Category:Code Relief or Alternative
MONTHYEARML18145A1942018-06-15015 June 2018 Relief Request No. NDE R017 Fourth Inservice Inspection Interval Duane Arnold Energycenter (EPID-L-2017-LLR-0135) ML18106B1212018-04-25025 April 2018 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML18053A2092018-04-16016 April 2018 Request for Relief No. 03 Proposed Use of Alternative Requirements for Nozzle Inner Radius and Nozzle-to-Shell Weld Inspection for Fifth Inservice Inspection Interval (CAC No. MF9374; EPID L-2017-LLR-0110) ML17353A6822018-01-19019 January 2018 Request for Relief No. RR 01, Regarding Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds for the Renewed Operating License Term ML17272A0182017-12-19019 December 2017 Relief Request No. RR-02- Proposed Alternative to ASME Code Examination Requirements for Buried Piping Related to Fifth Inservice Inspection Interval Program Plan L-2017-121, Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography2017-07-24024 July 2017 Proposed Alternative for the Use of Encoded Phased Array Ultrasonic Examination Techniques in Lieu of Radiography ML16008A0862016-01-21021 January 2016 Relief Request No. PR-01, PR-02, VR-01, VR-02, and VR-03 Related to the Inservice Testing Program for the Fifth 10-Year Interval ML14144A0022014-06-0909 June 2014 Relief Request No. VR-03 Related to the Inservice Testing Program for the Fourth 10-Year Interval ML14099A3352014-04-29029 April 2014 Relief for 2nd Period Limited Weld Examinations ML12170A4212012-07-11011 July 2012 Evaluation of Relief Request VR-02 Regarding Inservice Testing of Safety/Relief Valves JAFP-11-0112, Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP2011-10-0303 October 2011 Relief Request (RR-8), Alternative Examination Requirements for Nozzle-to-Vessel Shell Welds and Nozzle Inner Radius Sections Using American Society of Mechanical Engineers Code Case N-702 and BWRVIP-108NP ML11235A9352011-09-0606 September 2011 Relief Request NDE-014 Authorized, Alternative Weld Overlay Repair ML11237A1052011-09-0606 September 2011 Alternative Regarding Testing Requirements of Main Steam Safety Relief Valve Psv 4402 ML0824806802008-10-0303 October 2008 Authorization of Relief Request Stock Rotation of Recirculation Pump Seal Assemblies ML0716603252007-06-14014 June 2007 Conference Call Record and Chronology, Duane Arnold Energy Center Relief Request to Use Alternative to ASME Section XI Requirements to Use Code Cases N-504-2 and N-638-1 for Weld Overlay Repairs NG-07-0143, Request for Relief from the ASME Section XI Code to Allow Use of the Provisions of Appendix Viii, Article VIII-4000, in the Evaluation of Changes in Maximum Cable Length for In-Service Inspection Examination Equipment2007-02-14014 February 2007 Request for Relief from the ASME Section XI Code to Allow Use of the Provisions of Appendix Viii, Article VIII-4000, in the Evaluation of Changes in Maximum Cable Length for In-Service Inspection Examination Equipment NG-06-0866, Responses to Requests for Additional Information and Revised Relief Requests NDE-R005 and NDE-R007 - Fourth 10-Year Inservice Inspection Program2006-12-21021 December 2006 Responses to Requests for Additional Information and Revised Relief Requests NDE-R005 and NDE-R007 - Fourth 10-Year Inservice Inspection Program ML0617103642006-07-0303 July 2006 Monticello Nuclear Generating Plant, Palisades Nuclear Plant, Point Beach Nuclear Plant Units 1 and 2, Prairie Island Nuclear Generating Plant, Units 1 and 2 - Use of ASME Code Case N-513-2 ML0612302932006-05-30030 May 2006 Relief, Third 10-Year Interval Service Inspection Program Plan Request for Relief to Extend the Third 10 Year Inservice Inspection Interval for the Examination of Welds VLA-001 VLA-002 ML0604004052006-04-0404 April 2006 Third 10-Year Interval Inservice Inspection Program Plan Request for Relief to Extend the Third 10-Year Inservice Inspection Interval for the Examination of Welds VLA-001 VLA-002 ML0509502282005-04-0707 April 2005 Duane Arnold, Evaluation of Relief Request to Use Code Case N-661 ML0432700512005-01-0606 January 2005 