Similar Documents at Perry |
---|
Category:Press Release
MONTHYEARML23052A1072023-02-14014 February 2023 News Release-III-23-004: NRC Names New Senior Resident Inspector at Perry Nuclear Power Station Press Release-III-22-009, NRC to Hold Public Meeting to Discuss 2021 Performance of Perry Nuclear Power Plant2022-05-10010 May 2022 Press Release-III-22-009: NRC to Hold Public Meeting to Discuss 2021 Performance of Perry Nuclear Power Plant Press Release-III-21-010, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Davis-Besse and Perry Nuclear Power Plants2021-06-15015 June 2021 Press Release-III-21-010: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Davis-Besse and Perry Nuclear Power Plants Press Release-III-20-008, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Davis-Besse and Perry Nuclear Power Plants2020-07-16016 July 2020 Press Release-III-20-008: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Davis-Besse and Perry Nuclear Power Plants Press Release-19-061, NRC Approves License Transfers for Firstenergy Nuclear Power Plants2019-12-0303 December 2019 Press Release-19-061: NRC Approves License Transfers for Firstenergy Nuclear Power Plants Press Release-III-19-020, NRC Names New Senior Resident Inspector at Clinton Nuclear Power Station2019-10-0202 October 2019 Press Release-III-19-020: NRC Names New Senior Resident Inspector at Clinton Nuclear Power Station Press Release-III-19-016, NRC to Hold Open House to Discuss 2018 Performance of Perry Nuclear Power Plant2019-07-0909 July 2019 Press Release-III-19-016: NRC to Hold Open House to Discuss 2018 Performance of Perry Nuclear Power Plant Press Release-III-18-013, NRC Names New Senior Resident Inspector at Perry Nuclear Power Plant2018-04-0303 April 2018 Press Release-III-18-013: NRC Names New Senior Resident Inspector at Perry Nuclear Power Plant Press Release-III-18-009, NRC to Hold Open House to Discuss 2017 Performance of Perry Nuclear Power Plant2018-03-29029 March 2018 Press Release-III-18-009: NRC to Hold Open House to Discuss 2017 Performance of Perry Nuclear Power Plant Press Release-18-008, NRC Issues Annual Assessments for Nation'S Nuclear Plants2018-03-0505 March 2018 Press Release-18-008: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-III-16-013, NRC to Hold Open House to Discuss Agency'S Assessment of Perry Nuclear Power Plant2016-06-0202 June 2016 Press Release-III-16-013: NRC to Hold Open House to Discuss Agency'S Assessment of Perry Nuclear Power Plant Press Release-III-16-002, NRC Begins Special Inspection at Perry Nuclear Plant2016-02-29029 February 2016 Press Release-III-16-002: NRC Begins Special Inspection at Perry Nuclear Plant Press Release-III-15-015, NRC Schedules Open House May 28 to Discuss Performance of Perry Nuclear Plant2015-05-21021 May 2015 Press Release-III-15-015: NRC Schedules Open House May 28 to Discuss Performance of Perry Nuclear Plant Press Release-III-14-007, NRC Schedules Public Meeting March 18 to Discuss Performance of Perry Nuclear Power Plant2014-03-0707 March 2014 Press Release-III-14-007: NRC Schedules Public Meeting March 18 to Discuss Performance of Perry Nuclear Power Plant Press Release-I-13-032, NRC Staff to Meet with Firstenergy on Sept. 24 in Coraopolis, Pa. to Discuss Performance of Company & Nuclear Power Plants2013-09-16016 September 2013 Press Release-I-13-032: NRC Staff to Meet with Firstenergy on Sept. 24 in Coraopolis, Pa. to Discuss Performance of Company & Nuclear Power Plants Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-III-13-009, NRC Schedules Public Meeting April 10 to Discuss Performance of Perry Nuclear Power Plant2013-04-0101 April 2013 Press Release-III-13-009: NRC Schedules Public Meeting April 10 to Discuss Performance of Perry Nuclear Power Plant Press Release-III-13-002, the NRC Will Keep Perry Nuclear Power Plant in Current Performance Column2013-01-18018 January 2013 Press Release-III-13-002: the NRC Will Keep Perry Nuclear Power Plant in Current Performance Column Press Release-III-12-037, NRC, Firstenergy Nuclear Operating Co. to Discuss Company Nuclear Plants on Sept. 262012-09-20020 September 2012 Press Release-III-12-037: NRC, Firstenergy Nuclear Operating Co. to Discuss Company Nuclear Plants on Sept. 26 Press Release-III-12-016, NRC Names New Resident Inspector at Perry Nuclear Power Plant2012-04-25025 April 2012 Press Release-III-12-016: NRC Names New Resident Inspector at Perry Nuclear Power Plant Press Release-III-12-011, NRC Schedules Public Meeting for April 5 to Discuss Perry Nuclear Power Plant Performance in 20112012-03-29029 March 2012 Press Release-III-12-011: NRC Schedules Public Meeting for April 5 to Discuss Perry Nuclear Power Plant Performance in 2011 Press Release-III-11-032, NRC Cites Perry Nuclear Plant for Issues Involving Radiological Controls2011-08-26026 August 2011 Press Release-III-11-032: NRC Cites Perry Nuclear Plant for Issues Involving Radiological Controls Press Release-III-11-028, NRC Schedules Public Meeting August 11 to Discuss Perry Nuclear Power Plant Performance and NRC Oversight2011-08-0404 August 2011 Press Release-III-11-028: NRC Schedules Public Meeting August 11 to Discuss Perry Nuclear Power Plant Performance and NRC Oversight Press Release-III-11-012, NRC Begins Special Inspection at Perry Nuclear Plant2011-04-26026 April 2011 Press Release-III-11-012: NRC Begins Special Inspection at Perry Nuclear Plant Press Release-III-10-030, NRC to Discuss 2009 Performance Assessment for Perry Nuclear Power Plant July 282010-07-20020 July 2010 Press Release-III-10-030: NRC to Discuss 2009 Performance Assessment for Perry Nuclear Power Plant July 28 Press Release-I-10-011, Nrc. Firstenergy Nuclear Operating Co. to Discuss Companys Nuclear Plants on March 312010-03-24024 March 2010 Press Release-I-10-011: Nrc. Firstenergy Nuclear Operating Co. to Discuss Companys Nuclear Plants on March 31 Press Release-III-10-003, NRC Names New Resident Inspector at Perry Nuclear Power Plant2010-01-21021 January 2010 Press Release-III-10-003: NRC Names New Resident Inspector at Perry Nuclear Power Plant Press Release-III-09-027, NRC Names New Senior Resident Inspector at Perry Nuclear Power Plant2009-09-17017 September 2009 Press Release-III-09-027: NRC Names New Senior Resident Inspector at Perry Nuclear Power Plant Press Release-III-09-023, NRC to Discuss 2008 Performance Assessment for Perry Nuclear Power Plant July 212009-07-16016 July 2009 Press Release-III-09-023: NRC to Discuss 2008 Performance Assessment for Perry Nuclear Power Plant July 21 Press Release-III-08-013, NRC to Discuss 2007 Performance Assessment for Perry Nuclear Power Plant2008-04-0808 April 2008 Press Release-III-08-013: NRC to Discuss 2007 Performance Assessment for Perry Nuclear Power Plant Press Release-III-07-026, NRC Begins Special Inspection at Perry Plant Due to a Scram and Feedwater Problems2007-11-29029 November 2007 Press Release-III-07-026: NRC Begins Special Inspection at Perry Plant Due to a Scram and Feedwater Problems Press Release-III-07-005, - NRC to Discuss 2006 Performance Assessment for Perry Nuclear Power Plant2007-03-16016 March 2007 Press Release-III-07-005 - NRC to Discuss 2006 Performance Assessment for Perry Nuclear Power Plant Press Release-III-07-004, NRC Returns Perry to Regular Oversight2007-03-0202 March 2007 Press Release-III-07-004: NRC Returns Perry to Regular Oversight Press Release-III-06-008, NRC to Discuss 2005 Performance Assessment for Perry Nuclear Power Plant2006-03-10010 March 2006 Press Release-III-06-008: NRC to Discuss 2005 Performance Assessment for Perry Nuclear Power Plant Press Release-I-06-001, NRC, Firstenergy Nuclear Operating Co. Managers to Discuss Company'S Fleet of Nuclear Plants2006-01-0303 January 2006 Press Release-I-06-001: NRC, Firstenergy Nuclear Operating Co. Managers to Discuss Company'S Fleet of Nuclear Plants Press Release-05-155, NRC Settles Discrimination Case; Georgia Co. Agrees to Strengthen Safety Conscious Work Environment2005-11-16016 November 2005 Press Release-05-155: NRC Settles Discrimination Case; Georgia Co. Agrees to Strengthen Safety Conscious Work Environment Press Release-III-05-040, NRC to Discuss Performance Improvement Activities at Perry Nuclear Power Plant2005-10-0606 October 2005 Press Release-III-05-040: NRC to Discuss Performance Improvement Activities at Perry Nuclear Power Plant Press Release-III-05-029, NRC to Discuss Preliminary Results of an In-Depth Inspection at Perry Nuclear Power Plant2005-05-23023 May 2005 Press Release-III-05-029: NRC to Discuss Preliminary Results of an In-Depth Inspection at Perry Nuclear Power Plant Press Release-III-05-010, NRC Finds Emergency Plan Violation at Perry Nuclear Plant to Be of Low to Moderate Safety Significance2005-03-30030 March 2005 Press Release-III-05-010: NRC Finds Emergency Plan Violation at Perry Nuclear Plant to Be of Low to Moderate Safety Significance Press Release-III-05-009, NRC to Discuss 2004 Performance Assessment for Perry Nuclear Power Plant2005-03-29029 March 2005 Press Release-III-05-009: NRC to Discuss 2004 Performance Assessment for Perry Nuclear Power Plant Press Release-III-05-007, NRC Proposes $55,000 Fine for Discrimination Against Perry2005-02-28028 February 2005 Press Release-III-05-007: NRC Proposes $55,000 Fine for Discrimination Against Perry Press Release-III-05-003, NRC Begins In-Depth, Three-Part Inspection at Perry Nuclear Plant2005-01-10010 January 2005 Press Release-III-05-003: NRC Begins In-Depth, Three-Part Inspection at Perry Nuclear Plant Press Release-III-05-001, NRC Begins Special Inspection of Pump Issues at Perry Nuclear Plant2005-01-0707 January 2005 Press Release-III-05-001: NRC Begins Special Inspection of Pump Issues at Perry Nuclear Plant Press Release-III-04-049, NRC to Meet with Firstenergy on Nuclear Plant Performance2004-11-0909 November 2004 Press Release-III-04-049: NRC to Meet with