BW050042, April 2005, Eleventh Refuel Outage Steam Generator Inservice Inspection Report
| ML051370406 | |
| Person / Time | |
|---|---|
| Site: | Braidwood |
| Issue date: | 05/10/2005 |
| From: | Polson K Exelon Generation Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| BW050042 | |
| Download: ML051370406 (2) | |
Text
Exekrn.
Exelon Generation Company, LLC www.exeloncorp.come Braidwood Station Nucear 35100 South Rt 53, Suite 84 Braceville, IL 60407-9619 May 10, 2005 BW050042 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 Braidwood Station, Unit 2 Facility Operating License No. NPF 77 NRC Docket No. STN 50-457
Subject:
April 2005, Eleventh Refuel Outage Steam Generator Inservice Inspection Report In accordance with Technical Specification 5.6.9, "Steam Generator (SG) Tube Inspection Reports,' Exelon Generation Company, LLC is reporting the number of tubes plugged or repaired during the SG inservice inspection activities conducted during the Braidwood Station, Unit 2 April 2005 eleventh refueling outage. Technical Specification 5.6.9.a requires that following each inservice inspection of the SG tubes, the number of tubes plugged or repaired in each SG shall be reported to the NRC within 15 days.
The Braidwood Station, Unit 2 April 2005 eleventh refueling outage SG tube eddy current inspection scope included 100% full-length bobbin coil inspection, and 20% +PointTM inspection of the hot leg top of tubesheet region to a depth of 17 inches, of the 2A, 2B, 2C and 2D SGs.
+Pointru inspection was conducted on any bobbin coil indications classified as requiring additional diagnostic testing.
The SG tube inspections were completed on April 26, 2005. No tube sleeving was performed this outage. The Braidwood Unit 2 Steam Generator Tube Plugging Summary summarizes the inspection results during the April 2005 eleventh refueling outage and number of tubes removed from service to date by tube plugging.
- U.S. Nuclear Regulatory Commission May 10, 2005 Page 2 of 2 BRAIDWOOD UNIT 2 STEAM GENERATOR TUBE PLUGGING
SUMMARY
SG A SG B SG C SG D Total Previously Plugged 53 48 54 25 180 Plugged During April 2005 4
0 2
0 6
Refueling Outage Total 57 48 56 25 186 Please direct any questions regarding this submittal to Dale Ambler, Braidwood Assurance Manager, (815) 417-2800.
Regulatory Sincerely, Keith J. Polson Site Vice President Braidwood Station cc:
Regional Administrator-NRC Region IlIl NRC Senior Resident Inspection - Braidwood station