Page 1 of 2 Summer 03/03/2005 09:48:01 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type MTN-ISI - INSERVICE INSPECTION 2 1 IP 7111108P Inservice Inspection Activities - PWR 04/25/2005 04/29/2005 Baseline Inspections MTNTI160 - 2515/160 U-1: PZR PENTRATION NOZZLES 1 1 IP 2515/160 Pzr Pene Nozzles & Stm Space Piping Connections in U.S. PWRs [NRC Bulletin 2004-01] 04/25/2005 04/29/2005 Safety Issues PS1-RP - RP OCCUPATIONAL - WEEK 1 2 1 IP 7112101 Access Control to Radiologically Significant Areas 04/25/2005 04/29/2005 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 04/25/2005 04/29/2005 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 04/25/2005 04/29/2005 Baseline Inspections 1 IP 71151 Performance Indicator Verification 04/25/2005 04/29/2005 Baseline Inspections PS1-RP - RP OCCPATIONAL BASELINE - WEEK 2 2 1 IP 7112101 Access Control to Radiologically Significant Areas 05/02/2005 05/06/2005 Baseline Inspections 1 IP 7112102 ALARA Planning and Controls 05/02/2005 05/06/2005 Baseline Inspections 1 IP 7112202 Radioactive Material Processing and Transportation 05/02/2005 05/06/2005 Baseline Inspections 1 IP 71151 Performance Indicator Verification 05/02/2005 05/06/2005 Baseline Inspections MTNSGISI - STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 05/09/2005 05/13/2005 Baseline Inspections MTN-HS - HEAT SINK 1 1 IP 7111107B Heat Sink Performance 06/06/2005 06/10/2005 Baseline Inspections RP-PS1 - RP OCCUPATIONAL BASELINE (TENTATIVE) 1 1 IP 7112202 Radioactive Material Processing and Transportation 06/06/2005 06/10/2005 Baseline Inspections PS EP - EMERGENCY EXERCISE 3 1 IP 7111401 Exercise Evaluation 07/18/2005 07/22/2005 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/18/2005 07/22/2005 Baseline Inspections 1 IP 71151 Performance Indicator Verification 07/18/2005 07/22/2005 Baseline Inspections OL RQ - REQUAL INSPECTION 2 1 IP 7111111B Licensed Operator Requalification Program 08/08/2005 08/12/2005 Baseline Inspections EB1-MODS - MODIFICATIONS/10CFR50.59 4 1 IP 7111102 Evaluation of Changes, Tests, or Experiments 10/03/2005 10/07/2005 Baseline Inspections OL PREP - INITIAL EXAM PREP 3 1 V23212 SUMMER/EXAMS AT POWER FACILITIES 11/28/2005 12/03/2005 Not Applicable OL EXAM - INITIAL EXAM 3 1 V23212 SUMMER/EXAMS AT POWER FACILITIES 12/12/2005 12/16/2005 Not Applicable MTN-MR - MR EFFECTIVENESS 2 1 IP 7111112B Maintenance Effectiveness 01/09/2006 01/13/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Summer 03/03/2005 09:48:01 Inspection / Activity Plan Report 22 03/01/2005 - 09/30/2006 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type PS1-RP - RP BASELINE PUBLIC 4 1 IP 7112101 Access Control to Radiologically Significant Areas 01/09/2006 01/13/2006 Baseline Inspections 1 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 01/09/2006 01/13/2006 Baseline Inspections 1 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 01/09/2006 01/13/2006 Baseline Inspections 1 IP 7112203 Radiological Environmental Monitoring Program 01/09/2006 01/13/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 01/09/2006 01/13/2006 Baseline Inspections PI&R - PROBLEM IDENTIFICATION AND RESOLUTION 5 1 IP 71152B Identification and Resolution of Problems 05/01/2006 05/05/2006 Baseline Inspections 1 IP 71152B Identification and Resolution of Problems 05/15/2006 05/19/2006 Baseline Inspections EB1SSDPC - SSDPC PRE-INSPECTION VISIT 1 1 IP 7111121 Safety System Design and Performance Capability 05/01/2006 05/03/2006 Baseline Inspections EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY 5 1 IP 7111121 Safety System Design and Performance Capability 06/05/2006 06/10/2006 Baseline Inspections 1 IP 7111121 Safety System Design and Performance Capability 06/19/2006 06/23/2006 Baseline Inspections PS2-EP - EP INSP 1 1 IP 7111402 Alert and Notification System Testing 07/31/2006 08/04/2006 Baseline Inspections 1 IP 7111403 Emergency Response Organization Augmentation Testing 07/31/2006 08/04/2006 Baseline Inspections 1 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/31/2006 08/04/2006 Baseline Inspections 1 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 07/31/2006 08/04/2006 Baseline Inspections 1 IP 71151 Performance Indicator Verification 07/31/2006 08/04/2006 Baseline Inspections This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.