Similar Documents at Hatch |
---|
Category:- No Document Type Applies
MONTHYEARML24018A0702023-11-30030 November 2023 Form 2.1-1 Examination Preparation Checklist ML17076A4322017-03-23023 March 2017 TSTF-542 Deviations Descriptions for Hatch Nuclear Plant ML16285A3282016-10-12012 October 2016 ROP PI Frequently Asked Questions (Faqs): 14-05 ML15236A1202015-08-25025 August 2015 Order EA-13-109 (HCVS) Phase 1 and 2 OIP Rev 0H3A - August 25, 2015 ML15233A0742015-08-10010 August 2015 SPRA Relief - Information to Support Reconsideration of Hatch U1 for Inclusion in SPRA Relief Due to Seismic Robustness and Similarities to Hatch U2 ML14314A5122014-11-13013 November 2014 Enclosure 2 - Frequently Asked Questions (Faqs) Discussed During the October 22 2014 Reactor Oversight Process Public Meeting ML13143A3312013-06-0606 June 2013 Operating Boiling-Water Reactor Licensees with Mark 1 and Mark 2 Containments Addresses List - Enclosure 2 ML12056A0522012-03-12012 March 2012 Enclosure 6 - List of Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML11313A1472011-09-30030 September 2011 CR New Summary - Southern Company ML11308A6682011-09-28028 September 2011 Georgia Power Company - Reactor Plant Event Notification Worksheet ML1020302702010-07-13013 July 2010 Current Issues, Edwin I Hatch Nuclear Plant ML1019303132010-06-0909 June 2010 Onsite Ground/Surface Water Monitoring Questionnaire for Hatch ML1019304602010-03-25025 March 2010 List of Historical Leaks and Spills at Us Commercial Nuclear Power Plants ML0933507512010-01-14014 January 2010 Temporary Instruction 2515/180, Managing Fatigue ML1019402172009-05-14014 May 2009 South Nuclear Plant E.I. Hatch - Actions for Potential Groundwater Contamination Events ML0818503872008-06-0606 June 2008 Consent and Hearing Waiver Form - Anthony Fortuna ML0806704192008-03-0707 March 2008 CDBI Findings ML0732400242007-10-25025 October 2007 Examples of Max Thermal Power License Conditions ML0626503122006-09-0101 September 2006 Liquid Radiation Release Lessons Learned Task Force Final Report (Enclosure) ML0610703612006-04-12012 April 2006 Attendance List ML0505404642004-02-0909 February 2004 Dynamic Web Page Printout Dated 02/09/2004 Regarding Applied Violations for Nuclear Power Plants ML0505402642003-10-22022 October 2003 Summary of EB1 Findings (07-09/03) ML0505402952003-09-30030 September 2003 Fire Protection Mc 0612 Appendix B Minor Questions Worksheet ML0403502122003-08-13013 August 2003 DRS Open Items Status ML0510100462003-07-21021 July 2003 NRC Audit Question 71 ML0510100542003-07-21021 July 2003 NRC Audit Question 72 ML0510100592003-07-21021 July 2003 NRC Audit Question 70 ML0510100562003-07-10010 July 2003 NRC Audit Question 51 ML0510100362003-07-0808 July 2003 NRC Audit Question 6 ML0505402572003-02-18018 February 2003 Note Regarding Local Operation of Valve 2E11-F015A ML0208102742002-02-28028 February 2002 Requested Permit Revisions - Edwin I. Hatch Nuclear Plant ML0208102722002-02-28028 February 2002 EPA Form 2C NPDES - Application for Permit to Discharge Wastewater Consolidated Permits Program - Edwin I. Hatch Nuclear Plant ML0208102712002-02-28028 February 2002 EPA Form 1 General - General Information Consolidated Permits Program - Edwin I. Hatch Nuclear Plant ML0208102792002-02-20020 February 2002 Certificate of Analysis from General Test Lab. to Georgia Power Co ML0208102762002-02-20020 February 2002 Certificate of Analysis from General Test Lab. to Georgia Power Co for Hatch Plant ML0208102782002-02-14014 February 2002 Florida Radiochemistry Services, Inc. - Lab Reports for Alabama Power Co ML0208102812002-02-0202 February 2002 Certificate of Analysis from General Test Lab. to Georgia Power Co 2023-11-30
[Table view] |
Text
- ;Control Number Audwt Question Processing Form lForStafuse ony)
Question Initiated By: Smith, Caswell Date: 7/21/2003 Regulatory Basis for Question:
Question:
DCR 91-134 describes the logic for the electrical backup for SRV actuation as being I out of 2 taken twice.
However, this DCR as implemented does not appear to have such logic and the implemented logic appears to have some un-intended consequences. How was this DCR reviewed and what where the post modification test requirements? Was the DCR specifically reviewed for its potential impact on post fire safe shutdown?
Response
The back-up SRV actuation logic as designed per DCR 91-134 represents one-out-of-two taken-twice logic which is consistent with logic concept per GE design specification for Plant Hatch systems. An example of GE specification and schematic diagram of similar one-out-of-two-taken-twice logic utilized in HPCI system is attached for reference. The one-out-of-two-taken-twice logic, for a normally de-energized system which is energized to trip, provides logic where two signals are connected in series by either, combining one signal from each channel of the same train or by combining one signal from one channel of each of the two trains.
The electrical back-up SRV logic is a normally de-energized logic, and is required to be energized on reactor vessel high pressure to actuate the SRVs. The one-out-of- two-taken-twice logic as designed per DCR 91-134 satisfied the above requirements. The logic as issued per DCR 91-134 also assures that a single failure (e.g.
loss of one division station battery) will not prevent the required opening of electrical back-up SRV on Reactor vessel high pressure.
DCR 91-134 was checked and reviewed in place at the time the DCR was processed in accordance with appropriate DCP preparation procedures for technical adequacy, failure modes and impacts on systems and component as per the Plant licensing basis which does not include consideration of multiple hot shorts. Plant readiness-review committee also reviewed the DCR-91-134 package-for completeness,-feasibility and-impacts -
to the plant.
DCR 91-134 provided the post modification functional testing requirements in items 1 through 5 of the function testing requirement section of the DCP per the Plant licensing basis which does not include consideration of multiple hot shorts.
DCR 91-134 was also reviewed specifically for its impacts on post fire safe shutdown per the appropriate engineering procedures for DCP package preparation, and as per the Plant licensing basis which does not include consideration of multiple hot shorts.
(For Staff use only)
Response by: Rathod, Jitu Reviewved by: Staff init:
NRC Status: In Progress
Control Number:
'Audit Question Processing Form (For Staff use only)
V'!-.-
. .:Iv~-i.-r-i,/t
- -, ¢ X-'.,wt i- - -:_7 i *,',--
- : *-, : . . :t - .I: ..
It X m 'ti.w i Consequently, the modification as issued under DCR 91-134 does not introduce un-intended consequences.
(For Staff use only)
Response by: Rathod, Jitu Reviewed by: Staff init:
NRC Status: In Progress