Re Confirmation of Initial Operator License Examination
ML051090394
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 04/18/2005
From: Hironori Peterson
Division of Reactor Safety III
To: O'Connor W
Detroit Edison
References
Download: ML051090394 (3)


Text

April 18, 2005 Mr. William OConnor, Jr.

Vice President Nuclear Generation Detroit Edison Company 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

FERMI POWER PLANT - CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATION

Dear Mr. OConnor:

In a letter (NRC-04-0050) dated July 15, 2004, your staff requested we schedule an initial license operator examination in February 2006. We have tentatively scheduled the requested examination to occur during the weeks of February 20 and 27, 2006. On-site validation of the examination is tentatively scheduled to occur at the station during the week of January 23, 2006. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately upon discovery of such conditions and make arrangements to administer the examination at a mutually acceptable date.

As stated in your letter, Your staff will develop the examination. Your letter indicated that you are training approximately 12 candidates for the examination. Please inform us if the number of candidates declines below nine as this will impact the examination schedule. Please inform us at your earliest opportunity if you discover you need to change the scheduled date for the examination.

A supplementary letter will be sent to the training department approximately 120 days prior to the initial examination informing them of the chief examiners name. The letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination dates, and reconfirm the number of candidates you have in the training program. If you have any questions concerning this information, please contact Mr. Michael Bielby of my staff at (630) 829-9762.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and

W. OConnor Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-341 License No. NPF-43 cc: N. Peterson, Manager, Nuclear Licensing D. Pettinari, Legal Department Compliance Supervisor G. White, Michigan Public Service Commission Michigan Department of Environmental Quality Monroe County, Emergency Management Division Planning Manager, Emergency Management Division MI Department of State Police E. F. Kokosky, Training Manager

W. OConnor Management System (ADAMS). ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-341 License No. NPF-43 cc: N. Peterson, Manager, Nuclear Licensing D. Pettinari, Legal Department Compliance Supervisor G. White, Michigan Public Service Commission Michigan Department of Environmental Quality Monroe County, Emergency Management Division Planning Manager, Emergency Management Division MI Department of State Police E. F. Kokosky, Training Manager ADAMS Distribution:

LXR1 NKR RidsNrrDipmIipb GEG KGO SJC4 DRPIII DRSIII PLB1 JRK1 DCT MAB1 DOCUMENT NAME: ML051090394.wpd To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME MABies:tr MBielby HPeterson DATE 04/13/05 04/13/05 04/18/05 OFFICIAL RECORD COPY