R. E. Ginna Nuclear Power Plant, Emergency Operating Procedures
ML050630254
Person / Time
Site: Ginna Constellation icon.png
Issue date: 02/17/2005
From: Marlow T
Constellation Energy Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML050630254 (4)


Text

1503 Lake Road Ontario, NewYork 14519-9364 585.771.3000 Constellation Energy R.E. Ginna Nuclear Power Plant, LLC February 17, 2005 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555

Subject:

Emergency Operating Procedures R.E. Ginna Nuclear Power Plant Docket No. 50-244 As requested, enclosed are Ginna Station Emergency Operating Procedures.

Very truly yours, Thomas A. Marlow TAM/jdw xc:

U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406-1415 Ginna USNRC Senior Resident Inspector Enclosure(s):

ATT Index ATT-14.7, Rev I

4.

C NPSPO200 E66429 C

Ginna Nuclear Power Plant PROCEDURE INDE.

C Thu 2/17/2005 2:14:58 pm Page 1 of 2 INPUT PARAMETERS: TYPE:

PRATT STATUS VALUE(S):

EF, QU 5 YEARS ONLY:

PRATT EOP ATrACHMENTS PROCEDURE NUMBER ATT-1.0 ATT-1.1 ATT-2.1 ATT-2.2 ATT-2.3 ATT-2.4 ATT-2.5 ATT-3.0 ATT-3.1 ATT-4.0 ATT-5.0 ATT-5.1 ATT-5.2 ATT-6.0 ATT-7.0 ATT-8.0 ATT-8.1 ATT-8.2 ATT-8.3 ATT-8.4 ATT-8.5 ATT-9.0 ATT-9.1 ATT-10.0 ATT-11.0 ATT-11.1 ATT-11.2 ATT-12.0 ATT-13.0 ATT-14.0 PROCEDURE ITLE ATTACHMENT AT POWER CCWALIGNMENT ATTACHMENT NORMAL CCW FLOW ATTACHMENT MIN SW ATTACHMENT SW ISOLATION ATTACHMENT SW LOADS IN CNMT ATTACHMENT NO SW PUMPS ATTACHMENT SPLIT SW HEADERS ATTACHMENT CUM ATTACHMENT CNMT CLOSURE ATTACHMENT CNMT RECIRC FANS ATTACHMENT COND TO SJG ATTACHMENT SAFW ATTACHMENT FIRE WATER COOLING TO TDAFW PUMP ATTACHMENT COND VACUUM ATTACHMENT CR EVAC ATTACHMENT DC LOADS ATTACHMENT DIG STOP ATTACHMENT GEN DEGAS ATTACHMENT NON!MTAL ATTACHMENT SWV ATTACHMENT LOSS OF OFFSITE POWER ATTACHMENT LETDOWN ATTACHMENT EXCESS LID ATTACHMENT FAULTED SIG ATTACHMENT LA CONCERNS ATTACHMENT IA SUPPLY ATTACHMENT DIESEL AIR COMPRESSOR ATTACHMENT N2 PORVS ATTACHMENT NC ATTACHMENT NORMAL RHR COOLING EFFECT LAST REV DATE REVIEW 003 02)1212003 0211212003 000 0511812000 05/1812000 005 02101/2001 02103/2003 008 03/06/2002 0312712003 004 03/06/2002 04/06)2004 002 05)3012003 10/31/2001 000 06n26/2002 06/26/2002 008 12/01/2004 02/17/2004 005 0211712004 0211712004 003 07/26)1994 03127/2003 006 1011012003 04/06/004 008 05)3012002 0410612004 004 10/07/2004 8/120151/2 003 12/18/1996 02/03/2003 006 03/06/2002 02103/2003 007 02/04/2004 02)04/2004 005 03/0612002 02/03/2003 008 06/2012002 05/28/2004 004 03/06/2002 02103/2003 005 03/0612002 02103/2003 001 08/26/2003 05/02/2002 009 01/07/2004 03/06/2002 006 07/2812004 10)31/2001 006 03/06/2002 03/27/2003 004 09/01/2004 03/27/2003 003 03/0612002 03127/2003 004 11/1812002 03/10/2003 005 02/12/2003 02/12/2003 003 0211212003 02/12/2003 003 03/06/2002 04/0612004 NEXT REVIEW 02/12/2008 05/18/2005 02103/2008 03/2712008 04/06/2009 10/31/2006 06/28/2007 02/17/2009 02/17/2009 03/2712008 04/06/2009 04/06/2009 01128/2009 02/03/2008 02103/2008 02104/2009 02/03/2008 05/28/2009 02/03/2008 02103/2008 05/02/2007 03/06/2007 10/31/2006 03/27/2008 03/27/2008 03/27/2008 03/10/2008 02/12/2008 02/12/2008 04/06/2009 ST EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF EF

