Facsimile Transmission, Draft Request for Additional Information
ML051880008
Person / Time
Site: Millstone Dominion icon.png
Issue date: 07/07/2005
From: Nerses V
NRC/NRR/DLPM/LPD1
To: Darrell Roberts
NRC/NRR/DLPM/LPD1
Nerses V, NRR//DLPM, 415-1484
References
TAC MC6257
Download: ML051880008 (3)


Text

July 7, 2005 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Senior Project Manager, Section 2 /RA/

Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 2, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MC6257)

The attached draft request for additional information (RAI) was transmitted by facsimile on July 7, 2005, to Mr. Paul Willoughby, Dominion Nuclear Connecticut, Inc. (DNC). This draft RAI was transmitted to facilitate the technical review being conducted by the NRC staff and to support a conference call with DNC in order to clarify certain items in the licensees submittal.

This draft RAI is related to DNCs submittal dated February 25, 2005, regarding a request to modify the Technical Specification surveillance requirement for trisodium phosphate. Review of the RAI would allow DNC to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.

Docket No. 50-336

Enclosure:

Draft Request for Additional Information

July 7, 2005 MEMORANDUM TO: Darrell J. Roberts, Chief, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Victor Nerses, Senior Project Manager, Section 2 /RA/

Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation

SUBJECT:

MILLSTONE POWER STATION, UNIT NO. 2, FACSIMILE TRANSMISSION, DRAFT REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MC6257)

The attached draft request for additional information (RAI) was transmitted by facsimile on July 7, 2005, to Mr. Paul Willoughby, Dominion Nuclear Connecticut, Inc. (DNC). This draft RAI was transmitted to facilitate the technical review being conducted by the NRC staff and to support a conference call with DNC in order to clarify certain items in the licensees submittal.

This draft RAI is related to DNCs submittal dated February 25, 2005, regarding a request to modify the Technical Specification surveillance requirement for trisodium phosphate. Review of the RAI would allow DNC to determine and agree upon a schedule to respond to the RAI. This memorandum and the attachment do not convey a formal request for information or represent an NRC staff position.

Docket No. 50-336

Enclosure:

Draft Request for Additional Information DISTRIBUTION PUBLIC DRoberts PKrohn, REGII PDI-2 Reading VNerses LLund YDiaz ACCESSION NO.: ML051880008 OFFICE PDI-2/PM EMCB/SC PDI-2/SC NAME VNerses LLund DRoberts DATE 7/7/05 6/23/05 7/7/05 OFFICIAL RECORD COPY

DRAFT REQUEST FOR ADDITIONAL INFORMATION MILLSTONE POWER STATION, UNIT NO. 2 DOCKET NO. 50-336 By letter dated February 25, 2005, Dominion Nuclear Connecticut, Inc. (DNC) submitted a request to modify the Technical Specification surveillance requirement for trisodium phosphate (TSP). The NRC has developed the following draft question during its review of the DNC letter:

In page 4 of the February 25, 2005 submittal, DNC stated: Past testing on compacted TSP indicates that even if the TSP crystals become compressed and partially fused together, rapid dissolution is still assured. Please justify your statement and provide more specific information on how you arrived at your results.