Public Meeting NRC Slides Byron End-of-Cycle Plant Performance AssessmentML051260278 |
Person / Time |
---|
Site: |
Byron |
---|
Issue date: |
04/19/2005 |
---|
From: |
NRC/RGN-III |
---|
To: |
|
---|
References |
---|
Download: ML051260278 (21) |
|
Similar Documents at Byron |
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML24003A1812024-01-0808 January 2024 Handout - Byron-Braidwood Core Monitoring and Support System LAR Pre-Submittal Meeting January 8,2024 ML23345A0362023-12-11011 December 2023 ATWS Uet December 11, 2023 Pre-submittal Meeting Slides ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23229A0132023-08-17017 August 2023 Relief Request for Alternative Requirements for Byron Unit 1 Reactor Pressure Vessel Inservice Inspection Intervals NRC Meeting Handout ML23229A4832023-08-17017 August 2023 RR 20-Year ISI Pre-Submittal NRC Meeting Handout ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23163A1642023-06-12012 June 2023 2022 Braidwood/Byron End-of-Cycle Meeting Presentation ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML23033A6672023-01-30030 January 2023 Public Call with Constellation January 30, 2023 (Slides) ML22159A3332022-06-0909 June 2022 Presentation Slides for Braidwood and Byron 2021 End of Cycle Meeting ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21166A3722021-06-15015 June 2021 End-of-Cycle Meeting Presentation ML20258A0302020-09-22022 September 2020 Decommissioning Licensing Action Submittal Plan for Byron and Dresden Stations Early Shutdowns ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20209A5322020-07-24024 July 2020 2019 Braidwood and Byron End-of-Cycle Presentation ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML19318F9512019-11-20020 November 2019 Presentation Slides for November 20, 2019, Pre-Application Meeting - Request for Revision to Quality Assurance Program Internal Audit Frequency ML19161A2572019-06-0404 June 2019 BWR Fleet Msv/Srv - Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19151A6602019-05-31031 May 2019 BWR Fleet Mssv/Srv Testing Frequency Relief Request NRC Pre-Application Meeting June 4, 2019 ML19022A2002019-01-23023 January 2019 Request for Use of ASME Code Case N-879 for Exelon Nuclear Power Plants ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18218A1122018-08-0808 August 2018 Reactor Pressure Vessel Head Penetration Nozzle Post Peening Follow-up Inspection Relief Requests for Byron Unit 2 and Braidwood Unit 1 ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17296A2032017-10-0303 October 2017 Accident Tolerant Fuel Lead Test Assembly Deployment ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML17132A1772017-05-25025 May 2017 LAR for Control Room Cooling at Byron and Braidwood Stations ML16334A4642016-12-0505 December 2016 Westinghouse Pre-Application Meeting: License Amendment Request to Modify Byron Station Facility Operating License in Support of the Molybdenum-99 Isotope Production Project - December 5, 2016 ML16327A3702016-11-25025 November 2016 Enclosure 3: Exelon Byron Station Design (Meeting Handout) ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML16062A4222016-03-0202 March 2016 Meeting Slides for March 7, 2016 Public Meeting to Discuss Backfit Appeal ML15342A1012015-12-0909 December 2015 TORMIS Computer Code Methodology Public Meeting Slides ML15232A6832015-08-27027 August 2015 Stations Auxiliary Feedwater System - Unit Cross-tie License Amendment Request ML15209A9722015-07-30030 July 2015 Alloy 600 PWSCC Mitigation Plan for Reactor Vessel Head Penetration Nozzles Utilizing Cavitation Peening at Byron and Braidwood ML15133A4732015-05-20020 May 2015 Digital Upgrades of the Non-Safety Related NSSS Control Systems at Byron and Braidwood Stations ML14342A8122014-12-10010 December 2014 Presentation Slides for December 10, 2014 Meeting on Alloy 600 PWSCC Mitigation for Rvh Nozzles ML14261A1112014-09-22022 September 2014 2014 NEI Fire Protection Information Forum NRC Public Slides ML14251A4852014-09-10010 September 2014 Byron/Braidwood Auxiliary Feedwater Cross-Tie ML14051A0662014-02-20020 February 2014 2/06/2014, Exelon Presentation Slides (Public Meeting with Exelon Generation Company, Nuclear Energy Industry, and Cask System Vendors to Discuss Issues with Spent Fuel Vacuum Drying Process) ML14051A0592014-02-20020 February 2014 2/06/2014, NRC Presentation Slides (Public Meeting with Exelon Generation Company, Nuclear Energy Industry, and Cask System Vendors to Discuss Issues with Spent Fuel Vacuum Drying Process) ML13275A0402013-08-20020 August 2013 License Renewal Process and Environmental Scoping Meeting Slides ML13227A3922013-08-14014 August 2013 2012 Byron End-of-Cycle Public Meeting NRC Presentation 2024-04-09
