MONTHYEARIR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24061A1702024-03-0101 March 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000237/2024010 and 05000249/2024010 IR 05000237/20230062024-02-28028 February 2024 Annual Assessment Letter for Dresden Nuclear Station, Units 2 and 3 (Report 05000237/2023006; 05000249/2023006) ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23087A0852023-03-28028 March 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000237/20220062023-03-0101 March 2023 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2022006 and 05000249/2022006) ML23037A9192023-02-0707 February 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000237/2023011 and 05000249/2023011 ML22318A1842022-11-15015 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000237/2023401; 05000249/2023401 ML22306A2172022-11-0202 November 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) ML22068A0862022-03-0909 March 2022 Reissue Dresden Nuclear Power Station, Units 2 and 3 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22062B0522022-03-0404 March 2022 Information Request for an Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection IR 05000237/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000237/2021006 and 05000249/2021006) ML22027A3592022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000010, License No. DPR-2 IR 05000237/20220102021-12-21021 December 2021 Notification of NRC DBAI (Programs) and Initial RFI Inspection Report 05000237/2022010 05000249/2022010 ML21265A2262021-09-22022 September 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000237/2021004 05000249/2021004 IR 05000237/20210052021-09-0101 September 2021 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3, Report 05000237/2021005 and 05000249/2021005 ML21096A1752021-04-0606 April 2021 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000237/2021011; 05000249/2021011 IR 05000237/20200062021-03-0404 March 2021 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020006 and 05000249/2020006) ML20337A4242020-12-0202 December 2020 Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection 05000237/2021401 and 05000249/2021401 ML20302A4602020-10-28028 October 2020 Request for Information for an NRC Triennial Baseline Deisgn Bases Assurance Inspection (Team): Inspection Report 05000237/2021010; 05000249/202101 IR 05000237/20200052020-09-0101 September 2020 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005) IR 05000237/20190062020-03-0303 March 2020 Annual Assessment Letter for Dresden, Units 2 and 3 (Report 05000237/2019006 and 05000249/2019006, 05000237/2019006 and 05000249/2019006) ML19290G5152019-10-15015 October 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20190052019-08-28028 August 2019 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2019005 and 05000249/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000237/20180062019-03-0404 March 2019 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018006 and 05000249/2018006) ML19008A3912019-01-0707 January 2019 Initial Information Request (Part 2) for the Upcoming Phase IV License Renewal Inspection, Dated 01/07/19 (DRS-J. Corujo-Sandin) IR 05000237/20180052018-08-28028 August 2018 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018005 and 05000249/2018005) IR 05000237/20170062018-03-0202 March 2018 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017006 and 05000249/2017006) IR 05000237/20170112018-01-0202 January 2018 NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000237/2017011 and 05000249/2017011 ML17354B0352017-12-20020 December 2017 U1: CY2018 Master Inspection Plan IR 05000237/20170052017-08-28028 August 2017 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017005 and 05000249/2017005) ML17240A2672017-08-25025 August 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Dresden, Units 2 and 3 ML17236A0742017-08-23023 August 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2017004; 05000249/2017004 IR 05000237/20160062017-03-0101 March 2017 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2016006 and 05000249/2016006) ML16351A1072016-12-15015 December 2016 Master Inspection Plan - Calendar Year 2017 IR 05000237/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3,(Report 05000237/2016005; 05000249/2016005) ML16242A0712016-08-26026 August 2016 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000237/2017007; 05000249/2017007 ML16070A1102016-03-0909 March 2016 Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000237/2016009; 05000249/2016009 IR 05000237/20150062016-03-0202 March 2016 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Inspection Report 05000237/2015006 and 05000249/2015006) ML16011A4852016-01-11011 January 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML15357A1282015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML15322A3722015-11-18018 November 2015 IR 05000237/2016008; 05000249/2016008 February 8 - 12, 2016; and February 22 - 26, 2016, Dresden Nuclear Power Station, Units 2 and 3; Request for Information for an NRC Pilot Component Design Bases Inspection IR 05000237/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2015005; 05000249/2015005) IR 05000237/20140012015-03-0404 March 2015 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3, (Report 05000237/2014001; 05000249/2014001) IR 05000237/20130012014-03-0404 March 2014 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2013001; 05000249/2013001) ML14003A2832014-01-0303 January 2014 Fire Protection Request for Information ML13308B2322013-11-0404 November 2013 Ltr 11/4/13 Dresden, Unit 2 and 3, Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestone 1-7 and Request for Information IR 05000237-14-405; 05000249-144-40 ML13301A7352013-10-28028 October 2013 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Dresden Nuclear Power Station, Units 2 and 3 2024-08-28
