Jeffrey B. Archie Vice President, Nuclear Operations 803.345.4214 A SCANA COMPANY July 13, 2005 Document Control Desk U. S. Nuclear Regulatory Commission Washington, DC 20555 Attention: Director, Office of Resource Management
Dear Sir / Madam:
Subject:
VIRGIL C. SUMMER NUCLEAR STATION DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 JUNE MONTHLY OPERATING REPORT Enclosed is the June 2005 Monthly Operating Report for the Virgil C. Summer Nuclear Station Unit No. 1.
This submittal is made in accordance with the requirements of Technical Specifications, Section 6.9.1.10.
If there are any questions, please call me at your convenience.
Very truly yours, y B Ar JBA/mbb Attachment c:
T. D. Gatlin T. G. Eppink (w/o Attachment)
R. J. White W. D. Travers R. E. Martin G. A. Lippard NRC Resident Inspector Morgan Lewis Paulette Ledbetter W. R. Higgins S. A. Byrne INPO Records Center J&H Marsh & McLennan William G. Wendland (ANI)
Pat Haught (Westinghouse)
C. W. Adams NSRC CER (0-L-99-0350-1)
File (818.03-1, RR 4100)
DMS (RC-05-0102) el SCE&G I Virgil C. Summer Nudear Station
- P. 0. Box 88. Jenkinsville, South Corolina 29065
- T (803) 345.5209. ww.scanox.om
Director, Office of Resource Management June Monthly Operating Report RC-05-01 02 Page 1 of 4 ATTACHMENT I AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE DAY 1
2 3
4 5
6 7
8 9
10 11 12 13 14 15 16 June 2005 AVERAGE DAILY POWER LEVEL DAY (Mwe-Net) 0 17 158 18 381 19 677 20 915 21 967 22 980 23 981 24 980 25 979 26 980 27 982 28 981 29 981 30 981 980 50/395 V. C. SUMMER I July 6, 2005 T. V. Dao (803) 345-4812 AVERAGE DAILY POWER LEVEL (Mwe-Net) 980 981 981 980 982 982 980 980 980 980 980 980 979 980
Director, Office of Resource Management June Monthly Operating Report RC-05-01 02 Page 2 of 4 ATTACHMENT II OPERATING DATA REPORT DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I July 6, 2005 T. V. Dao (803) 3454812 OPERATING STATUS 1
Reporting Period:
Gross Hours in Reporting Period:
2 Currently Authorized Power Level (MWt):
Max. Depend. Capacity (MWe-Net):
Design Electrical Rating (MWe-Net):
3 Power Level to Which Restricted (If Any) (MWe-Net):
4 Reasons for Restrictions:
June 2005 720 2900 966 972.7 N/A N/A THIS MONTH YR TO DATE CUMULATIVE 5
Number of Hours Reactor Critical 6
Reactor Reserve Shutdown Hours 7
Hours Generator On Line 8
Unit Reserve Shutdown Hours 9
Gross Thermal Energy Generated (MWH) 10 Gross Electrical Energy (MWH) 11 Net Electrical Energy Generated (MWH) 12 Reactor Service Factor 13 Reactor Availability Factor 14 Unit Service Factor 15 Unit Availability Factor 16 Unit Capacity Factor (Using MDC) 17 Unit Capacity Factor (Using Design) 18 Unit Forced Outage Rate 720.0 0.0 696.6 0.0 1897967 666360 639101 100.0 100.0 96.8 96.8 91.9 91.3 0.0 3413.3 0.0 3383.7 0.0 9626003 3401030 3267081 78.6 78.6 77.9 77.9 77.9 77.3 0.0 158723.9 0.0 156633.5 0.0 426564168 144854219 138513210 84.2 84.2 83.1 83.1 80.4 79.3 3.0 19 Shutdowns Scheduled Over Next 6 Months (Type, Date, & Duration of Each):
N/A 20 If Shutdown at End of Report Period, Estimated Date of Startup:
N/A 21 Units in Test Status (Prior to Commercial Operation):
N/A
Director, Office of Resource Management June Monthly Operating Report RC-05-01 02 Page 3 of 4 ATTACHMENT IlIl UNIT SHUTDOWNS AND POWER REDUCTION DOCKET NO.
50/395 UNIT V. C. SUMMER I DATE July 6, 2005 COMPLETED BY T. V. Dao TELEPHONE (803) 345-4812 June 2005 NO.
DATE TYPE DURATION REASON METHOD CORRECTIVE ACTION/COMMENTS 2
4/23/2005 S
22.2 C
4 Completed Refueling 15 3
06/212005 S
1.2 B
9 Turbine Overspeed Trip Test 1
REASON A: Equipment Failure B: Maintenance or Test C: Refueling D: Regulatory Restriction E: Operator Training and License Examination F: Administrative G: Operational Error H: Other (Explain) 2 METHOD 1: Manual 2: Manual Trip/Scram 3: Automatic Trip/Scram 4: Continuation (Use Initial Date) 5: Power Reduction (Duration 0.0) 9: Other (Explain)
SUMMARY
Director, Office of Resource Management June Monthly Operating Report RC-05-01 02 Page 4 of 4 ATTACHMENT IV NARRATIVE
SUMMARY
OF OPERATING EXPERIENCE DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50/395 V. C. SUMMER I July 6, 2005 T. V. Dao (803) 345-4812 June 2005 The unit returned to service at 22:13 on 06/01/2005 following completion of Refueling Outage 15. Turbine overspeed testing was performed at 02:30 on 06/02/2005 and ended at 03:41 on 06/02/2005.