FENOC FirstEnergy Nuclear Operating Company 76 South Main Street Akron, Ohio 44308 Joseph J. Hagan Senior Vice President, Engineering and Services 330-761-7895 Fax: 330-384-3799 Docket Number 50-346 Docket Number 72-14 License Number NPF-3 Serial Number 3123 10 CFR 72.48 February 3, 2005 Director, Spent Fuel Project Office Office of Nuclear Material Safety and Safeguards United States Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Document Control Desk
Subject:
10 CFR 72.48 Report of Dry Fuel Storage Facility Changes, Tests and Experiments
Dear Ladies and Gentlemen:
The FirstEnergy Nuclear Operating Company hereby submits, pursuant to 10 CFR 72.48(d)(2) and the licensing provisions of 10 CFR 72, Subparts K and L for Dry Fuel Storage, the biennial 10 CFR 72.48 Summary Report of Facility Changes, Tests and Experiments for the Davis-Besse Nuclear Power Station, Unit Number 1 (DBNPS).
This 10 CFR 72.48 Summary Report is for the period of January 1, 2003 through December 31, 2004. No changes occurred to the Dry Fuel Storage Facility during this reporting period.
Should you have any questions or require additional information, please contact Mr. Henry L. Hegrat, Supervisor - Licensing, at (330) 315-6944.
Very truly yours, GMW Attachment ks (a 5SOA
Docket Number 50-346 License Number NPF-3 Serial Number 3123 Page 2 of 2 cc: J. R. Strosnider, Director, Office of Nuclear Material Safety and Safeguards J. B. Hopkins, DB-1 NRC/NRR Senior Project Manager C. S. Thomas, DB-1 Senior Resident Inspector Utility Radiological Safety Board U.S. NRC Document Control Desk
Docket Number 50-346 License Number NPF-3 Serial Number 3123 Attachment Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by Davis-Besse. They are described only as information and are not regulatory commitments. Please notify the Supervisor - Fleet Licensing (330) 315-6944 of any questions regarding this document or associated regulatory commitments.
COMMITMENTS DUE DATE None NIA