Notification of an NRC Triennial Fire Protection Baseline Inspection 05000263-05-013
ML052280286
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 08/16/2005
From: Julio Lara
Division of Reactor Safety III
To: Conway J
Nuclear Management Co
References
IR-05-013
Download: ML052280286 (8)


See also: IR 05000263/2005013

Text

August 16, 2005

Mr. J. Conway

Site Vice President

Monticello Nuclear Generating Plant

Nuclear Management Company, LLC

2807 West County Road 75

Monticello, MN 55362-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - NOTIFICATION OF AN NRC

TRIENNIAL FIRE PROTECTION BASELINE INSPECTION 05000263/2005013

Dear Mr. Conway:

On October 17, 2005, the NRC will begin a triennial fire protection baseline inspection at the

Monticello Nuclear Generating Plant. This inspection activity will be performed in accordance

with the NRC baseline Inspection Procedure 71111.05T.

The schedule for the inspection is as follows:

Information gathering visit: October 4 - 5, 2005

On-site inspection activity: October 17 - 21 and October 31 - November 4, 2005

The purpose of the information gathering visit is: (1) to obtain information and documentation

needed to support the inspection; (2) to become familiar with the Monticello Nuclear Generating

Plant fire protection programs, fire protection features, post-fire safe shutdown capabilities and

plant layout; and (3) to arrange administrative details such as office space, availability of

knowledgeable office personnel and to ensure unescorted site access privileges.

Experience has shown that the baseline fire protection inspections are extremely resource

intensive both for the NRC inspectors and the licensee staff. In order to minimize the

inspection impact on the site and to ensure a productive inspection for both sides, we have

enclosed a request for documents needed for the inspection. These documents have been

divided into four groups. The first group lists information necessary to aid the inspection team

in choosing specific focus areas for the inspection. It is requested that this information be

provided to the lead inspector via mail or electronically no later than September 23, 2005. The

second group lists information necessary to ensure that the inspection team is adequately

prepared for the inspection. This information should be available on-site no later than

October 4, 2005. The third group of requested documents are those items that the team will

review, or need access to, during the inspection. Please have this information available by the

first day of the on-site portion of the inspection, October 17, 2005. The fourth group lists

information necessary to aid the inspection team in tracking issues identified as a result of the

inspection. It is requested that this information be provided to the lead inspector as the

information is generated during the inspection. It is important that all of these documents are

J. Conway

-2-

up to date and complete in order to minimize the number of additional documents requested

during the preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Mr. Ronald A. Langstaff. We understand that our

technical contact for this inspection is Ms. Michelle Kelly of your organization. If there are any

questions about the inspection or the material requested, please contact the lead inspector at

(630) 829-9747 or via e-mail at ral4@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-263

License Nos. DPR-22

Enclosure:

Fire Protection Inspection Document Request

cc w/encl:

J. Cowan, Executive Vice President

and Chief Nuclear Officer

Manager, Regulatory Affairs

J. Rogoff, Vice President, Counsel, and Secretary

Nuclear Asset Manager, Xcel Energy, Inc.

Commissioner, Minnesota Department of Health

R. Nelson, President

Minnesota Environmental Control Citizens

Association (MECCA)

Commissioner, Minnesota Pollution Control Agency

D. Gruber, Auditor/Treasurer,

Wright County Government Center

Commissioner, Minnesota Department of Commerce

Manager - Environmental Protection Division

Minnesota Attorney Generals Office

J. Conway

-2-

up to date and complete in order to minimize the number of additional documents requested

during the preparation and/or the on-site portions of the inspection.

The lead inspector for this inspection is Mr. Ronald A. Langstaff. We understand that our

technical contact for this inspection is Ms. Michelle Kelly of your organization. If there are any

questions about the inspection or the material requested, please contact the lead inspector at

(630) 829-9747 or via e-mail at ral4@nrc.gov.

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter and

its enclosure will be available electronically for public inspection in the NRC Public

Document Room or from the Publicly Available Records (PARS) component of NRC's

document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Julio F. Lara, Chief

Engineering Branch 3

Division of Reactor Safety

Docket Nos. 50-263

License Nos. DPR-22

Enclosure:

Fire Protection Inspection Document Request

cc w/encl:

J. Cowan, Executive Vice President

and Chief Nuclear Officer

Manager, Regulatory Affairs

J. Rogoff, Vice President, Counsel, and Secretary

Nuclear Asset Manager, Xcel Energy, Inc.

