April 2005 Monthly Operating Report for Turkey Point Units 3 and 4
ML051440300
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 05/16/2005
From: Jones T
Florida Power & Light Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-2005-118
Download: ML051440300 (3)


Text

-

Z FPL MAY 1 6 2005 L-2005-1 18 10 CFR 50.36 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Re:

Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Monthly Operating Report - April 2005 In accordance with the requirements of Turkey Point Units 3 and 4 Technical Specification 6.9.1.5, and the guidance of Generic Letter 97-02, attached are the April 2005 Operating Data Reports and Summaries of Operating Experience for Turkey Point Units 3 and 4.

Very truly yours, Terry O.Jo s

Vice President Turkey Point Plant RLE Attachments NRC Regulatory Issue Summary 2001-05 waived the requirements that multiple copies of documents be submitted to the NRC.

an FPL Group company

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

Reporting Period April, 2005 50-250 Turkey Point Unit 3 5/12/2005 Ronald Everett (305) 246-6190 OPERATING DATA REPORT Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693

-- -;:m:.:- M Month Year-to-date Cumulative No. of hours reactor was critical 719 2786 212399.7 No. of hours generator was on line (service hours) 719 2718.4 209794.2 Unit reserve shutdown hours 0

0 121.8 Net Electrical Energy (MWH) 519582 1912942 137451607 UNIT SHUTDOWNS (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F -Administrative G -Operational Error (Explain)

H -Other 1 - Manual 2 - Manual Trip/Scram 3 -Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 3 operated at essentially 100% power for the month of April.

DOCKET NO.:

UNIT:

DATE:

COMPLETED BY:

TELEPHONE:

50-251 Turkey Point Unit 4 5/12/2005 Ronald Everett (305) 246-6190 Reporting Period April, 2005 Design Electrical Rating (MWe-Net) 720 Maximum Dependable Capacity (MWe-Net) 693 Month Year-to-date Cumulative No. of hours reactor was critical 226.9 2345.2 210486.4 No. of hours generator was on line (service hours) 226.9 2330.6 205971.9 Unit reserve shutdown hours 0

0 577.2 Net Electrical Energy (MWH) 93209 1549244 136149995 UNIT SHUTDOWNS No.

Date Type Duration Reason Method of Corrective Action/ Comments F=Forced (hours)

(1)

Shutting S=Scheduled Down (2) 20050018 04/10/2005 S

492.1 C

1 Refueling Outage Cycle 22 (1) Reason (2) Method A - Equipment Failure (Explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training/License Examination F - Administrative G - Operational Error (Explain)

H - Other 1 - Manual 2-Manual Trip/Scram 3 - Automatic Trip/Scram 4 - Continuation 5 - Other (Explain)

Summary Of Monthly Operating Experience Unit 4 operated at essentially 60% power (due to failure of the 4A Steam Generator Feed Pump Motor March 22, 2005), until April 10", 2005, when the unit was shut down for a scheduled refueling outage.