Fermi Annual Assessment Meeting Fermi Annual Assessment Meeting Reactor Oversight Program Reactor Oversight Program -- CY 2004 CY 2004 Nuclear Regulatory Commission Nuclear Regulatory Commission -- Region III Region III Lisle, Illinois Lisle, Illinois May 25, 2005 May 25, 2005
Purpose of Todays Meeting A public forum for discussion of the licensees A public forum for discussion of the licensees performance performance NRC will address the licensee performance issues NRC will address the licensee performance issues identified in the annual assessment letter identified in the annual assessment letter Licensee will respond to the information in the letter Licensee will respond to the information in the letter and inform the NRC of new or existing programs to and inform the NRC of new or existing programs to maintain or improve their performance maintain or improve their performance
Agenda z Introduction z Review of Reactor Oversight Process z National Summary of Plant Performance z Discussion of Plant Performance Results z Licensee Response and Remarks z NRC Closing Remarks z Break z NRC available to address public questions
NRC Representatives NRC Representatives z Robert M. Lerch, Project Engineer
- (630) 829-9759 z Stephen J. Campbell, Senior Resident Inspector
- (734) 586-2798 z Timothy C. Steadham, Resident Inspector
- (734) 586-2798
Region III Organization James L. Caldwell Regional Administrator Geoffrey E. Grant Deputy Regional Administrator Mark A. Satorius Director Division of Reactor Projects Steven A. Reynolds Deputy Director Cynthia D. Pederson Director Division of Reactor Safety Roy J. Caniano Deputy Director Eric Duncan Branch Chief Regional Specialists Fermi Resident Inspectors Stephen J. Campbell Timothy C. Steadham Project Engineer Robert M. Lerch
NRC Performance Goals z Safety: Ensure protection of the public health and safety and the environment z Security: Ensure the secure use and management of radioactive materials z Openness: Ensure openness in our regulatory process z Effectiveness: Ensure that NRC actions are effective, efficient, realistic, and timely z Management: Ensure excellence in agency management to carry out the NRC strategic objective
Reactor Oversight Process Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas Safety Cornerstones Baseline Inspection Results Significance Threshold Action Matrix Significance Threshold Performance Indicator Results Regulatory Response Strategic Performance Areas
Examples of Baseline Inspections z Equipment Alignment
~92 hrs/yr z Triennial Fire Protection
~200 hrs every 3 yrs z Operator Response
~125 hrs/yr z Emergency Preparedness
~80 hrs/yr z Rad Release Controls
~100 hrs every 2 yrs z Worker Radiation Protection ~100 hrs/yr z Corrective Action Program
~200 hrs every 2 yrs z Corrective Action Case Reviews ~60 hrs/yr
Significance Threshold Performance Indicators Green:
Only Baseline Inspection White:
May increase NRC oversight Yellow:
Requires more NRC oversight Red:
Requires more NRC oversight Inspection Findings Green:
Very Low safety issue White:
Low to moderate safety issue Yellow:
Substantial safety issue Red:
High safety issue
Action Matrix Concept Licensee
Response
Regulatory
Response
Degraded Cornerstone Multiple/Rep.
Degraded Cornerstone Unacceptable Performance Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2004 Licensee Response 78 Regulatory Response 21 Degraded Cornerstone 0
Multiple/Repetitive Degraded Cornerstone 3
Unacceptable 0
Total 102*
- Davis-Besse is in IMC 0350 process
National Summary z Performance Indicator Results (at end of CY 2004)
Green 1834 White 6
Yellow 0
Red 0
z Total Inspection Findings (CY 2004)
Green 778 White 11 Yellow 0
Red 0
Fermi Assessment Results (Jan 1 - Dec 31, 2004) zRegulatory Response Column: Based on one White PI in the Mitigating Systems Cornerstone from Q3, 2003, for which Supplemental Inspection Procedure (IP) 95001 was conducted.
zAll other PIs and inspection findings were of very low safety significance (Green).
Fermi Inspection Activities (Jan 1 (Jan 1 -- Dec 31, 2004)
Dec 31, 2004) 1375 Hours of Total Baseline Inspection by Resident and Regional Inspectors.
13 Green findings in the Reactor Safety Strategic Performance Area.
November 5 to December 3, 2004 refueling outage.
Fermi Inspection Activities (Jan 1 (Jan 1 -- Dec 31, 2004)
Dec 31, 2004)
White PI - Supplemental Inspection.
Emergency Preparedness Exercise Inspection.
Biennial Maintenance Rule Inspection.
Biennial Permanent Plant Modifications and 10 CFR 50.59 Inspection.
Inservice Inspection and Radiation Protection Inspection performed during refueling outage.
Safety Significant Findings or PIs zzAll inputs in the 2004 assessment period All inputs in the 2004 assessment period were Green with the exception of the one were Green with the exception of the one White PI from 2003.
White PI from 2003.
Cross-Cutting Issue z In the letter dated March 2, 2005, the NRC identified a substantive cross-cutting issue in the area of human performance.
z This finding is based in part on 7 Green findings during the assessment period that exhibited a common theme of failure to follow procedures and personnel errors.
Cross-Cutting Issue z Reduction in the number, significance, and common causality is needed to resolve this issue.
z NRC will monitor plant performance in this area through the baseline inspection program and evaluate the results in our semi-annual trend review at the mid-cycle assessment point.
Fermi Annual Assessment Summary January 1 - December 31, 2004 z Detroit Edison operated Fermi in a manner that preserved public health and safety.
z NRC plans baseline inspections at Fermi for calendar year 2005.
Licensee Response and Remarks William O'Connor, Jr.
Vice President Nuclear Generation Fermi Power Plant