Acknowledgment of Request for Exemptions from Record Keeping Requirements of 10 CFR 50 for the Haddam Neck Plant
ML050690014
Person / Time
Site: Haddam Neck File:Connecticut Yankee Atomic Power Co icon.png
Issue date: 03/10/2005
From: Tanya Smith
NRC/NMSS/DWMEP/DD
To: Norton W
Connecticut Yankee Atomic Power Co
References
FOIA/PA-2005-0203
Download: ML050690014 (2)


Text

March 10, 2004 Mr. Wayne Norton President Connecticut Yankee Atomic Power Company 362 Injun Hollow Road East Hampton, Connecticut 06424-3099

SUBJECT:

ACKNOWLEDGMENT OF REQUEST FOR EXEMPTIONS FROM RECORD KEEPING REQUIREMENTS OF 10 CFR 50 FOR THE HADDAM NECK PLANT

Dear Mr. Norton:

The NRC staff has received your application for exemption dated February 16, 2005, CY 025, for the Haddam Neck Plant. Your letter requests exemption from 10 CFR 50 Appendix A Criterion 1 and 10, Appendix B Criterion XVII, and 10 CFR 50.59(d)(3).

We have completed the initial processing, which is an administrative review, and have accepted your request for a more detailed technical review. The more detailed technical review may identify omissions in the submitted information or technical issues that will result in a Request for Additional Information (RAI). If required, these will be forwarded to you under separate cover. The staff expects to complete its review by August, 2005. This schedule assumes no RAIs are required.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Document Access Management System (ADAMS). ADAMS is accessible from the NRC Web site:

http://www.nrc.gov.reading-rm/adams.html.

If you have any questions on these matters, please contact me at (301) 415-6721.

Sincerely,

/RA/

Theodore Smith Project Manager Decommissioning Directorate Division of Waste Management and Environmental Protection Office of Nuclear Materials Safety and Safeguards Docket No.50-213

March 10, 2004 Mr. Wayne Norton President Connecticut Yankee Atomic Power Company 362 Injun Hollow Road East Hampton, Connecticut 06424-3099

SUBJECT:

ACKNOWLEDGMENT OF REQUEST FOR EXEMPTIONS FROM RECORD KEEPING REQUIREMENTS OF 10 CFR 50 FOR THE HADDAM NECK PLANT

Dear Mr. Norton:

The NRC staff has received your application for exemption dated February 16, 2005, CY 025, for the Haddam Neck Plant. Your letter requests exemption from 10 CFR 50 Appendix A Criterion 1 and 10, Appendix B Criterion XVII, and 10 CFR 50.59(d)(3).

We have completed the initial processing, which is an administrative review, and have accepted your request for a more detailed technical review. The more detailed technical review may identify omissions in the submitted information or technical issues that will result in a Request for Additional Information (RAI). If required, these will be forwarded to you under separate cover. The staff expects to complete its review by August, 2005. This schedule assumes no RAIs are required.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs Agencywide Document Access Management System (ADAMS). ADAMS is accessible from the NRC Web site:

http://www.nrc.gov.reading-rm/adams.html.

If you have any questions on these matters, please contact me at (301) 415-6721.

Sincerely,

/RA/

Theodore Smith Project Manager Decommissioning Directorate Division of Waste Management and Environmental Protection Office of Nuclear Materials Safety and Safeguards Docket No.50-213 DISTRIBUTION PUBLIC RDS Reading RidsNmssPMTSmith DOrlando RidsOgcRp RidsRgn1MailCenter (MMiller) CCraig DSchmidt ML050690014 OFC RDS/DCD RDS/DCD NAME TSmith CCraig DATE 3 /9/05 3/10/05 OFFICIAL RECORD COPY