Schedule Adjustment for Impingement/Entrainment Sampling
ML050950141
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/29/2005
From: Hellman E
Wisconsin Electric Power Co
To: Luebke P
Office of Nuclear Reactor Regulation, State of WI, Dept of Natural Resources
References
WI-0000957-07-0
Download: ML050950141 (1)


Text

March 29, 2005 Mr. Paul Luebke Bureau of Watershed Management Wisconsin Department of Natural Resources P.O. Box 7921 Madison, WI 53707-7921

SUBJECT:

WPDES Permit No. WI-0000957-07-0 Wisconsin Electric Power Company - Point Beach Nuclear Plant Proposal for Information Collection - Cooling Water Intake Structure

Dear Mr. Luebke:

Wisconsin Electric Power Company submitted to you in December 2004 a Proposal for Information Collection (PIC) for Point Beach Nuclear Plant (PBNP). The PIC included projected dates for conducting an impingement mortality and entrainment characterization study. While we had planned to conduct the impingement and entrainment sampling at PBNP from April 1, 2005 through March 31, 2006, due to other environmental compliance project priorities within the Company we are deferring the commencement of the study to either late 2005 or early 2006. This change will in no way compromise our ability to comply with the Comprehensive Demonstration Study (CDS) submittal deadline listed in the WPDES permit for PBNP.

If you have any questions regarding this matter, please contact me at (414) 221-3235.

You may also contact David Michaud at (414) 221-2187 with questions regarding the impingement mortality and entrainment characterization study plans.

Sincerely, Elizabeth Hellman, P.E.

Principal Environmental Engineer cc: Mr. David Gerdman, DNR-Mishicot Office