FENOC Perry Nuclear Power Plant 10 Center Road FirstEnergy Nuclear Operating Company Perry Ohio 44081 Richard Anderson 440-280-5579 Vice President-Nuclear Fax: 440-280-8029 September 9, 2005 PY-CEIINRR-2908L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:
Attached is the August 2005 Monthly Operating Report for Perry Unit 1. Page I is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."
If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.
Very truly yours, Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector
OPERATING DATA REPORT UNIT:
Per DATE:
9/7/05 1.
2.
3.
4.
5.
6.
7.
Docket: 50-440 Unit Name: Perry Nuclear Power Plant Reporting Period August 2005 Utility
Contact:
T. Phelos Telephone: 440-280-7660 Design Electrical Rating (Net MWe):
Maximum Dependable Capacity (Net MWe):
1260 1235 8.
9.
10.
11.
Hours Reactor was Critical Hours Generator On-Line Unit Reserve Shutdown Hours Net Electrical Energy (MWeH)
This Month 744.0 744.0 0.0 910.533.0 Yr-to-Date 3.539.9 3.434.5 0.0 A 4299 8n n Cumulative 124.209.3 121.325.8 0.0 139.378.737.0 Page 1
II UNIT SHUTDOWNS REPORT MONTH - AUGUST 2005 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 917/05 CONTACT: T. PhelDs TELEPHONE: (440) 280-7660 No.
Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence Hours 2
3
SUMMARY
- The Perry Nuclear Power Plant was on line the entire month of August, 2005.
- 1. TYPE:
F: Forced S: Scheduled
- 2. REASON:
A - Equipment Failure (explain)
B - Maintenance or Test C - Refueling D - Regulatory E - Operating Training &
License Examination F -Administrative G - Operational Error (explain)
H - Other (explain)
- 3. METHOD:
1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation 5 - Other Page 2