Firstenergy on Nuclear Plant Performance Press Release-III-04-047, NRC Staff to Meet Oct. 28 with Firstenergy Officials to Review Performance Improvement Activities at Perry Nuclear Plant2004-10-19019 October 2004 Press Release-III-04-047: NRC Staff to Meet Oct. 28 with Firstenergy Officials to Review Performance Improvement Activities at Perry Nuclear Plant Press Release-III-04-044, NRC to Increase Regulatory Oversight of Perry Nuclear Plant2004-08-12012 August 2004 Press Release-III-04-044: NRC to Increase Regulatory Oversight of Perry Nuclear Plant Press Release-III-04-038, NRC to Discuss Perry Inspection Findings with Firstenergy Officials2004-06-16016 June 2004 Press Release-III-04-038: NRC to Discuss Perry Inspection Findings with Firstenergy Officials Press Release-III-04-034, NRC Begins Special Inspection of Pump Failure at Perry Nuclear Plant2004-05-24024 May 2004 Press Release-III-04-034: NRC Begins Special Inspection of Pump Failure at Perry Nuclear Plant Press Release-III-04-022, NRC to Meet with Firstenergy Nuclear Operating Co. to Discuss Performance of Perry Nuclear Plant2004-04-14014 April 2004 Press Release-III-04-022: NRC to Meet with Firstenergy Nuclear Operating Co. to Discuss Performance of Perry Nuclear Plant Press Release-III-03-075, NRC to Discuss Safety Significance of Pump Problem at Perry Nuclear Plant2003-12-11011 December 2003 Press Release-III-03-075: NRC to Discuss Safety Significance of Pump Problem at Perry Nuclear Plant 2023-02-14
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 2443 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov E-mail: opa3@nrc.gov No. III-05-009 March 29, 2005 CONTACT: Jan Strasma (630) 829-9663 Viktoria Mitlyng (630) 829-9662 NRC TO DISCUSS 2004 PERFORMANCE ASSESSMENT FOR PERRY NUCLEAR POWER PLANT The Nuclear Regulatory Commission staff will meet in Paineville, Ohio, on Monday, April 4, with representatives of FirstEnergy Nuclear Operating Company to discuss the agencys assessment of safety performance for the year 2004 at the Perry Nuclear Power Plant. The plant is located at Perry, Ohio.
The meeting, which will be open to the public for observation, is scheduled to begin at Monday, April 4, 2005, at 6 p.m. in the Barberry Room at the Renaissance Quail Hollow Resort, 11080 Concord-Hambden Road, Painesville.
Before the meeting is adjourned, NRC staff will be available to answer questions from the public on the safety performance of the Perry plant, as well as the role of the NRC in ensuring safe plant operation.
The NRC continually reviews the performance of the Perry plant and the nations other commercial nuclear power facilities, NRC Region III Administrator James Caldwell said. This meeting will provide an opportunity for a discussion of our annual assessment of safety performance with the company and with local officials and residents who live near the plant. Our goal is to explain the NRC oversight process and make as much information as possible available to the public regarding our regulation of these facilities.
A letter sent from the NRC Region III Office to plant officials addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/perr_2004q4.pdf The NRCs assessment concluded that the Perry plant operated safely during the 2004.
However, because of equipment problems which occurred over a two-year period from 2002 through last year, the NRC in August increased its regulatory scrutiny over the plant.
During 2004, NRC inspections also identified issues with the plants corrective action program and with staff performance. Instances were noted where the plant staff did not take effective corrective actions in response to equipment problems or had to perform multiple revisions of its evaluations of the cause of the problems.
NRC inspection findings during the year also identified problems caused by failure to follow procedures or inattention to detail by the plant staff.
As a result of the NRCs heightened oversight, the agency is conducting a broad inspection evaluating the performance of the Perry plant and the status of its activities to improve plant performance. The first two parts of this inspection have been completed, and the remaining portion of the inspection will be conducted in April and May. When the inspection in completed, the NRC will schedule a public meeting to discuss the findings of all three parts of the inspection and issue a written report.
Routine inspections are performed by two NRC Resident Inspectors assigned to the plant and by inspection specialists from the Region III Office in Lisle, Ill., and the agencys headquarters in Rockville, Md. Among the areas of plant operations to be inspected this year by NRC specialists are emergency preparedness, maintenance, safety system performance, and how the plant finds and fixes problems.
Current performance information for Perry is available on the NRCs web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/PERR1/perr1_chart.html