C, NPSP0200 E66429 C

Ginna Nuclear Power Plant PROCEDURE INDE)

(Ii Thu 2/17/2005 2:14:58 pm Page 2 of 2 INPUT PARAMETERS: TYPE:

PRATT STATUSVALUE(S):

EFQU 5 YEARS ONLY:

PRATT EOP ATTACHMENTS PROCEDURE

/

EFFECT LAST NEXT NUMBER PROCEDURE TITLE REV DATE REVIEW REVIEW ST ATT-14.1 ATTACHMENT RHR COOL 007 09101/2004 01/08/2002 01/08/2007 F

ATT-14.2 ATTACHMENT RHR ISOL 003 02V1212003 02112003 02V1212008 EF ATT-14.3 ATTACHMENT RHR NPSH 003 0310612002 01/2812004 01/2812009 EF ATT-14.5 ATTACHMENT RHR SYSTEM 003 0312012003 021032003 0210312008 EF ATT-14.6 ATTACHMENT RHR PRESS REDUCTlION 002 0310612002 01/2812004 0112812009 EF ATT-14.7 ATTACHMENT ADJUST RHR FLOW 001 0211712005 0211712004 0V21712009 EF ATT-15.0 ATTACHMENT RCP START 010 01/1112005 01/1112005 01/1112010 EF ATT-15.1 ATTACHMENT RCP DIAGNOSTICS 003 04/2411997 0210312003 0210312008 EF ATT-15.2 ATTACHMENT SEAL COOUNG 005 0310612002 0210312003 0210312008 EF ATT-16.0 ATTACHMENT RUPTURED SIG 013 0111112005 01/1112005 0111112010 EF ATT-16.1 ATTACHMENT SGTL 003 0910112004 0910812000 0910812005 EF ATT-16.2 ATTACHMENT RCS BORON FOR SGTL 003 11/2612003 0910812000 0910812005 EF ATT-17.0 ATTACHMENT SD-1 019 0112112005 0112112005 01/2112010 EF ATT-17.1 ATTACHMENTSD-2 007 0910112004 0113012001 0113012006 EF ATT-18.0 ATTACHMENT SFP-RWST 005 03106/2002 0210312003 0210312008 EF ATT-20.0 ATTACHMENT VENT TIME 004 09/0112004 0210312003 02103/2008 EF ATT-21.0 ATTACHMENT RCS ISOLATION 002 03/106/2002 0210312003 02103/2008 EF ATT-22.0 ATTACHMENT RESTORING FEED FLOW 004 11)17/2004 01)2212002 01/2212007 EF ATT-23.0 ATTACHMENTTRANSFER 4160V LOADS 000 02126/1999 01128/2004 0112812009 EF ATT-24.0 ATTACHMENT TRANSFER BATTERY TO TSC 001 1210112004 09/0812000 0910812005 EF ATT-26.0 ATTACHMENT RETURN TO NORMAL OPERATIONS 000 10131/2001 1013112001 1013112006 EF PRATT TOTAL 51 GRAND TOTAL 51

LOP:

TITLE:

REV:

1 ATT-14.7 ATTACHMENT ADJUST RHR FLOW PAGE 1 of 1 Responsible Manager _

Date ___

_a?0S This attachment provides instructions for locally throttling HCV-624 and HCV-625 following a LOCA to ensure RHR pump NPSH requirements are met for sump recirculation.

NOTE:

Locked valve key required.

1. Perform the following to locally throttle HCV-624 handwheel:

a) Unlock and remove chain from HCV-624 handwheel.

b) Turn handwheel in the closed direction to take up handwheel play until resistance is felt (- 3/4 handwheel turn) and reference marks attached to the handwheel and air operator bonnet are aligned. At this point, further handwheel actuation will initiate valve travel in the closed direction.

c) With reference marks attached to the handwheel and air operator bonnet aligned, rotate handwheel 17 complete turns in the closed direction.

d) Upon attaining 17.complete turns closed, turn handwheel in the open direction 2 complete turns.

e) Lock HCV-624 handwheel to maintain current throttled setting of HCV-624.

2. Perform the following to locally throttle HCV-625 handwheel:

a) Unlock and remove chain from HCV-625 handwheel.

b) Turn handwheel in the closed direction to take up handwheel play until resistance is felt (- 2, handwheel turns) and reference marks attached to the handwheel and air operator bonnet are aligned.

At this point, further handwheel actuation will initiate valve travel in the closed direction.

c) With reference marks attached to the handwheel and air operator bonnet aligned, rotate handwheel 17 complete turns in the closed direction.

d) Upon attaining 17 complete turns closed, turn handwheel I in the open direction 1 complete turn.

e) -Lock HCV-625 handwheel to maintain current throttled setting of HCV-625.