[Table view] Category:Letter
MONTHYEARML24291A0272024-10-31031 October 2024 NRC Letter to C. Mayer Illinois SHPO Request to Initiate Section 106 Consultation for Subsequent License Renewal of Units 2 and 3 RS-24-103, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-10-21021 October 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-102, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-5912024-10-21021 October 2024 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-591 RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24225A2132024-09-26026 September 2024 Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval ML24253A0942024-09-23023 September 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID L-2024-Sle-0002) (Docket Numbers: 50-237 and 50-249) ML24270A0332024-09-20020 September 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVPLTR 24-0030, ISFSI Annual Effluent Release Report2024-09-20020 September 2024 ISFSI Annual Effluent Release Report IR 05000237/20244022024-09-19019 September 2024 – Security Baseline Inspection Report 05000237/2024402 and 05000249/2024402 - (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000237/20240022024-08-14014 August 2024 Integrated Inspection Report 05000237/2024002 and 05000249/2024002 ML24215A2912024-08-14014 August 2024 Request for Withholding Information from Public Disclosure Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations IR 05000237/20240102024-08-0909 August 2024 NRC Age-Related Degradation Inspection Report 05000237/2024010 and 05000249/2024010 ML24157A0792024-08-0808 August 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID L-2024-Sle-0002) (Docket Numbers: 50-237, and 50-249) IR 05000237/20230112024-08-0707 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 IR 05000237/20200012024-08-0606 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 - Integrated Inspection Report 05000237/2020001 and 05000249/2020001 ML24184A1712024-08-0202 August 2024 SLRA Schedule Letter RS-24-073, Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information2024-07-31031 July 2024 Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information ML24136A1322024-07-30030 July 2024 Transmittal Letter for Renewed License ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24193A0882024-07-24024 July 2024 Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Unit 1 Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations (Docket 50-10) ML24204A1862024-07-24024 July 2024 – Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2; TSTF-591, Revision 0; and 10 CFR 50.69 IR 05000237/20243012024-06-27027 June 2024 NRC Initial License Examination Report 05000237/2024301; 05000249/2024301 ML24138A0572024-06-26026 June 2024 – Issuance of Amendment Nos. 285 and 278 Application to Adopt TSTF-564, Safety Limit MCPR ML24138A1812024-06-18018 June 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24128A2742024-06-14014 June 2024 Notice of Acceptance and Opportunity for Hearing - Letter RS-24-063, Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-222024-06-14014 June 2024 Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-22 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24156A2332024-06-11011 June 2024 Letter Supplemental Information for Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24183A2752024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel SVPLTR 24-0020, Registration of Use of Casks to Store Spent Fuel2024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel RS-24-056, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2024-05-28028 May 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24145A0432024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel 10 CFR 72.212 SVPLTR 24-0019, Registration of Use of Casks to Store Spent Fuel2024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel ML24158A0012024-05-22022 May 2024 License Amendment Request to Adopt TSTF-564 (EPID L-2023-LLA-0120) Illinois State Concurrence ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24135A0722024-05-10010 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report ML24129A1352024-05-0808 May 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-59 ML24134A1132024-05-0808 May 2024 Retraction: LER 2303-001-00 for Dresden Nuclear Power Station, Unit 2, HPCI Inoperable Due to Air Void Accumulation ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) 2024-09-06
[Table view] |
Text
August 30, 2005 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION
Dear Mr. Crane:
On August 9, 2005, the NRC staff completed its performance review of the Dresden Nuclear Power Station for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Plant performance for the most recent quarter at Dresden Units 2 and 3 was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only reactor oversight process (ROP) baseline inspections at your facility through March 31, 2007.
In our Mid-Cycle Performance Review letter dated August 30, 2004, we advised you of a substantive cross-cutting issue in the area of human performance. In our Annual Assessment Letter dated March 2, 2005, we advised you that human performance issues had continued and we were continuing the substantive human performance cross-cutting issue pending a reduction in the number, significance, and common causality. You responded to the Annual Assessment Letter with a letter dated April 29, 2005, describing your assessment of human performance at Dresden, the causal factors that had resulted in the human performance issues, and the Human Performance Improvement Plan that you had developed. We understand that you have now achieved site-wide implementation of the Human Performance Improvement Plan. We also noted that only one finding was identified in the last half of the assessment period (2005) having aspects of the substantive cross-cutting area of human performance.