Relief, Alternatives for Examination of Reactor Pressure Vessel Circumferential Shell Welds Relief Request NDE-R047 ML0401607382004-02-26026 February 2004 Prairie, Units 1 and 2, Kewaunee, Point Beach, Units 1 and 2, Palisades, Re Request for Alternatives to ASME Section XI, Appendix Viii, Supplement 10 ML0313902782003-06-0303 June 2003 Third 10-year Interval Inservice Inspection Program Relief Request No. NDE-R045 ML0307804782003-03-26026 March 2003 Relief Request, Third 10-Year Interval Inservice Inspection Program Relief Requests NDE-R028, Revision 2, and NDE-R044 NG-02-0268, License DPR-49 Relief Request NDE-R001 Revision 1 NDE-R028 Revision 2, NDE-R044 and NDE-R0452002-03-29029 March 2002 License DPR-49 Relief Request NDE-R001 Revision 1 NDE-R028 Revision 2, NDE-R044 and NDE-R045 2018-06-15
[Table view] Category:Letter
MONTHYEARML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities NG-24-0004, 2023 Annual Radiological Environmental Operating Report2024-05-0808 May 2024 2023 Annual Radiological Environmental Operating Report NG-24-0003, Submittal of 2023 Annual Radioactive Material Release Report2024-04-24024 April 2024 Submittal of 2023 Annual Radioactive Material Release Report ML24072A0292024-03-29029 March 2024 Nextera Energy Duane Arnold, Llc. Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) NG-24-0002, 2023 Annual Exposure Report - Form 5s2024-03-0606 March 2024 2023 Annual Exposure Report - Form 5s NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) NG-23-0010, Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-12-0606 December 2023 Supplement to Duane Arnold Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule NG-23-0009, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment NG-23-0006, Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-05-23023 May 2023 Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update ML23137A1672023-05-11011 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report NG-23-0004, 2022 Annual Radioactive Material Release Report2023-04-25025 April 2023 2022 Annual Radioactive Material Release Report NG-23-0003, 2022 Annual Exposure Report - Form 5s2023-04-21021 April 2023 2022 Annual Exposure Report - Form 5s NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-23-0002, 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report2023-03-27027 March 2023 10 CFR 50.59 Report, Commitment Changes, 10 CFR 72.48 Report, Quality Assurance Program Changes, Technical Specification Basis Changes, and Revision of the DAEC Defueled Safety Analysis Report L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22339A0012022-12-22022 December 2022 Acceptance of Requested Licensing Action Amendment Request for Common Emergency Plan IR 05000331/20220032022-12-13013 December 2022 NRC Inspection Report No. 05000331/2022003 (Drss) ML22285A0072022-10-13013 October 2022 NRC Analysis of NextEra Energy Duane Arnold'S Decommissioning Funding Status Report, Docket No. 50-331 IR 05000331/20220022022-07-13013 July 2022 NRC Inspection Report Nos. 05000331/2022002(DNMS) and 07200032/2022002(DNMS) ML22090A1922022-05-26026 May 2022 Letter to B. Coffey, FPL from M. Doell - Duane Arnold Post Shutdown Activities Report Review Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22111A0332022-05-20020 May 2022 Operating License Page Correction Letter to B. Coffey, Florida Power and Light, from M. Doell NG-22-0055, Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan2022-05-20020 May 2022 Revision to Duane Arnold Energy Center (DAEC) ISFSI-Only Emergency Plan ML22089A0492022-05-12012 May 2022 Sfmp Review Letter NG-22-0053, 2021 Annual Radiological Environmental Operating Report2022-05-0606 May 2022 2021 Annual Radiological Environmental Operating Report NG-22-0052, Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative2022-05-0404 May 2022 Regulatory Issue Summary 2000-11. NRC Emergency Telecommunications System, Statement of Intent to Implement the Proposed Voluntary Initiative IR 05000331/20224012022-04-27027 April 2022 Decommissioning Security Inspection Report 05000331/2022401 