FENOC Perry Nuclear Power Plant I _%
10 Center Road FirstEnergy Nuclear Operating Company Perry Ohio 44081 RichardAnderson 440-280-5579 Vice President-Nuclear Fax: 440-280-8029 August 8, 2005 PY-CEI/NRR-2899L Secretary, Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555 Perry Nuclear Power Plant Docket No. 50-440 Response to a July 19, 2005 Commission Order Imposing Additional Security Measures on the Transportation of Radioactive Material Quantities of Concern By letter dated July 19, 2005, the Nuclear Regulatory Commission (NRC) issued an immediately effective Order (EA-05-007) imposing additional security measures on the transportation of radioactive material quantities of concern (RAMQC), which requires compliance with specific security measures by January 17, 2006 or before the next shipment of RAMQC thereafter.
Pursuant to 10 C.F.R. § 2.202(d), the FirstEnergy Nuclear Operating Company consents to the Order, and is not requesting a hearing on the Perry Nuclear Power Plant docket.
There are no regulatory commitments contained in this letter or its attachments. If there are any questions concerning this matter, please contact Mr. Henry L. Hegrat, Supervisor-Fleet Licensing, at (330) 315-6944.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 8,2005.
cc: NRC Project Manager NRC Resident Inspector.
NRC Region IlIl Document Control Desk Director, Office of Nuclear Reactor Regulation
,Assistant General Counsel for Materials Litigation and Enforcement Office of Enforcement