ML051720466
| ML051720466 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 06/13/2005 |
| From: | Jones T Florida Power & Light Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| GL-97-002, L-2005-133 | |
| Download: ML051720466 (3) | |
Text
-
FPL JUN 1 3 2005 L-2005-133 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:
Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - May 2005 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the May 2005 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.
Very truly yours, Terry 0. Jones Vice President Turkey Point Plant RLE Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.
I-aq an FPL Group company
N' DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
Reporting Period May, 2005 50-250 Turkey Point Unit 3 6/2/2005 Ronald Everett (305) 246-6190 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 ft..R Maximum Dependable Capacity (MWe-Net) 693,
Month Year-to-date Cumulative No. of hours reactor was critical 744 3530 213143.7 No. of hours generator was on line (service hours) 744 3462.4 210538.2 Unit reserve shutdown hours 0
0 121.8 Net Electrical Energy (MWH) 530494 2443436 137982101 UNIT SHUTDOWNS No.
Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours)
(1)
Shutting S=Scheduled Down (2)
N/A N/A N/A N/A N/A N/A (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/Ucense Examination F - Administrative G -Operational Error (Explain)
H -Other 1 - Manual 2 - Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
Summary Of Monthly Operatina Experience Unit 3 operated at essentially 100% power for the month of May.
DOCKET NO.:
UNIT:
DATE:
COMPLETED BY:
TELEPHONE:
50-251 Turkey Point Unit 4 6/2/2005 Ronald Everett (305) 246-6190 Reporting Period: May, 2005 Design Electrical Rating (MWe-Net) 720
¢
-M Maximum Dependable Capacity (MWe-Net) 693 ;
Month Year-to-date Cumulative No. of hours reactor was critical 0
2345.2 210486.4 No. of hours generator was on line (service hours) 0 2330.6 205971.9 Unit reserve shutdown hours 0
0 577.2 Net Electrical Energy (MWH) 0 1549244 136149995 UNIT SHUTDOWNS No.
Date Type Duration Reason Method of Corrective Actionl Comments F=Forced (hours)
(1)
Shutting S=Scheduled Down (2) 20050021 05/01/2005 S
744 C
1 Refueling Outage Cycle 22 Started 4/10/05 (1) Reason (2) Method A - Equipment Failure (Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/Ucense Examination F - Administrative G - Operational Error (Explain)
H - Other 1 - Manual 2-Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)
Summary Of Monthly Operating Experience Unit 4 has been shut down for a scheduled refueling outage since April 10'h, 2005, and was down the entire month of May, 2005 for the Cycle 22 refueling outage.