Surry Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/29/2005 16:21:03 Report 22 5
EB1-MODS
- MODIFICATIONS/10CFR50.59 Baseline Inspections 09/19/2005 09/23/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 Baseline Inspections 09/19/2005 09/23/2005 Permanent Plant Modifications IP 7111117B 1, 2 1
EB1SSDPC - SSDPC PRE-INSPECTION VISIT Baseline Inspections 12/12/2005 12/16/2005 Safety System Design and Performance Capability IP 7111121 1, 2 4
OL PREP
- INITIAL EXAM PREP Not Applicable 01/09/2006 01/13/2006 SURRY/EXAMS AT POWER FACILITIES V23210 1
6 EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY Baseline Inspections 01/09/2006 01/13/2006 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 01/23/2006 01/27/2006 Safety System Design and Performance Capability IP 7111121 1, 2 Baseline Inspections 02/06/2006 02/10/2006 Safety System Design and Performance Capability IP 7111121 1, 2 4
OL EXAM
- EXAM WEEK 1 Not Applicable 01/23/2006 01/27/2006 SURRY/EXAMS AT POWER FACILITIES V23210 1
4 OL EXAM
- EXAM WEEK 2 Not Applicable 02/06/2006 02/10/2006 SURRY/EXAMS AT POWER FACILITIES V23210 1
4 PS2 EP
- EP EXERCISE Baseline Inspections 02/06/2006 02/10/2006 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 02/06/2006 02/10/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 02/06/2006 02/10/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 02/06/2006 02/10/2006 Performance Indicator Verification IP 71151 1, 2 2
EB3-ISI
- U1 INSERVICE INSPECTION Baseline Inspections 05/01/2006 05/05/2006 Inservice Inspection Activities - PWR IP 7111108P 1
1 EB3SGISI
- U1 STEAM GENERATOR ISI Baseline Inspections 05/08/2006 05/12/2006 Inservice Inspection Activities - PWR IP 7111108P 1
1 EB3-HS
- HEAT SINK Baseline Inspections 05/22/2006 05/26/2006 Heat Sink Performance IP 7111107B 1, 2 4
EB2-TFP
- TRIENNIAL FP PRE-INSPECTION VISIT Baseline Inspections 05/16/2006 05/18/2006 Fire Protection [Triennial]
IP 7111105T 1, 2 4
EB2-TFP
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 06/12/2006 06/16/2006 Fire Protection [Triennial]
IP 7111105T 1, 2 4
EB2-TFP
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 06/26/2006 06/30/2006 Fire Protection [Triennial]
IP 7111105T 1, 2 1
PS1-RP
- RP PREINSPECTION VISIT PUBLIC/ ISFSI Baseline Inspections 07/10/2006 07/12/2006 Access Control to Radiologically Significant Areas IP 7112101 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclosure
Surry Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/29/2005 16:21:03 Report 22 4
PS1-RP
- RP BASELINE PUBLIC Baseline Inspections 07/31/2006 08/04/2006 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 07/31/2006 08/04/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 07/31/2006 08/04/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 07/31/2006 08/04/2006 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P IP 7112203 1, 2 Baseline Inspections 07/31/2006 08/04/2006 Performance Indicator Verification IP 71151 1, 2 2
EB3-MR
- MR EFFECTIVENESS Baseline Inspections 08/28/2006 09/01/2006 Maintenance Effectiveness IP 7111112B 1, 2 1
PS2-EP
- EP INSP Baseline Inspections 10/23/2006 10/27/2006 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 10/23/2006 10/27/2006 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 10/23/2006 10/27/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 10/23/2006 10/27/2006 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 10/23/2006 10/27/2006 Performance Indicator Verification IP 71151 1, 2 1
EB3-ISI
- U2 INSERVICE INSPECTION Baseline Inspections 10/30/2006 11/03/2006 Inservice Inspection Activities - PWR IP 7111108P 2
1 EB3SGISI
- U2 STEAM GENERATOR ISI Baseline Inspections 11/06/2006 11/10/2006 Inservice Inspection Activities - PWR IP 7111108P 2
- REQUAL INSPECTION Baseline Inspections 03/05/2007 03/09/2007 Licensed Operator Requalification Program IP 7111111B 1, 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.