MONTHYEARBVY 24-005, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-30030 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-004, Report of Investigation Pursuant to 10 CFR 20, Appendix G2024-01-23023 January 2024 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 24-003, Nuclear Onsite Property Damage Insurance2024-01-0404 January 2024 Nuclear Onsite Property Damage Insurance BVY 24-001, Pre-Notice of Disbursement from Decommissioning Trust2024-01-0202 January 2024 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-030, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-12-20020 December 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-029, Proof of Financial Protection2023-12-12012 December 2023 Proof of Financial Protection BVY 23-028, Pre-Notice of Disbursement from Decommissioning Trust2023-11-28028 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-027, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-21021 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-026, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-11-13013 November 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-025, Pre-Notice of Disbursement from Decommissioning Trust2023-11-0202 November 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 3172023-10-10010 October 2023 License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 IR 07200059/20234012023-10-0505 October 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200059/2023401 BVY 23-022, Pre-Notice of Disbursement from Decommissioning Trust2023-08-23023 August 2023 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20230012023-08-15015 August 2023 Northstar Nuclear Decommissioning Company, Llc., Vermont Yankee Nuclear Power Station, - NRC Inspection Report 05000271/2023001 BVY 23-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-08-0202 August 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-020, Pre-Notice of Disbursement from Decommissioning Trust2023-08-0202 August 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-019, Update to 2022 Radiological Effluent Release Report2023-07-24024 July 2023 Update to 2022 Radiological Effluent Release Report BVY 23-018, Update to Nuclear Onsite Property Damage Insurance2023-07-12012 July 2023 Update to Nuclear Onsite Property Damage Insurance BVY 23-017, Pre-Notice of Disbursement from Decommissioning Trust2023-06-29029 June 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-015, Report of Investigation Pursuant to 1O CFR 20, Appendix G2023-06-0505 June 2023 Report of Investigation Pursuant to 1O CFR 20, Appendix G BVY 23-016, 10 CFR 72.48 Report2023-06-0505 June 2023 10 CFR 72.48 Report BVY 23-014, Pre-Notice of Disbursement from Decommissioning Trust2023-05-31031 May 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-013, 2022 Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Radiological Environmental Operating Report BVY 23-011, 2022 Radiological Effluent Release Report2023-05-10010 May 2023 2022 Radiological Effluent Release Report BVY 23-012, Pre-Notice of Disbursement from Decommissioning Trust2023-05-0202 May 2023 Pre-Notice of Disbursement from Decommissioning Trust ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment BVY 23-009, 2022 Individual Monitoring NRC Form 5 Report2023-04-24024 April 2023 2022 Individual Monitoring NRC Form 5 Report BVY 23-008, Pre-Notice of Disbursement from Decommissioning Trust2023-04-0606 April 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 23-007, Report of Investigation Pursuant to 10 CFR 20, Appendix G2023-03-29029 March 2023 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 23-006, Status of Decommissioning and Spent Fuel Management Fund for Year Ending 20222023-03-29029 March 2023 Status of Decommissioning and Spent Fuel Management Fund for Year Ending 2022 BVY 23-005, Nuclear Onsite Property Damage Insurance2023-03-13013 March 2023 Nuclear Onsite Property Damage Insurance BVY 23-004, Pre-Notice of Disbursement from Decommissioning Trust2023-03-0202 March 2023 Pre-Notice of Disbursement from Decommissioning Trust ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities IR 05000271/20220022023-02-22022 February 2023 Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station - NRC Inspection Report No. 05000271/2022002 BVY 23-003, Pre-Notice of Disbursement from Decommissioning Trust2023-01-31031 January 2023 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-030, Documentary Evidence of Performance Bond2022-12-30030 December 2022 Documentary Evidence of Performance Bond ML22347A2792022-12-21021 December 2022 Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 05000271/20224012022-12-15015 December 2022 NRC Inspection Report No. 05000271/2022401, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont (Letter Only) BVY 22-028, Re Proof of Financial Protection2022-11-28028 November 2022 Re Proof of Financial Protection BVY 22-027, Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station2022-11-11011 November 2022 Bvy 22-027; Pre-Notice of Disbursement from Decommissioning Trust for Vermont Yankee Nuclear Power Station BVY 22-026, Pre-Notice of Disbursement from Decommissioning Trust2022-10-31031 October 2022 Pre-Notice of Disbursement from Decommissioning Trust ML22273A1492022-10-0404 October 2022 Review of Decommissioning Funding Status 2022 BVY 22-025, Pre-Notice of Disbursement from Decommissioning Trust2022-10-0404 October 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-023, Pre-Notice of Disbursement from Decommissioning Trust2022-09-0101 September 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-022, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-22022 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-021, Report of Investigation Pursuant to 10 CFR 20, Appendix G2022-08-16016 August 2022 Report of Investigation Pursuant to 10 CFR 20, Appendix G BVY 22-020, Pre-Notice of Disbursement from Decommissioning Trust2022-08-0101 August 2022 Pre-Notice of Disbursement from Decommissioning Trust IR 05000271/20220012022-08-0101 August 2022 NRC Inspection Report No. 05000271/2022001, Northstar Nuclear Decommissioning Company, LLC, Vermont Yankee Nuclear Power Station, Vernon, Vermont BVY 22-019, Pre-Notice of Disbursement from Decommissioning Trust2022-07-0606 July 2022 Pre-Notice of Disbursement from Decommissioning Trust BVY 22-013, Notification of Revised Decommissioning Cost Estimate2022-06-17017 June 2022 Notification of Revised Decommissioning Cost Estimate 2024-01-04
[Table view] |
Text
June 27, 2005 Mr. Ed Anthes Nuclear Free Vermont by 2012 P.O. Box 6325 Brattleboro, VT 05302
Dear Mr. Anthes,
I am responding to your email dated March 14, 2005, regarding your concerns about Vermont Yankees emergency notification system.
