July 14, 2005 Mr. David A. Christian, Sr. Vice President and Chief Nuclear Officer Dominion Resources 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

REQUALIFICATION PROGRAM INSPECTION - MILLSTONE POWER STATION

Dear Mr. Christian:

In a telephone conversation on June 30, 2005, Mr. Tim Kulterman, Supervisor of LORT, and Mr. Joseph DAntonio, made arrangements for the U. S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Millstone Power Station, Unit 3 facility. The inspection is planned for the week of August 28, 2005, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.

In accordance with 10 CFR 55.59, the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past two years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past two years on simulator performance problems; 3) an index or summary of simulator performance test results in the past two years; and 4) the examination schedule, sample plan, written examinations and operating test scheduled for the week of the inspection to the NRC by the week of August 15, 2005. Mr. Kulterman has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2006.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, D.C. 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV ; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0101), Office of Management and Budget, Washington, D.C. 20503-0001.

Mr. David A. Christian The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).

Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. Joseph DAntonio at (610) 337-5085.

Sincerely,

/RA/

Richard J. Conte, Chief Operations Branch Division of Reactor Safety Docket Nos.

50-336; 50-423 License Nos. DPR-65, NPF-49 cc w/encl:

J. A. Price, Site Vice President, Millstone Station C. L. Funderburk, Director, Nuclear Licensing and Operations Support D. W. Dodson, Supervisor, Station Licensing L. M. Cuoco, Senior Counsel C. Brinkman, Manager, Washington Nuclear Operations J. Roy, Director of Operations, Massachusetts Municipal Wholesale Electric Company First Selectmen, Town of Waterford R. Rubinstein, Waterford Library J. Markowicz, Co-Chair, NEAC E. Woollacott, Co-Chair, NEAC E. Wilds, Director, State of Connecticut SLO Designee J. Buckingham, Department of Public Utility Control G. Proios, Suffolk County Planning Dept.

R. Shadis, New England Coalition Staff G. Winslow, Citizens Regulatory Commission (CRC)

S. Comley, We The People D. Katz, Citizens Awareness Network (CAN)

R. Bassilakis, CAN J. M. Block, Attorney, CAN P. Eddy, Electric Division, Department of Public Service, State of New York P. Smith, President, New York State Energy Research and Development Authority J. Spath, SLO Designee, New York State Energy Research and Development Authority M. J. Wilson, Manager - Nuclear Training

Mr. David A. Christian Distribution: VIA E-MAIL:

Region I Docket Room (with concurrences)

S. Collins, RA A. Blough, DRS R. Crlenjak, DRS R. Conte, DRS J. DAntonio, DRS Examiner C. Bixler, DRS S. Lee, RI OEDO D. Roberts, NRR V. Nerses, NRR G. Wunder, NRR S. Schneider, Senior Resident Inspector E. Bartels, Resident OA P. Krohn, RI S. Barber, RI T. Madden, OCA L. Vick, HOHB, NRR DOCUMENT NAME: E:\\Filenet\\ML051960003.wpd ADAMS PKG: ML051870448 SISP Review Complete: RJC After declaring this document An Official Agency Record it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CJBixler/CJB JDAntonio/RJC for RJConte/RJC DATE 07/14/05 07/14/05 07/14/05 OFFICIAL RECORD COPY