Commissioner, Minnesota Department of Health

R. Nelson, President

Minnesota Environmental Control Citizens

Association (MECCA)

Commissioner, Minnesota Pollution Control Agency

D. Gruber, Auditor/Treasurer,

Wright County Government Center

Commissioner, Minnesota Department of Commerce

Manager - Environmental Protection Division

Minnesota Attorney Generals Office

  • Concurrence via email

DOCUMENT NAME: ML052280286.wpd

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy

OFFICE

RIII *

RIII

RIII

NAME

RLangstaff:tr

BBurgess

JLara

DATE

08/12/05

08/16/05

08/16/05

OFFICIAL RECORD COPY

J. Conway

-3-

ADAMS Distribution:

HKN

LMP

RidsNrrDipmIipb

GEG

KGO

SPR

DRPIII

DRSIII

PLB1

JRK1

INITIAL DOCUMENT REQUEST

Enclosure

1

FIRE PROTECTION INSPECTION DOCUMENT REQUEST

Inspection Report: 05000263/2005013(DRS)

Inspection Dates:

October 4 - 5, 2005

(Information Gathering)

October 17 - 21, 2005

(On-site Inspection Activity)

October 31 - November 4, 2005

(On-site Inspection Activity)

Inspection Procedures:

IP 71111.05T, Fire Protection

IP 71152, Identification and Resolution of Problems

Inspectors:

Lead Inspector:

R. Langstaff

Team Members:

A. Dahbur

Contractor

Information Requested Prior to the Information Gathering Visit

The following information is requested by September 23, 2005. If you have any questions

regarding this information, please call the lead inspector as soon as possible. All information

may be sent electronically (to R. A. Langstaff, e-mail address ral4@nrc.gov) or provided on

compact disc.

(1)

The reactor plant's Individual Plant Examination for External Events (IPEEE) for fire,

results of any post-IPEEE reviews for fire, and listings of actions taken/plant

modifications conducted in response to IPEEE information for fire. Alternatively,

probabilistic risk analyses for fire and associated information, if it exists and is more

recent than the IPEEE.

(2)

A list of fire areas requiring alternative shutdown capability, i.e., those areas for which

10 CFR Part 50, Appendix R, Section III.G requirements are satisfied under

Section III.G.3.

Information Requested During the Information Gathering Visit (October 4 - 5, 2005)

This information is requested to be available on-site during the information gathering visit.

(1)

The current version of the Fire Protection Program and Fire Hazards Analysis;

(2)

Listing of plant fire protection licensing basis documents;

(3)

Copies of NRC Safety Evaluation Reports, relevant to fire protection and safe shutdown

in the event of a fire;

(4)

Listing of changes to the fire protection program and associated adverse to safe

shutdown evaluations;

(5)

A list of Generic Letter 86-10 evaluations;

INITIAL DOCUMENT REQUEST

Enclosure

2

(6)

A list of applicable codes and standards related to the design of plant fire protection

features. The list should include National Fire Protection Association (NFPA) code

versions committed to (i.e., the NFPA codes of record);

(7)

A list of plant deviations from code commitments;

(8)

Post-fire safe shutdown analyses, including the identification of post-fire safe shutdown

systems and separation analyses, plant transient response analyses, and manual action

feasibility analyses, as applicable;

(9)

Piping and instrumentation (flow) diagrams showing the components used to achieve

and maintain hot standby and cold shutdown for fires outside the control room and those

components used for those areas requiring alternative shutdown capability;

(10)

Plant layout drawings which identify plant fire area delineation, areas protected by

automatic fire suppression and detection, and the locations of fire protection equipment

for selected fire zones/areas (to be determined during information gathering visit);

(11)

Listing of open and closed fire protection condition reports for the past three years;

(12)

Listing of fire impairments for the previous year;

(13)

Pre-fire plans for selected fire zones/areas (to be determined during information

gathering visit);

(14)

Plant operating procedures which would be used to respond to a fire alarm/annunciator,

for dispatching a fire brigade, and implementing safe shutdown for a postulated fire in

selected fire zones/areas (to be determined during information gathering visit);