NG-22-0050, Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 02022-04-26026 April 2022 Revised Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program, Revision 0 NG-22-0049, 2021 Annual Radioactive Material Release Report2022-04-26026 April 2022 2021 Annual Radioactive Material Release Report ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval L-2022-068, NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 22022-04-25025 April 2022 NextEra Energy Duane Arnold Quality Assurance Topical Report (FPL-3) Revision 2 NG-22-0035, Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 02022-04-13013 April 2022 Response to Request for Additional Information Relating to Decommissioning Quality Assurance Program. Revision 0 NG-22-0047, Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool2022-04-11011 April 2022 Registration of Independent Spent Fuel Installation Storage Cask and Notification of Permanent Removal of All Spent Fuel Assemblies from the Spent Fuel Pool NG-22-0042, Registration of Independent Spent Fuel Installation Storage Casks2022-04-0808 April 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0041, and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report2022-03-31031 March 2022 and Independent Spent Fuel Storage Installation, 2022 Annual Decommissioning and Spent Fuel Management Funding Status Report NG-22-0030, Registration of Independent Spent Fuel Installation Storage Casks2022-03-23023 March 2022 Registration of Independent Spent Fuel Installation Storage Casks NG-22-0031, 2021 Annual Exposure Report - Form 5s2022-03-23023 March 2022 2021 Annual Exposure Report - Form 5s ML22080A1822022-03-22022 March 2022 Letter to B. Coffey from M. Doell - Duane Arnold ISFSI QAPD RAI Letter L-2022-012, Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3)2022-03-16016 March 2022 Florida Power & Light Company Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML22059A7462022-03-10010 March 2022 ISFSI-Only Physical Security Plan License Amendment Approval NG-22-0025, Registration of Independent Spent Fuel Installation Storage Casks2022-03-0808 March 2022 Registration of Independent Spent Fuel Installation Storage Casks IR 05000331/20220012022-03-0404 March 2022 Subject: NRC Inspection Report Nos. 05000331/2022001(DNMS) and 07200032/2022001(DNMS) 2024-09-04
[Table view] Category:Safety Evaluation
MONTHYEARML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter ML22132A2872022-05-24024 May 2022 ISFSI DQAP Approval Letter ML22089A0492022-05-12012 May 2022 Sfmp Review Letter ML22066A7632022-04-25025 April 2022 ISFSI-Only Emergency Plan License Amendment Approval ML22028A2822022-02-0303 February 2022 Defueled Physical Security Plan License Amendment Approval ML21067A6422021-05-13013 May 2021 Cyber Security License Amendment Approval ML21098A1662021-04-28028 April 2021 PDEP and EAL License Amendment Approval ML21097A1412021-04-13013 April 2021 EP Exemption Issuance Letter and SE ML20225A0002020-08-27027 August 2020 Approval of Quality Assurance Topical Report (FPL-3), Revision 0 (EPID-L-2020-LLQ-0002) ML20184A0032020-07-30030 July 2020 Issuance of Amendment No. 312 Removal of License Condition 2.C.(3), Fire Protection Program ML20134J1042020-07-10010 July 2020 Issuance of Amendment No. 311 to Revise Operating License and Technical Specifications for Permanently Defueled Conditions ML20083G0082020-04-29029 April 2020 Issuance of Amendment No. 310 Changes to the Post-Shutdown Emergency Plan for Duane Arnold Energy Center ML20015A1232020-02-0606 February 2020 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML19310C2042020-01-0202 January 2020 Issuance of Amendment No. 309 to Align Technical Specifications Staffing and Administrative Requirements ML19204A2872019-08-28028 August 2019 Approval of a Certified Fuel Handler Training and Retraining Program ML19198A0102019-07-23023 July 2019 Approval of Change in the BWRVIP Integrated Surveillance Program Capsule Test Schedule to Accommodate Early Closure ML19168A1302019-06-21021 June 2019 Safety Evaluation Regarding Implementation of Hardened Containment Vents Capable of Operation