTF-484, Use of TS 3.10.1 for Scram Time Testing Activities. ML0819005982008-09-15015 September 2008 Tech Spec Pages for Amendment No. 208 Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves GO2-08-122, Supplement to Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves2008-08-28028 August 2008 Supplement to Adoption of Approved Generic Technical Specification Changes Associated with Containment Isolation Valves ML0817702012008-06-30030 June 2008 Tech Spec Pages for Amendment No. 207 Control Room Habitability in Accordance with TSTF-448-A, Rev 3 ML0810602972008-04-15015 April 2008 License Page 3 and Technical Specification Page 10 for Amendment No. 206 Eliminate Condition 2.F GO2-07-156, Supplement to License Amendment Request for Proposed Changes to Technical Specifications: Miscellaneous Administrative Changes Including Adoption of Approved TSTF Travelers 284, 479, and 4852007-11-0606 November 2007 Supplement to License Amendment Request for Proposed Changes to Technical Specifications: Miscellaneous Administrative Changes Including Adoption of Approved TSTF Travelers 284, 479, and 485 ML0703802052007-02-27027 February 2007 License and Technical Spec Pages - Amendment No. 202 Under Exigent Circumstances TS 3.6.1.7, Suppression Chamber-to-Drywell Vacuum Breakers-Allow One-time Extension to Current Closure Verification SR ML0705203982007-02-13013 February 2007 Supplemental Information Regarding License Amendment Request to Technical Specifications Associated with AC and DC Electrical Power ML0703000212007-02-0909 February 2007 Technical Specifications, Issuance of Amendment No. 201 to Facility Operating License Suppression Chamber-to-Drywell Vacuum Breakers and Drywell-to-Suppression Chamber Bypass Leakage Test ML0632800532006-11-27027 November 2006 Tech Spec Pages for Amendment 199 Changes to Technical Specifications to Replace the Current Accident Source Term Used in Design Basis Radiological Analyses ML0624301412006-07-11011 July 2006 Issuance of Technical Specification Pages Re Inoperability of Snubbers GO2-06-060, Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers (TSTF-372) Using the Consolidated Line Item Improvement Process2006-04-17017 April 2006 Application for Technical Specification Change to Add LCO 3.0.8 on the Inoperability of Snubbers (TSTF-372) Using the Consolidated Line Item Improvement Process ML0610202712006-03-13013 March 2006 E-mail 3/13/2006 - Clean TS Pages for DG AOT ML0630400372005-12-0808 December 2005 Technical Specifications, One Time Extension of the 72- Hour Completion Time (CT) for the Required Action of Condition B Technical Specification (TS) 3.7.1 ML0534101872005-12-0808 December 2005 Issuance of Amendment One Time Extension of the 72- Hour Completion Time (CT) for the Required Action of Condition B Technical Specification (TS) 3.7.1 TAC No. MC8421 GO2-05-186, Supplement to the License Amendment Request for a One-Time Change to Technical Specifications2005-11-30030 November 2005 Supplement to the License Amendment Request for a One-Time Change to Technical Specifications ML0527300232005-09-29029 September 2005 Tech Spec Pages for Amendment 194 Regarding Technical Specification Improvement to Revise Control Rod Scram Time Testing Frequency Using the Consolidated Line Item Improvement Process GO2-05-099, License Amendment Request to Technical Specifications Associated with AC and DC Electrical Power2005-05-31031 May 2005 License Amendment Request to Technical Specifications Associated with AC and DC Electrical Power ML0513602142005-05-12012 May 2005 Technical Specification Pages Reactor Coolant System (RCS) Pressure and Temperature Limits (Tac. MC3591) ML0510301872005-04-12012 April 2005 Technical Specifications, One-Time Extension of Appendix J Type a Integrated Leakage Rate Test Interval 2024-05-31
[Table view] |
Text
I
- -- K Control Rod Scram Times 3.1.4 SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.1.4.2 Verify, for a representative sample, each 200 days tested control rod scram time is within the cumulative I limits of Table 3.1.4-1 with reactor steam operation in dome pressure > 800 psig. MODE 1 SR 3.1.4.3 Verify each affected control rod scram time Prior to is within the limits of Table 3.1.4-1 with declaring any reactor steam dome pressure. control rod OPERABLE after work on control rod or CRD System that could affect scram time SR 3.1.4.4 Verify each affected control rod scram time Prior to is within the limits of Table 3.1.4-1 with exceeding reactor steam dome pressure > 800 psig. 40% RTP after work on control rod or CRD System that could affect scram time AND Prior to exceeding 40%
RTP after fuel movement within the reactor pressure vessel Columbia Generating Station 3.1.4- 3 Amendment rho. 1 l9-,<9, 194 1
Control Rod Scram Times 3.1.4 Table 3.1.4-1 Control Rod Scram Times
NOTE-------------------------------------
Enter applicable Conditions and Required Actions of LCO 3.1.3. "Control Rod OPERABILITY." for control rods with scram times > 7 seconds to notch position 5. These control rods are inoperable, in accordance with SR 3.1.3.4, and are not considered "slow."
SCRAM TIMES(a)(b) (seconds)
WHEN REACTOR STEAM DOME PRESSURE NOTCH POSITION > 800 psig 45 0.430 39 0.868 25 1.936 5 3.497 (a) Maximum scram time from fully withdrawn position, based on de-energization of scram pilot valve solenoids as time zero.
(b) Scram times as a function of reactor steam dome pressure, when
< 800 psig, are within established limits.
Columbia Generating Station 3.1.,1-/l Amendment hNo. +44 16i91