March 23, 2005 Mr. Joseph M. Solymossy Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 & 2 - REQUEST FOR ADDITIONAL INFORMATION FOR 4TH INTERVAL INSERVICE TESTING PLAN (TAC NOS. MC4509 AND MC4510)
Dear Mr. Solymossy:
By letter dated June 28, 2004, the Nuclear Management Company, LLC (NMC), submitted the 4th Interval Inservice Testing Program - Units 1 and 2, December 21, 2004, through December 20, 2014, for the Prairie Island Nuclear Generating Plant.
A draft of the request for additional information (RAI) was e-mailed to Mr. Jack Leveille, NMC, on November 9, 2004 (ADAMS ML043370346). In a telephone call on December 6, 2004, the U. S. Nuclear Regulatory Commission (NRC) staff and the NMC representatives discussed the subject RAIs. You provided written response to these RAIs in your submittal dated January 14, 2005.
The NRC staff review of the supplemental submittal, generated additional questions which were e-mailed to Mr. Jack Leveille (NMC) on February 16, 2005 (ADAMS ML050760060). The NRC staff and the NMC representatives had follow-up telephone discussions on March 2, 2005, during which your staff provided clarifications on these questions. However, NRC staff would like to get your written response on some of these questions provided in the enclosure. Please provide your response by April 15, 2005. If you have any further questions, please feel free to contact me at (301) 415-8371.
Sincerely,
/RA/
Mahesh Chawla, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Request for Additional Information cc w/encl: See next page
March 23, 2005 Mr. Joseph M. Solymossy Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 & 2 - REQUEST FOR ADDITIONAL INFORMATION FOR 4TH INTERVAL INSERVICE TESTING PLAN (TAC NOS. MC4509 AND MC4510)
Dear Mr. Solymossy:
By letter dated June 28, 2004, the Nuclear Management Company, LLC (NMC), submitted the 4th Interval Inservice Testing Program - Units 1 and 2, December 21, 2004, through December 20, 2014, for the Prairie Island Nuclear Generating Plant.
A draft of the request for additional information (RAI) was e-mailed to Mr. Jack Leveille, NMC, on November 9, 2004 (ADAMS ML043370346). In a telephone call on December 6, 2004, the U. S. Nuclear Regulatory Commission (NRC) staff and the NMC representatives discussed the subject RAIs. You provided written response to these RAIs in your submittal dated January 14, 2005.
The NRC staff review of the supplemental submittal, generated additional questions which were e-mailed to Mr. Jack Leveille (NMC) on February 16, 2005 (ADAMS ML050760060). The NRC staff and the NMC representatives had follow-up telephone discussions on March 2, 2005, during which your staff provided clarifications on these questions. However, NRC staff would like to get your written response on some of these questions provided in the enclosure. Please provide your response by April 15, 2005. If you have any further questions, please feel free to contact me at (301) 415-8371.
Sincerely,
/RA/
Mahesh Chawla, Project Manager, Section 1 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION:
PUBLIC OGC PDIII-1 Reading ACRS LRaghavan DPassehl, RIII MChawla THarris WPoertner ADAMS Accession Number: ML050760104 OFFICE PDIII-1/PM PDIII-1/LA EMCB/SC PDIII-1/SC NAME MChawla THarris DTerao LRaghavan DATE 3/23/05 3/23/05 03/21/05 3/23/05 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION REGARDING THE 4th INTERVAL INSERVICE INSPECTION PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 AND 2 DOCKET NOS. 50-282 AND 50-306 Please provide your written response to the following Nuclear Regulatory Commission staff questions:
- 1. The NRC staff accepted Code Case OMN-9, with the condition that (1) when the repair, replacement, or routine servicing of a pump may have affected a reference curve, the licensee must determine a new reference curve, or reconfirm an existing reference curve, in accordance with Section 3 of Code Case OMN-9; and (2) if it is necessary or desirable, for some reason other than that stated in Section 4 of Code Case OMN-9, to establish an additional reference curve or set of curves, the licensee must determine the new curves in accordance with Section 3 of Code Case OMN-9. Please discuss how these conditions will be implemented when utilizing Code Case OMN-9 as requested in Relief Requests 6, 7, and 8? Please verify that the comprehensive pump test will be performed within plus or minus 20 percent of pump design flow as required by ISTB.
- 2. Relief Request #11 states the valves will be disassembled, manually stroke exercised and inspected once each fuel cycle. Will the valves be inspected each cycle on a refueling outage frequency (i.e., 18 months)? Please provide a qualitative or quantitative discussion of the risk associated with testing the check valves on line versus during an outage. Please provide an overview of the program controlling on line maintenance. Please provide a time estimate to perform the valve inspection and the technical specifications allowed outage time. If the inspection is to be performed in conjunction with other maintenance activities please provide a time estimate to perform the other maintenance activities and discuss whether the valve inspection will impact the work window duration.
Enclosure Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Manager, Regulatory Affairs Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089 Manager - Environmental Protection Division Minnesota Attorney Generals Office 445 Minnesota St., Suite 900 St. Paul, MN 55101-2127 U.S. Nuclear Regulatory Commission Resident Inspector's Office 1719 Wakonade Drive East Welch, MN 55089-9642 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Administrator Goodhue County Courthouse Box 408 Red Wing, MN 55066-0408 Commissioner Minnesota Department of Commerce 85 7th Place East, Suite 500 St. Paul, MN 55101-2198 Tribal Council Prairie Island Indian Community ATTN: Environmental Department 5636 Sturgeon Lake Road Welch, MN 55089 Nuclear Asset Manager Xcel Energy, Inc.
414 Nicollet Mall, R.S. 8 Minneapolis, MN 55401 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Craig G. Anderson Senior Vice President, Group Operations Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 November 2004