(15)

A listing of the protection methodologies identified under 10 CFR Part 50, Appendix R,

Section III.G used to achieve compliance for selected fire zones/areas (to be

determined during information gathering visit). That is, please specify whether 3-hour

rated fire barriers (Section III.G.2.a), 20-foot separation along with detection and

suppression (Section III.G.2.b), 1-hour rated fire barriers with detection and suppression

(Section III.G.2.c), or alternative shutdown capability (Section III.G.3) is used for each

selected fire zone/area (to be determined during information gathering visit);

(16)

One-line schematic drawings of the electrical distribution system for 4160 volts -

alternating current (VAC) down to 480 Vac;

(17)

One-line schematic drawings of the electrical distribution system for 250 volts - direct

current (VDC) and 125 Vdc systems as applicable;

(18)

A listing of abbreviations/designators for plant systems;

(19)

Organization charts of site personnel down to the level of fire protection staff personnel;

and

(20)

A phone list for on-site licensee personnel.

INITIAL DOCUMENT REQUEST

Enclosure

3

In addition, during the information gathering visit, it is requested that licensee staff be available

for the following:

(1)

Informal discussion on plant procedures operators would use in the event of fire and

under what conditions would the plant be shutdown using alternative shutdown

methodology;

(2)

Informal discussion on the plants safe shutdown cable routing database and the

plant-wide cable routing database, as applicable; and

(3)

A tour of alternative shutdown and risk significant fire areas.

Information Requested to be Available on First Day of Inspection (October 17, 2005)

(1)

List of the fire protection program implementing procedures (e.g., administrative controls

and fire brigade);

(2)

List of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps, and fire suppression systems;

(3)

Coordination calculations and/or justifications that verify fuse/breaker coordination for

selected fire zones/areas (to be determined during information gathering visit) that are

fed off of the same electrical buses as components in the protected safe shutdown train;

(4)

List of maintenance procedures which routinely verify fuse breaker coordination in

accordance with the post-fire safe shutdown coordination analysis;

(5)

List of procedures/instructions that control the configuration of the reactor plant's fire

protection program, features, and post-fire safe shutdown methodology and system

design;

(6)

List of procedures/instructions that govern the implementation of plant modifications,

maintenance, and special operations, and their impact on fire protection;

(7)

List of significant fire protection and post-fire safe shutdown related design change

package descriptions (including their associated 10 CFR 50.59 evaluations) and Generic Letter (GL) 86-10 evaluations;

(8)

Gaseous suppression system pre-operational testing, if applicable, for selected fire

zones/areas (to be determined during information gathering visit);

(9)

Hydraulic calculations and supporting test data which demonstrate operability for water

suppression systems, if applicable, for selected fire zones/areas (to be determined

during information gathering visit);

(10)

Piping and instrumentation diagram for fire suppression systems, if applicable, for

selected fire zones/areas (to be determined during information gathering visit);

INITIAL DOCUMENT REQUEST

Enclosure

4

(11)

Isometric piping diagrams, if applicable, for piping associated with fire suppression

systems for selected fire zones/areas (to be determined during information gathering

visit);

(12)

Drawings showing the location of fire detectors, if applicable, for selected fire

zones/areas (to be determined during information gathering visit);

(13)

Structural drawings showing the location of structural members (e.g., beams) for the

floor above selected fire zones/areas (to be determined during information gathering

visit);

(14)

Ventilation flow diagrams, if applicable, for selected fire zones/areas (to be determined

during information gathering visit);

(15)

Alternating current (AC) coordination calculations for 4160 Vac down to 480 Vac

electrical systems;

(16)

The three most recent fire protection Quality Assurance (QA) audits and/or fire

protection self-assessments; and

(17)

Corrective action documents (e.g., condition reports, including status of corrective

actions) generated as a result of the three most recent fire protection Quality Assurance

(QA) audits and/or fire protection self-assessments.

Information Requested to Be Provided Throughout the Inspection

(1)

Copies of any corrective action documents generated as a result of the teams questions

or queries during this inspection; and

(2)

Copies of the list of questions submitted by the team members and the status/resolution

of the information requested (provide daily during the inspection to each team member).