Under Severe Accident Conditions Related to Order EA-13-109 (CAC No. MF4391; EPID No. L-2014-JLD-0039) ML18292A5662018-11-30030 November 2018 Issuance of Amendment 308 to Upgrade Emergency Action Level Scheme for Duane Arnold Energy Center (DAEC) ML18241A3832018-10-31031 October 2018 Issuance of Amendment 307 to Revise Technical Specifications to Adopt TSTF-551, Revision 3 ML18179A1842018-08-16016 August 2018 Issuance of Amendment 306 to Revise Technical Specification 3.5.1, ECCS-Operating ML18192C1832018-07-24024 July 2018 Fifth 10-Year Inservice Relief Request RR-05 ML18145A1942018-06-15015 June 2018 Relief Request No. NDE R017 Fourth Inservice Inspection Interval Duane Arnold Energycenter (EPID-L-2017-LLR-0135) ML18106B1212018-04-25025 April 2018 Proposed Alternative to Use Encoded Phased Array Ultrasonic Examination Techniques ML18053A2092018-04-16016 April 2018 Request for Relief No. 03 Proposed Use of Alternative Requirements for Nozzle Inner Radius and Nozzle-to-Shell Weld Inspection for Fifth Inservice Inspection Interval (CAC No. MF9374; EPID L-2017-LLR-0110) ML18016A6272018-03-0909 March 2018 Issuance of License Amendment No. 304 Revision to Technical Specification 3.1.2, Reactor Anomalies ML18011A0592018-03-0707 March 2018 Issuance of License Amendment No. 303 Revision to Technical Specification Table 3.3.2.1-1, Control Rod Block Instrumentation ML17353A6822018-01-19019 January 2018 Request for Relief No. RR 01, Regarding Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds for the Renewed Operating License Term ML17347A1112018-01-17017 January 2018 Safety Evaluation for Request for Relief from Seal Weld Procedure Qualification, Relief Request No. RR-04 ML17272A0182017-12-19019 December 2017 Relief Request No. RR-02- Proposed Alternative to ASME Code Examination Requirements for Buried Piping Related to Fifth Inservice Inspection Interval Program Plan ML17212A6462017-10-18018 October 2017 Issuance of Amendment to Modify the Plume Exposure Pathway Emergency Planning Zone Boundary ML17220A0262017-09-21021 September 2017 Issuance of Amendment 301 to Revise Emergency Plan ML17129A0372017-05-26026 May 2017 Safety Evaluation Regarding Implementation of Mitigation Strategies and Reliable Spent Fuel Pool Instrument Related to Orders EA-12-049 and EA-12-051 ML17027A0782017-04-0707 April 2017 Issuance of Amendments Regarding Technical Specifications for Inservice Testing Programs (CAC Nos. MF8202 Through MF8209) ML17072A2322017-03-30030 March 2017 Issuance of Amendment to Revise Technical Specifications Fuel Storage Requirements ML16313A4752016-11-30030 November 2016 Correction of Errors in Safety Evaluation Associated with License Amendment No. 298 ML16263A2452016-10-17017 October 2016 Issuance of Amendment to Technical Specifications Section 5.5.6 for the Inservice Testing Program ML16211A5142016-09-12012 September 2016 Issuance of Amendment to Revise Technical Specifications 2.1.1.2, Safety Limit Minimum Critical Power Ratio ML16210A0082016-08-30030 August 2016 Issuance of Amendment to Extend Containment Leakage Test Frequency ML16153A0912016-08-18018 August 2016 Issuance of Amendment to Revise the Value of Reactor Steam Dome Pressure ML16180A0862016-07-25025 July 2016 Issuance of Amendment to Revise and Relocate Pressure and Temperature Limit Curves to a Pressure and Temperature Limits Report ML16174A2812016-07-13013 July 2016 Issuance of Amendment (TSCR-154) to Correct Examples in Technical Specifications Section 1.4, Frequency ML16053A4262016-04-29029 April 2016 Correction of Typographical Errors in Safety Evaluation Associated with License Amendment No. 292 ML16008A0862016-01-21021 January 2016 Relief Request No. PR-01, PR-02, VR-01, VR-02, and VR-03 Related to the Inservice Testing Program for the Fifth 10-Year Interval ML15310A0822015-12-22022 December 2015 Issuance of Amendment to Adopt Technical Specifications Task Force (TSTF)-501, Relocate Stored Fuel Oil and Lube Oil Volume Values to Licensee Control ML15169A2612015-08-18018 August 2015 Issuance of Amendment Concerning Extension of Cyber Security Plan