C. Crane Therefore, since the number and significance of human performance findings decreased and the 2004 findings were already addressed, we no longer have a concern with the scope and progress of your efforts in addressing this cross-cutting area performance deficiency, and we are discontinuing the substantive cross-cutting issue in human performance.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2007. Please note that the biennial Problem Identification and Resolution inspection is planned for January 2006. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan See Attached Distribution DOCUMENT NAME: G:\Branch TSS\ALL MOC\midcycle 2004 to 2005\MOC letters\dres.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII E NAME MRing:dtp DATE 08/25/05 OFFICIAL RECORD COPY
C. Crane cc w/encl: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Director, Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood INPO
C. Crane ADAMS Distribution:
GYS DWW Project Director, NRR Project Mgr., NRR RidsNrrDipmlipb JLC1 GEG KGO RML2 SRI Dresden DRPIII DRSIII PLB1 JRK1
Page 1 of 2 Dresden 08/29/2005 11:01:36 Inspection / Activity Plan Report 22 09/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type INSPECTI - ISFSI INSPECTION - CASK LOADING 2 2 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 08/18/2005 09/28/2005 Other Routine ISI - UNIT 2 ISI INSPECTION 1 2 IP 7111108G Inservice Inspection Activities - BWR 11/07/2005 11/11/2005 Baseline Inspections 71121.02 - OUTAGE ALARA 1 2, 3 IP 7112102 ALARA Planning and Controls 11/14/2005 11/18/2005 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 11/14/2005 11/18/2005 Baseline Inspections 71114 - BASELINE EP INSPECTION 1 2, 3 IP 7111402 Alert and Notification System Testing 01/09/2006 01/13/2006 Baseline Inspections 2, 3 IP 7111403 Emergency Response Organization Augmentation Testing 01/09/2006 01/13/2006 Baseline Inspections 2, 3 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 01/09/2006 01/13/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 01/09/2006 01/13/2006 Baseline Inspections FY 2005 - DRESDEN INIT PREP 01/2006 3 2 W90124 OL - INITIAL EXAM - DRESDEN - JAN/FEB 2006 01/09/2006 01/13/2006 Not Applicable 71152B - PROBLEM IDENTIFICATION AND RESOLUTION 2 2, 3 IP 71152B Identification and Resolution of Problems 01/09/2006 01/27/2006 Baseline Inspections FY 2005 - DRESDEN INIT EXAM 02/2006 3 2 W90124 OL - INITIAL EXAM - DRESDEN - JAN/FEB 2006 02/06/2006 02/10/2006 Not Applicable 7112103 - RADIOLOGICAL INSTRUMENTATION 1 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/13/2006 03/17/2006 Baseline Inspections HS - HEAT SINK INSPECTION 1 2 IP 7111107B Heat Sink Performance 03/20/2006 03/24/2006 Baseline Inspections ISFSI - OPERATION OF AN ISFSI 1 2, 3 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 05/01/2006 06/30/2006 Other Routine INSPECTI - ISFSI INSPECTION 2 2 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 05/01/2006 07/30/2006 Other Routine 71111.11 - LIC OPERATOR REQUAL PROGRAM EVALUATION 2 2, 3 IP 7111111B Licensed Operator Requalification Program 05/15/2006 05/19/2006 Baseline Inspections 7112101 - RADIOLOGICAL ACCESS CONTROL 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 07/17/2006 07/21/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 07/17/2006 07/21/2006 Baseline Inspections 7112203 - REMP & RAD MATL CONTROL 1 2, 3 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P 09/25/2006 09/29/2006 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 09/25/2006 09/29/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Dresden 08/29/2005 11:01:36 Inspection / Activity Plan Report 22 09/01/2005 - 03/31/2007 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type ISI - DRESDEN UNIT 3 ISI INSPECTION 1 3 IP 7111108G Inservice Inspection Activities - BWR 10/16/2006 10/20/2006 Baseline Inspections 7112102 - ALARA OUTAGE INSP 1 2, 3 IP 7112102 ALARA Planning and Controls 11/13/2006 11/17/2006 Baseline Inspections M50.59 - MOD 50.59 INSPECTION 2 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 11/13/2006 11/30/2006 Baseline Inspections 2 IP 7111117A Permanent Plant Modifications 11/13/2006 12/15/2006 Baseline Inspections ME - MAINTENANCE EFFECTIVENESS INSPECTION 1 2, 3 IP 7111112B Maintenance Effectiveness 12/11/2006 12/15/2006 Baseline Inspections 7111401 - EP EXERCISE & PI INSP 1 2, 3 IP 7111401 Exercise Evaluation 03/19/2007 03/23/2007 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 03/19/2007 03/23/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.