MONTHYEARML24351A2422024-12-19019 December 2024 Reactor Coolant System Alloy 600 Inspection Program for License Renewal Commitment No. 15 ML24351A2412024-12-19019 December 2024 Reactor Vessel Internals Inspections Aging Management Program Submittal Related to License Renewal Commitment No. 13 IR 05000336/20243012024-12-0606 December 2024 Initial Operator Licensing Examination Report 05000336/2024301 05000423/LER-2024-002, Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary2024-11-26026 November 2024 Door Latch Failure Resulted in Loss of Safety Function for Secondary Containment Boundary 05000336/LER-2024-002, Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications2024-11-26026 November 2024 Two Main Steam Safety Valves Failed to Lift within the Acceptance Criteria Resulting in a Condition Prohibited by Technical Specifications ML24296B2352024-11-19019 November 2024 Issuance of Amendment No. 291 License Amendment to Support the Implementation of Framatome Gaia Fuel (EPID L-2023-LLA-0150) (Non-Proprietary) ML24317A2562024-11-12012 November 2024 Core Operating Limits Report, Gycle 30 IR 05000245/20240012024-11-12012 November 2024 Safstor Inspection Report 05000245/2024001 IR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 ML24289A0152024-10-21021 October 2024 Review of the Fall 2023 Steam Generator Tube Inspection Report 05000423/LER-2024-001, Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary2024-10-14014 October 2024 Loss of Safety Function and Condition Prohibited by Technical Specifications for Loss of Secondary Containment Boundary IR 05000336/20244022024-10-0808 October 2024 Security Baseline Inspection Report 05000336/2024402 and 05000423/2024402 (Cover Letter Only) ML24281A1102024-10-0707 October 2024 Requalification Program Inspection 05000423/LER-2023-006-02, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-09-26026 September 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2192024-09-16016 September 2024 Decommissioning Trust Fund Disbursement - Revision to Previous Thirty-Day Written Notification ML24260A1952024-09-16016 September 2024 Response to Request for Additional Information Regarding Proposed Amendment to Support Implementation of Framatome Gaia Fuel ML24248A2272024-09-0404 September 2024 Operator Licensing Examination Approval ML24240A1532024-09-0303 September 2024 Summary of Regulatory Audit Supporting the Review of License Amendment Request for Implementation of Framatome Gaia Fuel IR 05000336/20240052024-08-29029 August 2024 Updated Inspection Plan for Millstone Power Station, Units 2 and 3 (Reports 05000336/2024005 and 05000423/2024005 IR 05000336/20240022024-08-13013 August 2024 Integrated Inspection Report 05000336/2024002 and 05000423/2024002 ML24221A2872024-08-0808 August 2024 Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Cask Registration for Spent Fuel Storage IR 05000336/20244412024-08-0606 August 2024 Supplemental Inspection Report 05000336/2024441 and 05000423/2024441 and Follow-Up Assessment Letter (Cover Letter Only) ML24212A0742024-08-0505 August 2024 Request for Withholding Information from Public Disclosure - Millstone Power Station, Unit No. 3, Proposed Alternative Request IR-4-13 to Support Steam Generator Channel Head Drain Modification ML24211A1712024-07-25025 July 2024 Associated Independent Spent Fuels Storage Installation, Revision to Emergency Plan - Report of Change IR 05000336/20244032024-07-22022 July 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000336/2024403 and 05000423/2024403 IR 05000336/20245012024-07-0101 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000336/2024501 and 05000423/2024501 ML24180A0932024-06-28028 June 2024 Readiness for Additional Inspection: EA-23-144 IR 05000336/20240102024-06-26026 June 2024 Biennial Problem Identification and Resolution Inspection Report 05000336/2024010 and 05000423/2024010 ML24178A2422024-06-25025 June 2024 2023 Annual Report of Emergency Core Cooling System (ECCS) Model, Changes Pursuant to the Requirements of 10 CFR 50.46 IR 05000336/20244402024-06-24024 June 2024 Final Significance Determination for Security-Related Greater than Green Finding(S) with Assessment Follow-up; IR 05000336/2024440 and 05000423/2024440 and Notice of Violation(S), NRC Investigation Rpt 1-2024-001 (Cvr Ltr Only) ML24280A0012024-06-20020 June 2024 Update to the Final Safety Analysis Report (Redacted Version) ML24177A2792024-06-20020 June 2024 Preparation and Scheduling of Operator Licensing Examinations ML24176A2622024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 ML24176A1782024-06-20020 June 2024 Update to the Final Safety Analysis Report ML24281A2072024-06-20020 June 2024 Update to the Final Safety Analysis Report, Revision 37 (Redacted Version) ML24170B0532024-06-10010 June 2024 DOM-NAF-2-P/NP-A, Revision 0.5, Reactor Core Thermal-Hydraulics Using the VIPRE-D Computer Code 05000336/LER-2024-001, Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications2024-06-10010 June 2024 Control Room Air Conditioning Unit Inoperable Due to Refrigerant Overcharge