Milestone 8 Completion Date ML15014A2002015-02-10010 February 2015 Issuance of Amendment to Revise Technical Specifications to Adopt Technical Specifications Task Force - 523 Generic Letter 2008-01, Managing Gas Accumulation (Tac No. MF4358) ML14144A0022014-06-0909 June 2014 Relief Request No. VR-03 Related to the Inservice Testing Program for the Fourth 10-Year Interval ML14099A3352014-04-29029 April 2014 Relief for 2nd Period Limited Weld Examinations ML13301A7052013-11-27027 November 2013 Issuance of Amendment Adopting TSTF-535, Revise Shutdown Margin Definition to Address Advanced Fuel Designs. ML13323B4432013-11-26026 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation 2024-06-12
[Table view] |
Text
April 7, 2005 Mr. Mark A. Peifer Site Vice President Duane Arnold Energy Center Nuclear Management Company, LLC 3277 DAEC Road Palo, IA 52324-0351
SUBJECT:
DUANE ARNOLD ENERGY CENTER - EVALUATION OF RELIEF REQUEST TO USE CODE CASE N-661 (TAC NO. MC3877)
Dear Mr. Peifer:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated July 28, 2004, Nuclear Management Company, LLC (NMC, the licensee), requested that the NRC approve an alternative to the requirements of IWA-4221(a) and IWA-4221(b) of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code)Section XI, 1992 Edition through the 1992 Addenda. Specifically, the licensee requested that the NRC approve the use of ASME Code Case N-661, Alternative Requirements for Wall Thickness Restoration of Class 2 and 3 Carbon Steel Piping for Raw Water Service for use at Duane Arnold Energy Center (DAEC). The request was made pursuant to Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(a)(3)(i) to address replacement or internal weld repair of wall thinning conditions resulting from various wall thinning degradation mechanisms such as erosion, corrosion, cavitation, and pitting in Class 2 and 3 carbon steel raw water piping systems.
Based on the information provided in the licensees submittal, the NRC staff concludes that the licensee has provided an acceptable alternative to the requirements of IWA-4221(a) and IWA-4221(b) of the ASME Code,Section XI, 1992 Edition through the 1992 Addenda, subject to the following three conditions which must be met when using Code Case N-661. These conditions are: (a) if the root cause of the degradation has not been determined, the repair is only acceptable for one cycle, (b) weld overlay repair of an area can only be performed once in the same location, and (c) when through-wall repairs are made by welding on surfaces that are wet or exposed to water, the weld overlay repair is only acceptable until the next refueling outage.
The NRC staff concludes that the proposed alternative, as supplemented by the three conditions listed above, provides reasonable assurance of structural integrity and an acceptable level of quality and safety. Therefore, the proposed alternative is authorized, pursuant to 10 CFR 50.55a(a)(3)(i), for the DAEC, for the current 10-year inservice inspection (ISI) interval, or until Code Case N-661 is approved for general use by reference in Regulatory Guide (RG) 1.147, Inservice Inspection Code Case Acceptability, ASME Section XI, Division 1." At that time, if the licensee intends to continue implementing ASME Code Case N-661, it must
M. Peifer follow all provisions of Code Case N-661 with limitations or conditions specified in RG 1.147, if any. All other ASME Code,Section XI, requirements for which relief was not specifically requested and authorized herein by the NRC staff remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
A copy of the Safety Evaluation is enclosed.
Sincerely,
/RA/
L. Raghavan, Chief, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/encl: See next page
M. Peifer follow all provisions of Code Case N-661 with limitations or conditions specified in RG 1.147, if any. All other ASME Code,Section XI, requirements for which relief was not specifically requested and authorized herein by the NRC staff remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
A copy of the Safety Evaluation is enclosed.
