ML051400120

From kanterella
Jump to navigation Jump to search
NRC Slides for Annual Assessment Meeting with First Energy Nuclear Operating Company (Fenoc), Beaver Valley Station
ML051400120
Person / Time
Site: Beaver Valley
Issue date: 03/30/2005
From: Arthur Burritt
NRC Region 1
To:
Burritt A RGN-I/DRP/PB7/610-337-5069
Shared Package
ML050680486 List:
References
Download: ML051400120 (26)


Text

Beaver Valley Annual Assessment Meeting Reactor Oversight Program - CY 2004 Nuclear Regulatory Commission - Region I King of Prussia, PA March 30, 2005

Agenda

 Introductions

 Review of Reactor Oversight Process

 National Summary of Plant Performance

 Discussion of Plant Performance Results

 FENOC Response and Remarks

 NRC Closing Remarks

 Break

 NRC available to address public questions

Purpose of Todays Meeting

 NRC will address licensee performance as identified in our annual assessment

 FENOC will respond to our assessment and inform the NRC of new or existing programs to maintain or improve performance

 NRC comments on security, public involvement

 NRC will respond to questions from the public after the discussion with FENOC

NRC Representatives

 Arthur Burritt, Acting Branch Chief

- (610) 337-5069

 Paul Cataldo, Senior Resident Inspector

- (724) 643-2000

 Galen Smith, Resident Inspector

- (724) 643-2000

 Timothy Colburn, Senior Project Manager

- (301) 415-1402

 Ronald Bellamy, Decommissioning Branch Chief, DNMS

- (610) 337-5200

NRC Performance Goals

 Safety: Ensure protection of the public health and safety and the environment

 Security: Enhance the secure use and management of radioactive materials

 Openness: Ensure openness in our regulatory process

 Effectiveness: Ensure that NRC actions are effective, efficient, realistic and timely

 Management: Ensure excellence in agency management to carry out the NRCs strategic objective

Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response

Examples of Baseline Inspections

 Equipment Alignment ~92 hrs/yr

 Triennial Fire Protection ~200 hrs every 3 yrs

 Operator Response ~125 hrs/yr

 Emergency Preparedness ~80 hrs/yr

 Rad Release Controls ~100 hrs every 2 yrs

 Worker Radiation Protection ~100 hrs/yr

 Corrective Action Program ~250 hrs every 2 yrs

 Corrective Action Case Reviews ~60 hrs/yr

Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very Low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue

Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions

National Summary of Plant Performance Status at End of CY 2004 Licensee Response 78 Regulatory Response 21 Degraded Cornerstone 0 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total Units 102*

National Summary

Performance Indicator Results (at end of CY 2004)

< Green 1834

< White 6

< Yellow 0

< Red 0

Total Inspection Findings (CY 2004)

< Green 778

< White 11

< Yellow 0

< Red 0

Beaver Valley Assessment Results (Jan 1 - Dec 31, 2004)

 Operated safely

 Met all cornerstone objectives

 Both units in the Licensee Response Column of the Action Matrix for all four quarters of 2004

 NRC will continue to conduct baseline inspections in 2005

Beaver Valley Unit 1 & 2 Performance Indicators BV Unit 1 Inspection Findings www.nrc.gov/NRR/OVERSIGHT/ASSESS/ then click BV1

BV Unit 2 Inspection Findings www.nrc.gov/NRR/OVERSIGHT/ASSESS/ then click BV2

Beaver Valley Inspection Activities (Jan 1 - Dec 31, 2004)

 6,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> of inspection related activities

 2 resident inspectors assigned to the site

 14 regional inspections

 2 team inspections - Safety System Design Inspection and the Fire Protection Triennial Inspection

 Inspection Findings

< Eight findings of very low safety significance (Green)

BV - Examples of Inspection Findings

 Lack of test control associated with switches used to detect flooding internal at Unit 1

 Inadequate procedural adherence during the installation of scaffolding over safety-related equipment

 Turbine-driven auxiliary feedwater pump seal packing procedure not implemented properly at Unit 2

 Corrective actions to preclude repetitive failures of the Emergency Response Facility EDG were ineffective

Beaver Valley Assessment Summary (Jan 1 - Dec 31, 2004)

 Operated safely

 Preserved Public Health and Safety

 Highest Performance Category

BV Planned Inspections (Jan 1 - Dec 31, 2005)

12 regional inspector visits scheduled

1 team inspection scheduled

- Problem Identification & Resolution

FENOC Response and Remarks Beaver Valley Nuclear Power Station Units 1 & 2 First Energy Nuclear Operating Company

NRC Security Program Update

 Access Authorization Order (January 2003)

 Training Order (April 2003)

 Fatigue Order (April 2003)

 Above 3 Orders Implemented (Oct. 29, 2004)

 Changes to Site Security plans to incorporate the requirements of the orders (April 2004)

 Expanded Force-on-Force Exercises (ongoing)

 New NRC Security Baseline Inspection Program initiated (February 2004)

Ways for the Public To Become Informed

& Involved in the Regulatory Process Examples

 Participate in NRC Public Meetings

< Sign up to be on our mailing list

 Visit the NRC website on a regular basis

 Publically comment on proposed licensing actions or file a Petition for Rulemaking

 10 CFR 2.206 petition process

 Contact the NRC via E-mail, mail or phone to address questions or areas of concern

 Participate in open NRC/industry symposiums

 Freedom of Information Act (FOIA) requests

Reference Sources

Reactor Oversight Process

< http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html

Public Electronic Reading Room

< http://www.nrc.gov/reading-rm.html

Public Document Room

< 1-800-397-4209 (Toll Free)

Public Comment & Involvement in Rulemaking

< http://ruleforum.llnl.gov/

Contacting the NRC

 Report an emergency

< (301) 816-5100 (call collect)

 Report a safety concern:

< (800) 695-7403

< Allegation@nrc.gov

 General information or questions

< www.nrc.gov

< Select What We Do for Public Affairs

Substantive Cross-Cutting Issue

 ROP relies on early identification & correction of problems before they become significant

 Issues involve (cross-cut) multiple ROP cornerstones

 Three factors must exist for the NRC to identify a cross-cutting issue:

< Multiple Green or safety significant inspection findings within in the 12 month assessment period

< Causal factors have a common theme (e.g., PI&R -

identification) as indicated by >3 findings

< NRC has concern with licensees scope of efforts or progress in addressing the cross-cutting deficiency

Example BV Unit 1 Performance Indicator