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24310A0672024-11-0505 November 2024 Constellation NRC Pre-Submittal Meeting Slides - Proposed Alternative for Reactor Vessel Closure Stud Exam Optimization ML24100A7672024-04-11011 April 2024 Meeting Slides - Preapplication with Constellation on Planned Fleet Alternative Request to Adopt OMN-2 ML24089A2612024-04-0909 April 2024 Slides - Constellation - Pre-Application Regarding Hooded Masks 4/9/2024 Meeting Slides (L-2024-LLM-0041) ML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML24003A1812024-01-0808 January 2024 Handout - Byron-Braidwood Core Monitoring and Support System LAR Pre-Submittal Meeting January 8,2024 ML23345A0362023-12-11011 December 2023 ATWS Uet December 11, 2023 Pre-submittal Meeting Slides ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23229A0132023-08-17017 August 2023 Relief Request for Alternative Requirements for Byron Unit 1 Reactor Pressure Vessel Inservice Inspection Intervals NRC Meeting Handout ML23229A1722023-08-17017 August 2023 RR Pen-75 Pre-Submittal NRC Meeting Handout ML23229A4832023-08-17017 August 2023 RR 20-Year ISI Pre-Submittal NRC Meeting Handout ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23163A1642023-06-12012 June 2023 2022 Braidwood/Byron End-of-Cycle Meeting Presentation NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML23033A6662023-02-0909 February 2023 Summary of Public Meeting with Constellation Energy Generation, LLC (Constellation) to Discuss Its Request for Alternatives for Certain Steam Generator Weld Inspections for Calvert Cliffs 1 & 2, Byron 1 & 2, Braidwood 1 & 2, and Ginna ML23033A6672023-01-30030 January 2023 Public Call with Constellation January 30, 2023 (Slides) ML22159A3332022-06-0909 June 2022 Presentation Slides for Braidwood and Byron 2021 End of Cycle Meeting ML22098A0512022-04-11011 April 2022 2 Cycle 25 High Burnup Lead Test Assembly NRC Pre-Submittal Meeting on April 22, 2022 (EPID L-2022-LRM-0022) (Slides) ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21166A3722021-06-15015 June 2021 End-of-Cycle Meeting Presentation ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML20258A0302020-09-22022 September 2020 Decommissioning Licensing Action Submittal Plan for Byron and Dresden Stations Early Shutdowns ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20209A5322020-07-24024 July 2020 2019 Braidwood and Byron End-of-Cycle Presentation ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18218A1122018-08-0808 August 2018 Reactor Pressure Vessel Head Penetration Nozzle Post Peening Follow-up Inspection Relief Requests for Byron Unit 2 and Braidwood Unit 1 ML18086A8432018-03-27027 March 2018 NUREG-1021, Revision 11 Implementation ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML17291B0282017-10-17017 October 2017 Submittal of Slide Package Westinghouse Encore Lead Test Rod Program Byron Unit 2 (Proprietary/Non-Proprietary) ML17296A2032017-10-0303 October 2017 Accident Tolerant Fuel Lead Test Assembly Deployment ML17132A1772017-05-25025 May 2017 LAR for Control Room Cooling at Byron and Braidwood Stations ML16334A4452016-12-0505 December 2016 Pre-submittal Meeting Byron UT RR Presentation ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML16062A4222016-03-0202 March 2016 Meeting Slides for March 7, 2016 Public Meeting to Discuss Backfit Appeal ML15342A1012015-12-0909 December 2015 TORMIS Computer Code Methodology Public Meeting Slides ML15232A6832015-08-27027 August 2015 Stations Auxiliary Feedwater System - Unit Cross-tie License Amendment Request ML15209A9722015-07-30030 July 2015 Alloy 600 PWSCC Mitigation Plan for Reactor Vessel Head Penetration Nozzles Utilizing Cavitation Peening at Byron and Braidwood ML15204A4932015-07-23023 July 2015 Bb Station Requests for Relief for Alternate Examination Frequency ML15204A5052015-07-23023 July 2015 EPRI Tech Basis for Brd-Byr Head RR ML15133A4732015-05-20020 May 2015 Digital Upgrades of the Non-Safety Related NSSS Control Systems at Byron and Braidwood Stations ML14342A8122014-12-10010 December 2014 Presentation Slides for December 10, 2014 Meeting on Alloy 600 PWSCC Mitigation for Rvh Nozzles ML14261A1112014-09-22022 September 2014 2014 NEI Fire Protection Information Forum NRC Public Slides ML14251A4852014-09-10010 September 2014 Byron/Braidwood Auxiliary Feedwater Cross-Tie ML14051A0662014-02-20020 February 2014 2/06/2014, Exelon Presentation Slides (Public Meeting with Exelon Generation Company, Nuclear Energy Industry, and Cask System Vendors to Discuss Issues with Spent Fuel Vacuum Drying Process) ML14051A0592014-02-20020 February 2014 2/06/2014, NRC Presentation Slides (Public Meeting with Exelon Generation Company, Nuclear Energy Industry, and Cask System Vendors to Discuss Issues with Spent Fuel Vacuum Drying Process) 2024-04-09
