Dominion Nucear Connecticut, Inc.
Millstone Power Station Rope Ferry Road Waterford, CT 06385 ArDominion June 8, 2005 SAFEGUARDS INFORMATION United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D. C. 20555-0001 Serial No NL&OS/DWD Docket Nos.05-304 R4 50-336 50-423 License Nos. DPR-65 NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION UNITS 2 AND 3 RESPONSE TO NRC INSPECTION REPORT NOS. 05000336.42312005009 Dominion Nuclear Connecticut, Inc. (DNC) has reviewed Inspection Report Nos.
05000336,423/2005009, dated May 4, 2005. DNC disagrees with the NRC's application of the Significance Determination Process in this instance, and consequently denies the Violation as stated.
The basis for denial is described in detail in Attachment 1. provides supplemental information that clarifies the inspection report.
The attached material contains Safeguards Information as defined by 10 CFR 73.21 and ts disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended.
If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.
Very truly yours, Li David A. Christian Senior Vice President - Nuclear Operations and Chief Nuclear Officer Attachments 1 and 2 (Safeguards Information)
Commitments: None l--
NOTE: THE ATTACHMENTS CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ATTACHMENTS, THIS PAGE IS "DECONTROLLED."
SAFEGUARDS INFORMATION
/
to
Seral No.05-304 Page 2 of 2 cc:
Director, Office of Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 U. S. Nuclear Regulatory Commission Region I Regional Administrator 475 Allendale Road King of Prussia, PA 19406-1415 Mr. V. Nerses (without Attachments)
NRC Senior Project Manager Millstone Unit 2 U. S. Nuclear Regulatory Commission, Mail Stop 8 C2 Washington, D. C. 20555 Mr. G. F. Wunder (without Attachments)
NRC Senior Project Manager Millstone Unit 3 U. S. Nuclear Regulatory Commission, Mail Stop 8-B-1A Washington, D. C. 20555 Mr. S. M. Schneider (without Attachments)
NRC Senior Resident Inspector Millstone Power Station