CGS-05-2005 - Draft - Outline Comments
ML051780431
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/27/2005
From: Gody A
Operations Branch IV
To: Parrish J
Energy Northwest
References
50-397/05-301, CGS-05-2005 50-397/05-301
Download: ML051780431 (1)


Text

CGS May 2005 Re-Take Exam Outline Review Comments

1. There needs to be a backup scenario included for review and validation.
2. ES-D-1 did not indicate whether the scenarios were new, bank, or modified.
3. Should Event-1 of Scenario-1 and Scenario-2 be counted as a reactivity event?
4. Were there more KAs that were eliminated prior to random outline development than the several Systems & E/APEs identified on the ES401-1? Facility provided complete listing and justification of KAs eliminated prior to outline development; the Chief examiner reviewed and concurred with the eliminated KAs.

NOTE: Initially, the draft included a written exam for two SROI re-takes and the simulator portion of the operating exam for one RO re-take; subsequent to draft outline submittal, the utility decided not to put the RO up for the simulator re-take, so comments directed at the simulator portion of the outline are no longer relevant to this re-take exam.