Sincerely,
/RA/
L. Raghavan, Chief, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-331
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION PUBLIC PDIII-1 Reading ACRS OGC NRay DLPMDPR LRaghavan AMohseni EDO Contact THarris DSpaulding GGrant, RGN-III WRuland GHill (2)
ADAMS No: ML050950228 *No major changes to SE dated 12/7/04 (ML043500369)
OFFICE PM:PD3-1 PM:PD3-1 LA:PD3-1 EMCB:B:SC
- OGC SC:PD3-1 NAME NRay DSpaulding DClarke for TChan NWildermann LRaghavan THarris DATE 4/6/05 4/7/05 4/6/05 12 /07/04 3/31/05 4/7/05 OFFICIAL RECORD COPY
Duane Arnold Energy Center cc:
Mr. John Paul Cowan Daniel McGhee Executive Vice President & Utilities Division Chief Nuclear Officer Iowa Department of Commerce Nuclear Management Company, LLC Lucas Office Buildings, 5th floor 700 First Street Des Moines, IA 50319 Hudson, MI 54016 Chairman, Linn County John Bjorseth Board of Supervisors Plant Manager 930 1st Street SW Duane Arnold Energy Center Cedar Rapids, IA 52404 3277 DAEC Road Palo, IA 52324 Craig G. Anderson Senior Vice President, Group Operations Steven R. Catron 700 First Street Manager, Regulatory Affairs Hudson, WI 54016 Duane Arnold Energy Center 3277 DAEC Road Palo, IA 52324 U. S. Nuclear Regulatory Commission Resident Inspectors Office Rural Route #1 Palo, IA 52324 Regional Administrator, Region III U. S. Nuclear Regulatory Commission 2443 Warrenville Road, Suite 210 Lisle, IL 60532-4352 Jonathan Rogoff Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Bruce Lacy Nuclear Asset Manager Alliant Energy/Interstate Power and Light Company 3277 DAEC Road Palo, IA 52324
SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELIEF REQUEST TO USE ASME CODE CASE N-661 NUCLEAR MANAGEMENT COMPANY, LLC DUANE ARNOLD ENERGY CENTER DOCKET NOS. 50-331
1.0 INTRODUCTION
By letter to the U.S. Nuclear Regulatory Commission (NRC, Commission) dated July 28, 2004 (ADAMS No. ML042100484), Nuclear Management Company, LLC (NMC, the licensee),
requested that the NRC approve an alternative to the requirements of IWA-4221(a) and IWA-4221(b) of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code)Section XI, 1992 Edition through the 1992 Addenda. Specifically, the licensee requested that the NRC approve the use of ASME Code Case N-661, Alternative Requirements for Wall Thickness Restoration of Class 2 and 3 Carbon Steel Piping for Raw Water Service for use at the Duane Arnold Energy Center (DAEC). The request was made pursuant to Title 10 of the Code of Federal Regulation (10 CFR) 50.55a(a)(3)(i) to address replacement or internal weld repair of wall thinning conditions resulting from various wall thinning degradation mechanisms such as erosion, corrosion, cavitation, and pitting in Class 2 and 3 carbon steel raw water piping systems. The licensee stated the primary reason for the request was to provide adequate time for additional examination of adjacent piping so that pipe replacement can be planned to reduce impact on system availability including Maintenance Rule applicability of replacement materials.
2.0 REGULATORY EVALUATION
The regulation at 10 CFR 50.55a(g) specifies that inservice inspection (ISI) of nuclear power plant components shall be performed in accordance with the requirements of the ASME Code,Section XI, except where specific written relief has been granted by the Commission pursuant to 10 CFR 50.55a(g)(6)(i). As stated in 10 CFR 50.55a(a)(3), alternatives to the requirements of paragraph (g) may be used, when authorized by the NRC, if (i) the proposed alternatives would provide an acceptable level of quality and safety or (ii) compliance with the specified requirements would result in hardship or unusual difficulty without a compensating increase in the level of quality and safety.
Pursuant to 10 CFR 50.55a(g)(4), ASME Code Class 1, 2, and 3 components (including supports) shall meet the requirements, except the design and access provisions and the preservice examination requirements, set forth in the ASME Code,Section XI, Rules for Inservice Inspection (ISI) of Nuclear Power Plant Components, to the extent practical within the limitations of design, geometry, and materials of construction of the components.
The regulations require that inservice examination of components and system pressure tests conducted during the first 10-year interval and subsequent intervals comply with the requirements in the latest edition and addenda of Section XI of the ASME Code incorporated by reference in 10 CFR 50.55a(b) 12 months prior to the start of the 120-month interval, subject to the limitations and modifications listed therein.
3.0 LICENSEES PROPOSED ALTERNATIVE
3.1 ASME Code Components Affected
All ASME Code,Section XI, Class 2 and 3 carbon steel piping for raw water services.
3.2 Applicable ASME Code Requirement ASME Code,Section XI, 1992 Edition through the 1992 Addenda:
IWA-4221(a) requires that items used for repair/replacement activities shall meet the applicable Owners Requirements.
