March 16, 2005 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

PUBLIC MEETING TO DISCUSS THE 2004 END-OF-CYCLE PERFORMANCE ASSESSMENT OF POINT BEACH NUCLEAR PLANT

Dear Mr. Koehl:

This letter confirms the discussion between Mr. Mike Kunowski of the NRC staff and Ms. Fritzie Flentje of the Nuclear Management Company (NMC) to have a meeting at 6:00 p.m. (CDT) on Tuesday, April 19, 2005, at the Two Creeks Town Hall, 5128 East Tapawingo Road (Corner of Highway 42 and Tapawingo Road), Two Creeks, Wisconsin 54241.

The purpose of the meeting is to discuss the NRCs 2004 end-of-cycle performance assessment of Point Beach Nuclear Plant. The results of that assessment were previously provided to you in a letter from the NRC dated March 2, 2005. The meeting is open to the public and there will be an opportunity for the public to speak with NRC representatives before the meeting is adjourned.

If you have any questions regarding this meeting, please contact me at (630) 829-9627.

Sincerely,

/RA/

Patrick Louden, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 See Attached Distribution

March 16, 2005 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6590 Nuclear Road Two Rivers, WI 54241-9516

SUBJECT:

PUBLIC MEETING TO DISCUSS THE 2004 END-OF-CYCLE PERFORMANCE ASSESSMENT OF POINT BEACH NUCLEAR PLANT

Dear Mr. Koehl:

This letter confirms the discussion between Mr. Mike Kunowski of the NRC staff and Ms. Fritzie Flentje of the Nuclear Management Company (NMC) to have a meeting at 6:00 p.m. (CST) on Tuesday, April 19, 2005, at the Two Creeks Town Hall, 5128 East Tapawingo Road (Corner of Highway 42 and Tapawingo Road), Two Creeks, Wisconsin 54241.

The purpose of the meeting is to discuss the NRCs 2004 end-of-cycle performance assessment of Point Beach Nuclear Plant. The results of that assessment were previously provided to you in a letter from the NRC dated March 2, 2005. The meeting is open to the public and there will be an opportunity for the public to speak with NRC representatives before the meeting is adjourned.

If you have any questions regarding this meeting, please contact me at (630) 829-9627.

Sincerely,

/RA/

Patrick Louden, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301 License Nos. DPR-24; DPR-27 See Attached Distribution DOCUMENT NAME: E:\\Filenet\\ML050760370.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME MKunowski/co PLouden DATE 03/ /05 03/16 /05 OFFICIAL RECORD COPY

D. Koehl cc w/encl:

F. Kuester, President and Chief Executive Officer, We Generation J. Cowan, Executive Vice President Chief Nuclear Officer D. Cooper, Senior Vice President, Group Operations J. McCarthy, Site Director of Operations D. Weaver, Nuclear Asset Manager Plant Manager Regulatory Affairs Manager Training Manager Site Assessment Manager Site Engineering Director Emergency Planning Manager J. Rogoff, Vice President, Counsel & Secretary K. Duveneck, Town Chairman Town of Two Creeks Chairperson Public Service Commission of Wisconsin J. Kitsembel, Electric Division Public Service Commission of Wisconsin State Liaison Officer

D. Koehl ADAMS Distribution: