August 30, 2005 Mr. William OConnor, Jr.
Vice President Nuclear Generation The Detroit Edison Company 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN-FERMI POWER PLANT
Dear Mr. OConnor:
On August 9, 2005, the NRC staff completed its performance review of the Fermi Power Plant for the first half of the calendar year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Plant performance for the most recent quarter was within the Licensee Response column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct only reactor oversight process (ROP) baseline inspections at your facility through March 31, 2007.
In our Annual Assessment Letter dated March 2, 2005, we advised you of a cross-cutting human performance issue in the personnel area. During this assessment period, the staff continued to identify findings with cross-cutting aspects in the area of human performance. In the past six months, inspectors identified seven Green findings where human performance was inadequate. One was attributed to organization, and six were attributed to inadequate personnel performance. Five of these findings were in the reactor safety strategic performance area, three in the mitigating systems cornerstone, and two in the emergency preparedness cornerstone; and one other finding in the public radiation safety cornerstone. The finding attributed to human performance organization was in the emergency preparedness cornerstone. Therefore, the staff has concluded that the area of human performance continues to be a substantive cross-cutting issue.
W. OConnor, Jr. In response to the identification of human performance deficiencies, you have performed several immediate corrective actions. Additionally, you have planned several long-term corrective actions. You are requested to provide us with a letter, within 30 days of the receipt of this letter, which details the actions you have taken to date to address this long-standing substantive cross-cutting issue as well as your future planned actions with your implementation schedule.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through March 31, 2007. Significant inspections planned for this year include the Biennial Problem Identification and Resolution Inspection in October 2005, a Biennial Safety System Design and Performance Inspection in November 2005 and an Initial Operator Exam in February 2006. The inspection plan is provided to minimize the resource impact on your staff and to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review meeting.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact Eric Duncan at (630) 829-9628 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA by R. Lerch Acting for/
Eric R. Duncan, Chief Reactor Projects Branch 6 Division of Reactor Projects Docket No. 50-341 License No. NPF-43
Enclosure:
Fermi Power Plant Inspection/ Activity Plan See Attached Distribution
DOCUMENT NAME:G:\\Branch TSS\\ALL MOC\\midcycle 2004 to 2005\\MOC letters\\ferm.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RLerch for EDuncan:dtp DATE 08/29/05 OFFICIAL RECORD COPY
W. OConnor, Jr. cc w/encl:
N. Peterson, Manager, Nuclear Licensing D. Pettinari, Legal Department Compliance Supervisor G. White, Michigan Public Service Commission L. Brandon, Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division Monroe County, Emergency Management Division Planning Manager, Emergency Management Division MI Department of State Police Chair, Wayne County Board of Commissioners Wayne County Sheriff Director, Wayne County Emergency Management Agency Mayor of Flat Rock Mayor of Gibraltar City Administrator Monroe County Board Chairman Monroe County Sheriff Director, Monroe County Emergency Management Agency Director, Monroe County Health Department Mayor of Monroe Monroe City Manager Carleton Village President Mayor of Rockwood Rockwood City Administrator Frenchtown Charter Township Supervisor INPO
W. OConnor, Jr. ADAMS Distribution:
CAC DWW NKR Project Director, NRR RidsNrrDipmlipb JLC1 GEG KGO RML2 SRI Fermi DRPIII DRSIII PLB1 JRK1
Fermi Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/29/2005 11:02:26 Report 22 4
- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 10/17/2005 11/04/2005 Identification and Resolution of Problems IP 71152B 2
2 71111.11
- LIC OPERATOR REQUAL PROGRAM EVALUATION Baseline Inspections 10/24/2005 10/28/2005 Licensed Operator Requalification Program IP 7111111B 2
6 SSDPC
- SAFETY SYSTEM DESIGN & PERFORMANCE Baseline Inspections 11/14/2005 12/02/2005 Safety System Design and Performance Capability IP 7111121 2
1 71121.02
- NON-OUTAGE ALARA Baseline Inspections 12/05/2005 12/09/2005 ALARA Planning and Controls IP 7112102 2
Baseline Inspections 12/05/2005 12/09/2005 Performance Indicator Verification IP 71151 2
1 MAINT
- MAINTENANCE EFFECTIVENESS Baseline Inspections 01/09/2006 01/13/2006 Maintenance Effectiveness IP 7111112B 2
3 FY 2006
- FERMI INIT PREP 01/2006 Not Applicable 01/23/2006 01/27/2006 FERMI - JAN/FEB 2006 W90145 2
3 FY 2006
- FERMI INIT EXAM 02/03/2006 Not Applicable 02/20/2006 03/03/2006 FERMI - JAN/FEB 2006 W90145 2
1 ISI
- FERMI ISI INSPECTION Baseline Inspections 03/13/2006 03/17/2006 Inservice Inspection Activities - BWR IP 7111108G 2
2 7112102
- ALARA OUTAGE INSP Baseline Inspections 03/27/2006 03/31/2006 ALARA Planning and Controls IP 7112102 2
2 7111401
- EP EXERCISE BASELINE Baseline Inspections 06/05/2006 06/09/2006 Exercise Evaluation IP 7111401 2
Baseline Inspections 06/05/2006 06/09/2006 Performance Indicator Verification IP 71151 2
2 7112101
- RADIOLOGICAL ACCESS CONTROL Baseline Inspections 06/19/2006 06/23/2006 Access Control to Radiologically Significant Areas IP 7112101 2
Baseline Inspections 06/19/2006 06/23/2006 Performance Indicator Verification IP 71151 2
2 MOD/5059
- MODIFICATION/50.59 INSPECTIONS Baseline Inspections 07/24/2006 08/11/2006 Evaluation of Changes, Tests, or Experiments IP 7111102 2
Baseline Inspections 07/24/2006 08/11/2006 Permanent Plant Modifications IP 7111117B 2
1 7112101
- RADIOLOGICAL ACCESS CONTROL Baseline Inspections 07/24/2006 07/28/2006 Access Control to Radiologically Significant Areas IP 7112101 2
Baseline Inspections 07/24/2006 07/28/2006 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P IP 7112203 2
1 7112201
- EFFLUENTS Baseline Inspections 11/27/2006 12/01/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 2
Baseline Inspections 11/27/2006 12/01/2006 Performance Indicator Verification IP 71151 2
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Fermi Inspection / Activity Plan 09/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/29/2005 11:02:26 Report 22 1
7112103
- INSTRUMENTATION & ACCESS CONTROL Baseline Inspections 03/12/2007 03/16/2007 Access Control to Radiologically Significant Areas IP 7112101 2
Baseline Inspections 03/12/2007 03/16/2007 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 2
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.