Inspection / Activity Plan, 03/01/2005 - 09/30/2006
ML050610638
Person / Time
Site: Sequoyah  
Issue date: 03/02/2005
From:
Division Reactor Projects II
To:
Tennessee Valley Authority
Shared Package
ML050610628 List:
References
IR-05-001
Download: ML050610638 (2)


Text

Sequoyah Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 03/02/2005 11:17:31 Report 22 4

EB1SSDPC - SAFETY SYSTEM DESIGN & PERF. CAPABILITY Baseline Inspections 02/28/2005 03/04/2005 Safety System Design and Performance Capability IP 7111121 1, 2 1

PB6-SUPP

- SUPPLEMENT INSPECTION Supplemental Program 03/28/2005 03/30/2005 Supplemental Inspection For One Or Two White Inputs In A Strategic Performance Area IP 95001 1, 2 1

MTN-HS

- HEAT SINK Baseline Inspections 03/28/2005 04/01/2005 Heat Sink Performance IP 7111107B 1, 2 3

PS1-RP

- RAD PROTECTION OCCUPATIONAL - WEEK 1 Other Routine 04/25/2005 04/29/2005 Operation of an Independent Spent Fuel Storage Installation at Operating Plants IP 60855.1 1, 2 Baseline Inspections 04/25/2005 04/29/2005 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 04/25/2005 04/29/2005 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 04/25/2005 04/29/2005 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 04/25/2005 04/29/2005 Performance Indicator Verification IP 71151 1, 2 1

MTN-ISI

- U2 INSERVICE INSPECTION Baseline Inspections 05/02/2005 05/06/2005 Inservice Inspection Activities - PWR IP 7111108P 2

1 MTNTI160

- 2515/160 U-2: PZR PENETRATION NOZZLES Safety Issues 05/02/2005 05/06/2005 Pzr Pene Nozzles & Stm Space Piping Connections in U.S. PWRs [NRC Bulletin 2004-01]

IP 2515/160 2

1 MTNSGISI

- STEAM GENERATOR ISI Baseline Inspections 05/16/2005 05/20/2005 Inservice Inspection Activities - PWR IP 7111108P 2

3 PS-RP

- RAD PROTECTION OCCUPATIONAL - WEEK 2 Other Routine 05/16/2005 05/20/2005 Operation of an Independent Spent Fuel Storage Installation at Operating Plants IP 60855.1 1, 2 Baseline Inspections 05/16/2005 05/20/2005 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 05/16/2005 05/20/2005 ALARA Planning and Controls IP 7112102 1, 2 Baseline Inspections 05/16/2005 05/20/2005 Radioactive Material Processing and Transportation IP 7112202 1, 2 Baseline Inspections 05/16/2005 05/20/2005 Performance Indicator Verification IP 71151 1, 2 1

PS EP

- EP INSPECTION Baseline Inspections 06/20/2005 06/24/2005 Alert and Notification System Testing IP 7111402 1, 2 Baseline Inspections 06/20/2005 06/24/2005 Emergency Response Organization Augmentation Testing IP 7111403 1, 2 Baseline Inspections 06/20/2005 06/24/2005 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 06/20/2005 06/24/2005 Correction of Emergency Preparedness Weaknesses and Deficiencies IP 7111405 1, 2 Baseline Inspections 06/20/2005 06/24/2005 Performance Indicator Verification IP 71151 1, 2 4

PI&R

- PROBLEM IDENTIFICATION AND RESOLUTION Baseline Inspections 07/25/2005 07/29/2005 Identification and Resolution of Problems IP 71152B 1, 2 Baseline Inspections 08/08/2005 08/12/2005 Identification and Resolution of Problems IP 71152B 1, 2 4

EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 08/22/2005 08/26/2005 Evaluation of Changes, Tests, or Experiments IP 7111102 1, 2 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Sequoyah Inspection / Activity Plan 03/01/2005 - 09/30/2006 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 03/02/2005 11:17:31 Report 22 4

EB1-MODS

- MODIFICATIONS/10CFR50.59 Baseline Inspections 08/22/2005 08/26/2005 Permanent Plant Modifications IP 7111117B 1, 2 1

60855.1

- ISFSI OPERATIONS INSPECTION Other Routine 10/03/2005 10/07/2005 Operation of an Independent Spent Fuel Storage Installation at Operating Plants IP 60855.1 1, 2 3

EB2-TFP

- TFP PRE-INSPECTION VISIT Baseline Inspections 10/03/2005 10/07/2005 Fire Protection IP 7111105T 1, 2 3

EB2-TFP

- TRIENNIAL FIRE PROTECTION (TFP) INSP Baseline Inspections 10/31/2005 11/04/2005 Fire Protection IP 7111105T 1, 2 Baseline Inspections 11/14/2005 11/18/2005 Fire Protection IP 7111105T 1, 2 1

MTN-MR

- MR EFFECTIVENESS Baseline Inspections 02/13/2006 02/17/2006 Maintenance Effectiveness IP 7111112B 1, 2 2

MTN-ISI

- U1 INSERVICE INSPECTION Baseline Inspections 04/10/2006 04/14/2006 Inservice Inspection Activities - PWR IP 7111108P 1

1 MTN-ISI

- U1 STEAM GENERATOR ISI Baseline Inspections 04/17/2006 04/21/2006 Inservice Inspection Activities - PWR IP 7111108P 1

4 PS1-RP

- RP PUBLIC BASELINE Other Routine 07/24/2006 07/28/2006 Operation of an Independent Spent Fuel Storage Installation at Operating Plants IP 60855.1 1, 2 Baseline Inspections 07/24/2006 07/28/2006 Access Control to Radiologically Significant Areas IP 7112101 1, 2 Baseline Inspections 07/24/2006 07/28/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1, 2 Baseline Inspections 07/24/2006 07/28/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1, 2 Baseline Inspections 07/24/2006 07/28/2006 Radiological Environmental Monitoring Program IP 7112203 1, 2 Baseline Inspections 07/24/2006 07/28/2006 Performance Indicator Verification IP 71151 1, 2 3

OL PREP

- INITIAL EXAM PREP Not Applicable 08/28/2006 09/01/2006 SEQUOYAH/EXAM AT POWER FACILITIES V23243 1

3 PS2-EP

- EP EXERCISE Baseline Inspections 08/28/2006 09/02/2006 Exercise Evaluation IP 7111401 1, 2 Baseline Inspections 08/28/2006 09/02/2006 Emergency Action Level and Emergency Plan Changes IP 7111404 1, 2 Baseline Inspections 08/28/2006 09/02/2006 Performance Indicator Verification IP 71151 1, 2 1

MNT-ISI

- REACTOR HEAD EXAMINATION Safety Issues 09/04/2006 09/08/2006 Reactor Pressure Vessel Head and Vessel Head Penetration Nozzles (NRC Bulletin 2002-02 IP 2515/150 2

3 OL EXAM

- INITIAL EXAM Not Applicable 09/18/2006 09/22/2006 SEQUOYAH/EXAM AT POWER FACILITIES V23243 1

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.