PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION May 2, 2005 RN-05-016 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT REGULATORY ACTION Licensee:

Nuclear Management Company, LLC EA-05-021 Kewaunee Nuclear Power Plant Docket No. 50-305

Subject:

ISSUANCE OF FINAL SIGNIFICANCE DETERMINATION AND NOTICE OF VIOLATION This is to inform the Commission that one White Significance Determination Process finding will be issued on or about May 5, 2005, to Nuclear Management Company, LLC (NMC) as a result of inspections at the Kewaunee Nuclear Power Plant. This White finding, an issue of low to moderate safety significance, which may require additional NRC inspections, involved the licensees inability to rapidly close the containment equipment hatch during cold shutdown conditions due to an interference. Specifically, the interference was caused by the inadequate design of a rail system which was installed in the containment to facilitate reactor vessel head replacement activities.

A Notice of Violation is included based on a violation 10 CFR Part 50, Appendix B, Criterion V, (Instructions, Procedures, and Drawings). Specifically, the licensee did not develop or have in place procedures or plans to effect a rapid removal of the interior portion of the steel rail system to allow closure of the containment equipment hatch if it became necessary to do so. In accordance with the NRC Enforcement Policy, the Notice of Violation is considered an escalated enforcement action because it is associated with a White finding.

It should be noted that the licensee has not been specifically informed of the regulatory action.

The schedule of issuance and notification is:

Mailing of Final Significance Determination May 5, 2005 Telephone Notification of Licensee May 5, 2005 The State of Wisconsin will be informed.

Contacts: D. Starkey, OE, 301-415-3456 C. Nolan, OE, 301-415-3360

PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION PRELIMINARY INFORMATION - NOT FOR PUBLIC DISCLOSURE UNTIL VERIFICATION THAT LICENSEE HAS RECEIVED ACTION Distribution:

OWFN Chairman Diaz Comm. McGaffigan Comm. Merrifield Comm. Lyons Comm. Jaczko SECY OCA PA IP OWFN EDO DEDR DEDE OE OGC NRR NSIR OI SP TWFN OCFO OP CENTER NMSS OIG OCIO RES ACRS Regional Offices RI RII RIII RIV MAIL ADAMS File Name: E:\\Filenet\\ML051220385.wpd ADAMS: ML051220385 OE:ES OE:C DStarkey CNolan 05/2/05 05/2/05