Federal oversight of radiological emergency planning at Vermont Yankee is shared by the NRC and the Federal Emergency Management Agency (FEMA). FEMA assesses off-site emergency planning and response, including the primary and backup off-site emergency notification system, and assists state and local governments. The NRC assesses Entergys on-site emergency planning and response. The NRC also conducts inspections on aspects of the primary emergency notification system. FEMA provides to the NRC the results of its assessment regarding the adequacy and capability of implementing the off-site plan. FEMAs assessment, information regarding emergency preparedness performance indicators, and NRC inspection findings in the emergency preparedness area are used by the NRC to make a determination on the overall state of radiological emergency preparedness.
Each commercial United States nuclear power reactor plant, including the Vermont Yankee Nuclear Power Station, has an emergency plan to assure that adequate measures are taken on-site and off-site to protect the public in the event of a radiological emergency. An element of the plan requires that each plant have a primary and backup off-site emergency notification system to notify the public of a radiological emergency. Federal regulations require that Vermont Yankees primary off-site emergency notification system be able to essentially complete within about 15 minutes the initial notification of the public who are within the 10-mile emergency planning zone. In 1996 FEMA accepted Vermont Yankees plan to use sirens and, for those locations in which sirens were not effective, to use tone alert radios as the primary emergency notification system. It is important to note that the purpose of the sirens and tone alert radios is to alert the public to turn on their radio or television to the Emergency Broadcast System and listen for directions on how to respond to the radiological emergency.
In a letter dated February 2, 2005, as a result of an NRC inspection (Inspection Report 05000271/2004009), the NRC issued a Notice of Violation to Entergy because some members of the public who were in a location in the10-mile emergency planning zone that used tone alert radios did not have tone alert radios. Since that NRC inspection, Entergy has been working with the local emergency management directors and has provided tone alert radios to the affected portion of the public. In May 2005, Entergy notified the Vermont Emergency Management Agency that it had completed actions related to the tone alert radios. We have recently completed a review of Entergys corrective actions to our Notice of Violation. We were satisfied with Entergys corrective actions and will document this review in an upcoming inspection report.
2 We believe that since Entergy has completed its corrective actions, the primary off-site emergency notification system around Vermont Yankee is in compliance with the federal regulations and is able to essentially complete within about 15 minutes the initial notification of the public who are within the 10-mile emergency planning zone. Notwithstanding, Entergy has indicated to us that it plans to make enhancements to the off-site emergency notification system to upgrade the sirens by June 30, 2005, and to implement an automated telephone notification system at some later date.
In May 2005, Entergy and state and local emergency responders in Vermont, New Hampshire, and Massachusetts conducted an exercise in response to a simulated radiological emergency at Vermont Yankee. The NRC evaluated on-site emergency response and FEMA evaluated off-site emergency response. In letters to the States of Vermont and New Hampshire and the Commonwealth of Massachusetts, dated June 6, 2005, FEMA identified a total of seven deficiencies in the off-site response. Two deficiencies involved process delays by the off-site authorities associated with actuation of the primary off-site notification system and three involved the time to complete the backup emergency notification. None of the deficiencies related to the operability of the emergency notification equipment. FEMA requested that these deficiencies be corrected within 120 days. FEMA has informed the NRC that New Hampshire and Massachusetts have corrected the deficiencies associated with completing the backup emergency notification. The five deficiencies associated with the off-site response in Vermont are in the process of being corrected. The NRC sent a letter to Entergy dated June 15, 2005, transmitting a copy of the letters that FEMA sent to the states. The NRC will monitor Entergys efforts to work with the state and local authorities to correct the deficiencies.
A copy of the letter sent to Entergy, along with the FEMA letters sent to the three states, is available electronically from the Publicly Available Records (PARS) component of the NRC's document system (ADAMS) (Accession Number ml051660320). ADAMS is accessible from the NRC Web site at: http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
I hope that this letter has been responsive to your email. Please be aware that the NRC does have a process in place by which any member of the public can request an enforcement action or to modify a regulation. You can obtain information about these processes at the NRC Web site at: http://www.nrc.gov/public-involve.html If you have any further questions on this response, please contact me at 610-337-5227.
Sincerely
/RA/
Clifford J. Anderson, Chief Projects Branch 5 Division of Reactor Projects
3 Distribution w/encl: (via E-mail)
S. Collins, RA J. Wiggins, DRA C. Anderson, DRP D. Florek, DRP S. Lee, RI OEDO D. Roberts, NRR R. Ennis, PM, NRR D. Pelton, DRP, Senior Resident Inspector DOCUMENT NAME: E:\Filenet\ML051780400.wpd SISP Review Complete: RKL (Reviewers Initials)
After declaring this document An Official Agency Record it will/will not be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRS RI/DRP NAME DFlorekDJF1 RLorson/RKL CAnderson/CJA DATE 06/24/05 06/24/05 06/27/05 OFFICIAL RECORD COPY