7/27/05, Point Beach Nuclear Power Plant, Units 1 and 2 - Response to Generic Letter 2004-01, Requirements for Steam Generator Tube Inspections
ML051940594
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 07/27/2005
From: Chernoff H
NRC/NRR/DLPM/LPD3
To: Koehl D
Nuclear Management Co
Chernoff, H, NRR/DLPM, 301-415-4018
References
TAC MC4840, TAC MC4841
Download: ML051940594 (3)


Text

July 27, 2005 Dennis Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - RESPONSE TO GENERIC LETTER 2004-01, REQUIREMENTS FOR STEAM GENERATOR TUBE INSPECTIONS (TAC NOS. MC4840 AND MC4841)

On August 30, 2004, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2004-01, Requirements For Steam Generator Tube Inspections. The purpose of GL 2004-01 was to obtain information that would enable the NRC staff to determine whether licensees steam generator (SG) tube inspection programs comply with the existing tube inspection requirements (the plant technical specifications in conjunction with Appendix B to Title 10 of the Code of Federal Regulations (10 CFR) Part 50 Appendix B).

By letter dated October 29, 2004, Nuclear Management Company, LLC, responded to GL 2004-01 for Point Beach Nuclear Plant (PBNP), Units 1 and 2. The NRC staffs review of your response to the GL 2004-01 did not identify any concerns with the inspection practices employed at PBNP, Units 1 and 2. The NRC staff, therefore, concludes that your SG tube inspection practices are in compliance with the existing tube inspection requirements.

If you have any questions regarding this matter, please contact Harold Chernoff, at (301) 415-4018.

Sincerely,

/RA/

Deirdre W. Spaulding, Project Manager Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: See next page

July 27, 2005 Dennis Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - RESPONSE TO GENERIC LETTER 2004-01, REQUIREMENTS FOR STEAM GENERATOR TUBE INSPECTIONS (TAC NOS. MC4840 AND MC4841)

On August 30, 2004, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2004-01, Requirements For Steam Generator Tube Inspections. The purpose of GL 2004-01 was to obtain information that would enable the NRC staff to determine whether licensees steam generator (SG) tube inspection programs comply with the existing tube inspection requirements (the plant technical specifications in conjunction with Appendix B to Title 10 of the Code of Federal Regulations (10 CFR) Part 50 Appendix B).

By letter dated October 29, 2004, Nuclear Management Company, LLC, responded to GL 2004-01 for Point Beach Nuclear Plant (PBNP), Units 1 and 2. The NRC staffs review of your response to the GL 2004-01 did not identify any concerns with the inspection practices employed at PBNP, Units 1 and 2. The NRC staff, therefore, concludes that your SG tube inspection practices are in compliance with the existing tube inspection requirements.

If you have any questions regarding this matter, please contact Harold Chernoff, at (301) 415-4018.

Sincerely,

/RA/

Deirdre W. Spaulding, Project Manager Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301 cc: See next page DISTRIBUTION:

PUBLIC DSpaulding Rgn III PKlein MBanerjee PDIII-1 R/F HChernoff ACRS MYouder DLPM DPR LRaghavan DClarke OGC JTerrell ADAMS ACCESSION No.: ML051940594 OFFICE PDIII-1/PM PDIII-1/LA PDIII-1/SC NAME DSpaulding THarris for DClarke LRaghavan DATE 07/26/05 07/26/05 07/27/05 OFFICIAL RECORD COPY

Point Beach Nuclear Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. F. D. Kuester President & Chief Executive Officer WE Generation 231 West Michigan Street Milwaukee, WI 53201 Regulatory Affairs Manager Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Site Director of Operations Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241