IWA-4221(b) requires that an item to be used for repair/replacement activities shall meet the Construction Code specified in accordance with (1), (2), or (3) below.
(1) When replacing an existing item, the new item shall meet the Construction Code to which the original item was constructed.
(2) When adding a new item to an existing system, the Owner shall specify a Construction Code that is no earlier than the earliest Construction Code used for construction of any originally installed item in that system.
(3) When adding a new system, the Owner shall specify a Construction Code that is no earlier than the earliest Construction Code used for other systems that perform a similar function.
IWA-4422.1(a) states that a defect is considered removed when it has been reduced to an acceptable size.
3.3 Reason for Request
Relief is requested from replacement or weld repair of wall thinning conditions in ASME Code,Section XI, Class 2 and 3 carbon steel raw water piping systems to the design specification and the original construction code. The wall thinning conditions may be the result of various degradation mechanisms such as erosion, corrosion, cavitation, and pitting. The licensee stated the primary reason for this relief request is to provide adequate time so that pipe replacement can be planned to reduce impact on system availability including Maintenance Rule applicability and availability of replacement materials.
3.4 Proposed Alternative and Basis for Use The licensee will implement the requirements of ASME Code Case N-661 as an alternative under 10 CFR 50.55a(a)(3)(i) for Class 2 and 3 raw water piping system repairs resulting from degradation mechanisms such as erosion, corrosion, cavitation, or pitting as an alternative to the requirements of the ASME Code,Section XI, as referenced above. The licensee stated that these types of defects are typically identified by small leaks in the piping system or by pre-emptive non-code required examinations performed to monitor the degradation mechanisms. The alternative repair technique described in Code Case N-661 involves the application of additional weld metal overlay on the exterior of the piping system to restore the wall thickness of the component. The licensee stated that the repair technique will be utilized whenever the engineering evaluation determines that such a repair is suitable for the particular defect or degradation being resolved. The licensee stated that provisions for use of this Code Case will be addressed in the Repair/Replacement Program for DAEC.
The licensee stated that the provisions will require that adjacent areas be examined to verify that the repair will encompass the entire flawed area and that no other unacceptable degraded locations exist within a representative area dependent on the degradation mechanism present.
The licensee will perform an evaluation of the degradation mechanism to determine the re-examination schedule to be performed over the life of the repair. The repair will be considered to have a maximum service life of two fuel cycles unless the re-examinations conducted during each of the two fuel cycles establish the expected life of the repair.
Additionally, the licensee stated the following restrictions will be placed on the use of Code Case N-661, to ensure that the use of the Code Case will provide an acceptable alternative pursuant to 10 CFR 50.55a(a)(3)(i):
(a) If the root cause of the degradation has not been determined, the repair is only acceptable for one cycle.
(b) Weld overlay repair of an area can only be performed once in the same location.
(c) When through-wall repairs are made by welding on surfaces that are wet or exposed to water, the weld overlay repair is only acceptable until the next refueling outage.
The basis for use of the repair technique described in Code Case N-661 is that the ASME Code subcommittee for Section XI determined that this repair technique provides an acceptable alternative to the requirements of IWA-4000 and provides an acceptable level of quality and safety. Therefore, the proposed alternative is justified per 10 CFR 50.55a(a)(3)(i).
Code Case N-661 was approved by the ASME Section XI Code Committee on July 23, 2002, however, it has not been incorporated into NRC Regulatory Guide (RG) 1.147, Inservice Inspection Code Case Acceptability, ASME Section XI Division 1, and thus is not available for application at nuclear power plants without specific NRC approval. Therefore, NMC is requesting use of the alternative repair technique described via this relief request.
3.5 Duration of Proposed Alternative The licensee requested authorization of Code Case N-661 to be used for the DAEC, 10-year ISI interval or until the NRC publishes Code Case N-661 in a future revision of RG 1.147. Upon incorporation into the Regulatory Guide, the licensee stated they will review and follow the conditions specified. The licensee also stated that all other ASME Code,Section XI requirements for which relief was not specifically requested and authorized by the NRC staff will remain applicable including third party review by the Authorized Nuclear Inservice Inspector.
