March 8, 2005 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, Virginia 23060-6711
SUBJECT:
SURRY POWER STATION, UNITS 1 AND 2 - RESPONSE TO GENERIC LETTER 2004-01, REQUIREMENTS FOR STEAM GENERATOR TUBE INSPECTIONS (TAC NOS. MC4857 AND MC4858)
Dear Mr. Christian:
On August 30, 2004, the NRC staff issued Generic Letter (GL) 2004-01, Requirements for Steam Generator Tube Inspections to the industry. The purpose of this generic letter was to obtain information that would enable the NRC staff to determine whether a licensees steam generator (SG) tube inspection program complies with the existing tube inspection requirements (the plant technical specifications in conjunction with Title 10 of the Code of Federal Regulations, Part 50, Appendix B).
By letter dated October 29, 2004, Virginia Electric and Power Company (VEPCO) provided its response to GL 2004-01 for Surry Power Station, Units 1 and 2. After reviewing VEPCOs response, the NRC staff did not identify any concerns with the inspection practices related to GL 2004-01 that are employed at Surry. Therefore, the NRC staff concludes that VEPCOs SG tube inspection practices related to GL 2004-01 are in compliance with the existing SG tube inspection requirements.
If you have any questions regarding this matter, please contact Stephen Monarque at (301) 415-1544.
Sincerely,
/RA/
Stephen Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281 cc: See next page
March 8, 2005 Mr. David A. Christian Sr. Vice President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, Virginia 23060-6711
SUBJECT:
SURRY POWER STATION, UNITS 1 AND 2 - RESPONSE TO GENERIC LETTER 2004-01, REQUIREMENTS FOR STEAM GENERATOR TUBE INSPECTIONS (TAC NOS. MC4857 AND MC4858)
Dear Mr. Christian:
On August 30, 2004, the NRC staff issued Generic Letter (GL) 2004-01, Requirements for Steam Generator Tube Inspections to the industry. The purpose of this generic letter was to obtain information that would enable the NRC staff to determine whether a licensees steam generator (SG) tube inspection program complies with the existing tube inspection requirements (the plant technical specifications in conjunction with Title 10 of the Code of Federal Regulations, Part 50, Appendix B).
By letter dated October 29, 2004, Virginia Electric and Power Company (VEPCO) provided its response to GL 2004-01 for Surry Power Station, Units 1 and 2. After reviewing VEPCOs response, the NRC staff did not identify any concerns with the inspection practices related to GL 2004-01 that are employed at Surry. Therefore, the NRC staff concludes that VEPCOs SG tube inspection practices related to GL 2004-01 are in compliance with the existing SG tube inspection requirements.
If you have any questions regarding this matter, please contact Stephen Monarque at (301) 415-1544.
Sincerely,
/RA/
Stephen Monarque, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-280 and 50-281 cc: See next page Distribution PUBLIC EDunnington KLandis, RII JNakoski EHackett GHill (2 copies)
SMonarque PDII-1 R/F ACRS MBanerjee DLPM DPR PKlein JTerrell MYoder NGarrett, RII ADAMS ACCESSION NO. ML050690473 OFFICE PM/PDII-1 LA/PDII-2 SC/PDII-1 NAME SMonarque EDunnington JNakoski DATE 03/8/2005 03/8/2005 03/08/2005 OFFICIAL RECORD COPY
Surry Power Station, Units 1 & 2 cc:
Ms. Lillian M. Cuoco, Esq.
Senior Counsel Dominion Resources Services, Inc.
Building 475, 5th Floor Rope Ferry Road Waterford, Connecticut 06385 Mr. Donald E. Jernigan Site Vice President Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road Surry, Virginia 23883-0315 Senior Resident Inspector Surry Power Station U. S. Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation Post Office Box 1197 Richmond, Virginia 23218 Dr. Robert B. Stroube, MD, MPH State Health Commissioner Office of the Commissioner Virginia Department of Health Post Office Box 2448 Richmond, Virginia 23218 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Mr. Chris L. Funderburk, Director Nuclear Licensing & Operations Support Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, Virginia 23060-6711