GL-03-001: Control Room Habitability - Supplemental Response Commitment Extension
ML050810283
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 03/15/2005
From: Lambert C
Nuclear Management Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BL-03-001, GL-03-001, NRC-05-036
Download: ML050810283 (2)


Text

NMc Commfted to Nucler Exce Kewaunee Nuclear Power Plant Operated by Nuclear Management Company, LLC March 15, 2005 NRC-05-036 10 CFR 50 Appendix A U. S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, Maryland 20852 Kewaunee Nuclear Power Plant Docket 50-305 License No. DPR-43 Generic Letter 2003-01: Control Room Habitability - Supplemental Response Commitment Extension.

References:

1) Letter from Thomas Coutu (NMC) to Document Control Deck (NRC),

'Generic Letter 2003-01: Control Room Habitability 60-Day Response",

dated August 7, 2003.

2) Letter from Edward J. Weinkam (NMC) to Document Control Deck (NRC), "Generic Letter 2003-01: Control Room Habitability -

Response To Commitments", dated November 25, 2003.

The Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2003-01 on June 12, 2003. The GL contains a 180-day requested response for specific information.

Licensees that could not provide the information or could not meet the requested completion date were requested to submit a written response within 60-days to address any proposed alternative course of action, including the basis for acceptability and the schedule for completion of the alternative course of action. Reference 1 is the Nuclear Management Company, LLC (NMC) 60-Day response to the GL. In Reference 1, NMC committed to provide a schedule for the completion of the requested items in the GL.

Reference 2 provided the schedule to complete the tasks necessary to assure the information requested in the GL is available.

In reference 2, NMC committed to provide responses to items 1 (a) and item 1 (b), part 1, within 90 days of performing the ASTM E741 testing. The ASTM E741 testing was completed on December 15, 2004; therefore, the date NMC committed to provide the NRC with this information is March 15, 2005. Due to a forced outage, NMC has redirected the resources necessary to complete response to issues associated with the outage. This redirection has caused a delay in completing NMC's response to GL 2003-01, items 1 (a) and 1 (b), part 1, for the Kewaunee Nuclear Power Plant.

N490 Highway 42

  • Kewaunee, Wisconsin 54216-9511 Telephone: 920.388.2562

In reviewing the resources necessary to respond to the forced outage and complete NMC's response to GL 2003-01, items 1 (a) and 1 (b) - part 1, NMC has determine that the response can be provided by April 1, 2005.

Summary of Commitments This letter revises the following existing commitment.

Current Commitment

  • NMC will provide the requested information associated with GL 2003-01, items 1 (a) and 1 (b) - part 1, by T+90 days (March 15, 2005). Where T = date performed ASTM E741 Test.

Revised Commitment

  • NMC will provide the requested information associated with GL 2003-01, items 1 (a) and 1 (b) - part 1, by April 1, 2005.

Craig W.

et Site Vice-President, Kewaunee Nuclear Power Plant Nuclear Management Company, LLC cc:

Administrator, Region Ill, USNRC Project Manager, Kewaunee Nuclear Power Plant, USNRC Senior Resident Inspector, Kewaunee Nuclear Power Plant, USNRC Electric Division, PSCW