4.0 STAFF EVALUATION By letter dated July 28, 2004, NMC requested that the NRC approve an alternative to the requirements of IWA-4221(a) and IWA-4221(b) of the ASME Section XI,1992 Edition through the 1992 Addenda. Specifically, the licensee requested that the NRC approve ASME Code Case N-661 for use at DAEC. The request was made pursuant to 10 CFR 50.55a(a)(3)(i) to address replacement or internal weld repair of wall thinning conditions resulting from various wall thinning degradation mechanisms such as erosion, corrosion, cavitation, and pitting in Class 2 and 3 carbon steel raw water piping systems. The licensee stated the reason for the relief request was to provide adequate time for additional examination of adjacent piping so that pipe replacements can be planned to reduce impact on system availability and availability of replacement materials.
The licensee is proposing to use the provisions of Code Case N-661 to perform an alternative repair of degraded components which involves the application of weld metal overlay on the exterior of the piping system to restore the wall thickness of the component. The licensee stated that this repair technique will be utilized whenever engineering evaluations determine that such a repair is suitable for the particular defect or degradation being resolved. Provisions for use of this Code Case will be addressed in the licensees Repair and Replacement Program. The licensee stated that those provisions will require that adjacent areas be examined to verify that the entire flawed area will be encompassed by the repair and that there are no other unacceptable degraded locations within a representative area dependent on the degradation mechanism present. An evaluation of the degradation mechanism will be performed by the licensee to determine the re-examination schedule to be performed over the life of the repair. The licensee stated the repair will be considered to have a maximum service life of two fuel cycles unless re-examinations during each of the two fuel cycles are performed to establish the expected life of the repair.
The NRC staff finds the licensees reasoning in support of its request for relief acceptable. This finding is based on the fact that the NRC staff has reviewed Code Case N-661 for inclusion in RG 1.147. The NRC staffs review of Code Case N-661 established three conditions that the licensee agreed to place on the use of Code Case N-661 to assure that the Code Case will provide an acceptable alternative pursuant to 10 CFR 50.55a(a)(3)(i). These conditions are:
(a) If the root cause of the degradation has not been determined, the repair is only acceptable for one cycle.
(b) Weld overlay repair of an area can only be performed once in the same location.
(c) When through-wall repairs are made by welding on surfaces that are wet or
exposed to water, the weld overlay is only acceptable until the next refueling outage.
The NRC staff established these three conditions based on the following considerations:
(a) If the root cause of the degradation has not been determined, a suitable reinspection frequency cannot be established.
(b) Weld overlay repair of an area can only be performed once to ensure that ineffective repairs are not being repeatedly implemented in the same location.
(c) Performing through-wall weld repairs on surfaces that are wet or exposed to water would produce welds that include weld defects such as porosity, lack of fusion, and cracks. It is highly unlikely that a weld can be made on an open root joint with water present on the backside of the weld without having several weld defects. These types of weld defects can, and many times do, lead to premature failure of a weld joint.
5.0 CONCLUSION
Based on the information provided in the licensees submittal, the NRC staff concludes that the licensee has provided an acceptable alternative to the requirements of IWA-4221(a) and IWA-4221(b) of the ASME Code,Section XI, 1992 Edition through the 1992 Addenda, subject to the following three conditions which must be met when using Code Case N-661. These conditions are: (a) if the root cause of the degradation has not been determined, the repair is only acceptable for one cycle, (b) weld overlay repair of an area can only be performed once in the same location, and (c) when through-wall repairs are made by welding on surfaces that are wet or exposed to water, the weld overlay repair is only acceptable until the next refueling outage. The NRC staff concludes that the proposed alternative, as supplemented by the three conditions listed above provides reasonable assurance of structural integrity and an acceptable level of quality and safety. Therefore, the proposed alternative is authorized pursuant to 10 CFR 50.55a(a)(3)(i) for the DAEC, for the current 10-year ISI interval, or until Code Case N-661 is approved for general use by reference in RG 1.147. At that time, if the licensee intends to continue implementing Code Case N-661, it must follow all provisions of Code Case-661 with limitations or conditions specified in RG 1.147, if any. All other ASME Code,Section XI, requirements for which relief was not specifically requested and authorized herein by the NRC staff remain applicable, including third party review by the Authorized Nuclear Inservice Inspector.
Principal Contributor: E. Reichelt, NRR Date: April 7, 2005