Resulting in a Condition Prohibited by Technical Specifications ML24165A1292024-06-0505 June 2024 ISFSI, 10 CFR 50.59 Annual Change Report for 2023 Annual Regulatory Commitment Change Report for 2023 ML24128A2772024-06-0404 June 2024 Issuance of Amendment No. 290 to Revise TSs for Reactor Core Safety Limits, Fuel Assemblies, and Core Operating Limits Report for Use of Framatome Gaia Fuel (EPID L-2023-LLA-0074) (Non-Proprietary) ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24109A0032024-05-21021 May 2024 Issuance of Amendment No. 289 to Revise Technical Specifications to Use Framatome Loss of Coolant Accident Evaluation Methodologies for Establishing Core Operating Limit (EPID L-2023-LLA-0065) (Non-Proprietary) ML24110A0562024-05-21021 May 2024 Exemption from the Requirements of 10 CFR Part 50, Section 50.46, and Appendix K Regarding Use of M5 Cladding Material (EPID L-2023-LLE-0013) (Letter) ML24141A2432024-05-20020 May 2024 Response to Request for Additional Information Regarding Alloy 600 Aging Management Program Submittal Related to License Renewal Commitment No. 15 05000423/LER-2023-006-01, Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-05-20020 May 2024 Pressurizer Power Operated Relief Valve Failed to Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications ML24142A0952024-05-20020 May 2024 End of Cycle 22 Steam Generator Tube Inspection Report IR 05000336/20240012024-05-14014 May 2024 Integrated Inspection Report 05000336/2024001 and 05000423/2024001 and Apparent Violation ML24123A2042024-05-0202 May 2024 Pre-Decisional Replay to EA-23-144 05000423/LER-2023-006, Pressurizer Power Operated Relief Valve Failed to Stroke Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications2024-05-0202 May 2024 Pressurizer Power Operated Relief Valve Failed to Stroke Open During Surveillance Testing Resulting in a Condition Prohibited by Technical Specifications IR 05000336/20244012024-04-30030 April 2024 Security Baseline Inspection Report 05000336/2024401 and 05000423/2024401 (Cover Letter Only) 2024-09-04
[Table view] Category:Licensee Response to Notice of Violation
MONTHYEARML17320A1212017-11-0303 November 2017 Clarification to the Reply to a Notice of Violation, EA-16-090 ML16278A6022016-09-29029 September 2016 Follow-Up to a Reply to a Notice of Violation, EA-16-090 ML16162A1702016-06-0303 June 2016 Reply to Notice of Violation; EA-16-090 ML15097A0842015-03-31031 March 2015 Reply to a Notice of Violation EA-14-126 ML14325A0602014-11-19019 November 2014 Reply to a Notice of Violation; EA-14-092 ML14209A0122014-07-24024 July 2014 Reply to a Notice of Violation ML13350A1372013-12-0909 December 2013 Reply to Notice of Violation 05000423-13-004-01 ML0516602572005-06-0808 June 2005 Response to NRC Inspection Report Nos. 05000336-05-009 and 05000423-05-009 ML0210203282002-03-28028 March 2002 Response to Apparent Violations in Inspection Report No.05000245/2001013 2017-11-03
[Table view] |
Text
Dominion Nucear Connecticut, Inc.
Millstone Power Station ArDominion Rope Ferry Road Waterford, CT 06385 June 8, 2005 SAFEGUARDS INFORMATION United States Nuclear Regulatory Commission Serial No 05-304 Attention: Document Control Desk NL&OS/DWD R4 Washington, D. C. 20555-0001 Docket Nos. 50-336 50-423 License Nos. DPR-65 NPF-49 DOMINION NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION UNITS 2 AND 3 RESPONSE TO NRC INSPECTION REPORT NOS. 05000336.42312005009 Dominion Nuclear Connecticut, Inc. (DNC) has reviewed Inspection Report Nos.
05000336,423/2005009, dated May 4, 2005. DNC disagrees with the NRC's application of the Significance Determination Process in this instance, and consequently denies the Violation as stated. The basis for denial is described in detail in Attachment 1. provides supplemental information that clarifies the inspection report.
The attached material contains Safeguards Information as defined by 10 CFR 73.21 and ts disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended.
If you have any questions, please contact Ms. Margaret Earle at (804) 273-2768.
Very truly yours, Li David A. Christian Senior Vice President - Nuclear Operations and Chief Nuclear Officer Attachments 1 and 2 (Safeguards Information)
Commitments: None l--
NOTE: THE ATTACHMENTS CONTAIN "SAFEGUARDS INFORMATION" AND MUST BE PROTECTED ACCORDINGLY. UPON SEPARATION OF THE ATTACHMENTS, THIS PAGE IS "DECONTROLLED."
SAFEGUARDS INFORMATION /
to
Seral No.05-304 Page 2 of 2 cc: Director, Office of Enforcement U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 U. S. Nuclear Regulatory Commission Region I Regional Administrator 475 Allendale Road King of Prussia, PA 19406-1415 Mr. V. Nerses (without Attachments)
NRC Senior Project Manager Millstone Unit 2 U. S. Nuclear Regulatory Commission, Mail Stop 8 C2 Washington, D. C. 20555 Mr. G. F. Wunder (without Attachments)
NRC Senior Project Manager Millstone Unit 3 U. S. Nuclear Regulatory Commission, Mail Stop 8-B-1A Washington, D. C. 20555 Mr. S. M. Schneider (without Attachments)
NRC Senior Resident Inspector Millstone Power Station