January 2005 Monthly Operating Report for Perry Unit 1
ML050610182
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 02/15/2005
From: Richard Anderson
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, PY-CEI/NRR-2864L
Download: ML050610182 (3)


Text

tC FENOC FrstEnergy Nuclear Operating Company Perry Nuclear Power Plant 10 Center Road Perry Ohio 44081 Richard Anderson Vice President-Nuclear 440-280-5579 Fax: 440-280-8029 February 15, 2005 PY-CEINRR-2864L United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Perry Nuclear Power Plant Docket No. 50-440 License No. NPF-58 Monthly Operating Report Ladies and Gentlemen:

Attached is the January 2005 Monthly Operating Report for Perry Unit 1. Page I is the Operating Data Report and page 2 is the Unit Shutdowns Report. This report is submitted in accordance with Technical Specification 5.6.4 and Generic Letter 97-02, "Revised Contents of the Monthly Operating Report."

If you have questions or require additional information, please contact Ms. Toni Phelps at (440) 280-7660.

Very truly yours, Attachment cc: NRC Region III Administrator NRC Project Manager NRC Resident Inspector q

OPERATING DATA REPORT UNIT:

Perry DATE:

217/05 1.

2.

3.

4.

5.

6.

7.

Docket: 50-440 Unit Name:

Perry Nuclear Power Plant Reporting Period January 2005 Utility

Contact:

T. Phelps Telephone: 440-280-7660 Design Electrical Rating (Net MWe):

Maximum Dependable Capacity (Net MWe):

1260 1235 8.

9.

10.

11.

This Month Hours Reactor was Critical 148.3 Hours Generator On-Line 121.2 Unit Reserve Shutdown Hours 0.0 Net Electrical Energy (MWeH)

_121586.0 Yr-to-Date 148.3 121.2 0.0 121.586.2 Cumulative __ __

120.817.7 118.012.5 0.0 135.477.343.0 Page 1

II UNIT SHUTDOWNS REPORT MONTH - JANUARY 2005 DOCKET NO: 50-440 NAME: Perry Nuclear Power Plant DATE: 02/07/05 CONTACT: T. Phelps TELEPHONE: (440) 280-7660 No.

Date Type Duration Reason Method Cause and Corrective Action to Prevent Recurrence 1

Hours 2

.3 05-01 1/6/05 F

622.8

.'A 2

On 1/6/05 at 0112 a manual scram iwas inserted due to the downshift of the Reactor Recirculation Pumps, along with the subsequent tripping offline of the Reactor Recirculation Pump A.

SUMMARY

The Perry Nuclear Power completed power ascension on 1/5/05 at 0117. A manual scram was inserted on 1/6/05 at 0112. Plant startup was in progress at months end
1. TYPE:
2. REASON:
3. METHOD:

F: Forced A - Equipment Failure (explain) 1 - Manual S: Scheduled B-Maintenance or Test 2-Manual Scram C - Refueling 3 -Automatic Scram D - Regulatory 4-Continuation E - Operating Training &

5 - Other License Examination F - Administrative G - Operational Error (explain)

H -Other (explain)

P Page 2