[Table view] |
Text
Byron Annual Assessment Meeting Reactor Oversight Program - CY 2004 Nuclear Regulatory Commission - Region III Lisle, IL
Purpose of Todays Meeting A public forum for discussion of the licensees performance
! NRC will address Byron performance issues discussed in the March 2, 2005 Annual Assessment Letter
! Licensee Remarks
Agenda Introduction
! Review of Reactor Oversight Process
! National Summary of Plant Performance
! Discussion of Plant Performance Results
! Licensee Response and Remarks
! NRC Closing Remarks
! NRC available to address public questions
NRC Representatives Mark A. Satorius, Director, Division Reactor Projects (DRP)
- (630) 829-9600
! Steven Reynolds, Deputy Director, DRP
- (630) 829-9600
! David Passehl, Branch Chief
- (630) 829-9872
! George Dick, Project Manager, NRR
- (315) 415-3019
! Rick Skokowski, Senior Resident Inspector
- (815) 234-5451
! Pete Snyder, Resident Inspector
- (815) 234-5451
! Thomas Tongue, Senior Project Engineer
- (630) 829-9613
Region III Organization Jim Caldwell Regional Administrator Geoffrey Grant Deputy Regional Administrator Mark A. Satorius Cynthia D. Pederson Director Division of Reactor Projects Director Division of Reactor Safety Steven Renyolds Roy J. Caniano Deputy Director Deputy Director David Passehl Regional Specialists Branch Chief Byron Project Engineer Resident Inspectors Thomas Tongue Rick Skokowski Pete Snyder
NRC Performance Goals Safety:Ensure protection of the public health and safety and the environment
! Security: Enhance the secure use and management of radioactive matrerials
! Openness: Ensure openness in our regulatory process
! Effectiveness: Ensure that NRC actions are effective, efficient, realistic, and timely
! Management: Ensure excellence in agency management to carry out the NRCs strategic objective
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Performance Indicator Baseline Inspection Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response
Examples of Baseline Inspections Equipment Alignment ~92 hrs/yr
! Triennial Fire Protection ~200 hrs every 3 yrs
! Operator Response ~125 hrs/yr
! Emergency Preparedness ~80 hrs/yr
! Public Radition Protection ~100 hrs every 2 yrs
! Worker Radiation Protection ~100 hrs/yr
! Corrective Action Program ~200 hrs every 2 yrs
! Corrective Action Case Reviews ~60 hrs/yr
Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very Low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC Management Involvement with Licensee Management Increasing Regulatory Actions
National Summary of Plant Performance Status at End of CY 2004 Licensee Response 78 Regulatory Response 21 Degraded Cornerstone 0 Multiple/Repetitive Degraded Cornerstone 3 Unacceptable 0 Total Units 102
National Summary
! Performance Indicator Results (at end of CY 2004)
< Green 1834
< White 6
< Yellow 0
< Red 0
! Total Inspection Findings (CY 2004)
< Green 778
< White 11
< Yellow 0
< Red 0
Byron Assessment Results (Jan 1 - Dec 31, 2004)
Licensee Response Column All Inspection Findings were Green
< Very Low Significance
! All Performance Indicators were within the Green band
Byron Inspection Activities (Jan 1 - Dec 31, 2004)
! Baseline Inspection
! Unit 2 Refueling Outage
! Other Inspections
Byron Inspection Activities (Jan 1 - Dec 31, 2004)
Completed Baseline Inspections Routine Integrated Inspections
! Triennial Fire Protection Inspection
! Maintenance Rule Inspection
! Modifications and 10 CFR 50.59 Inspection
! Emergency Preparedness Inspection
! Radiation Protection Inspection
! Licensed Operator Requalification Inspection
Byron Inspection Activities (Jan 1 - Dec 31, 2004)
Completed Other Inspections TI 2515/152 Reactor Pressure Vessel Lower Head Penatration Nozzles
! TI 2515/154 Spent Fuel Material and Accounting Inspection
! TI 2515/156 Offsite Power System Operational Readiness Inspection
Byron Performance (Jan 1 - Dec 31, 2004)
All Performance Indicators in the Green Band
! 14 Green Findings
Byron Annual Assessment Summary January 1- December 31, 2004 Exelon operated Byron in a manner that preserved public health and safety
! All cornerstone objectives were met
! In 2005, NRC plans baseline inspections
Licensee Response and Remarks Steve Kuczynski Site Vice President Byron Station
Contacting the NRC Report an emergency
< (301) 816-5100 (call collect)
! Report a safety concern:
< (800) 695-7403
< Allegation@nrc.gov
! General information or questions
< www.nrc.gov
< Select What We Do for Public Affairs
Reference Sources
! Reactor Oversight Process
< http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html
! Public Electronic Reading Room
< http://www.nrc.gov/reading-rm.html
! Public Document Room
< 1-800-397-4209 (Toll Free)