Tech Spec Page for Amendment 187, Primary Containment Leakage Rate Testing Program
ML050330157
Person / Time
Site: Hatch Southern Nuclear icon.png
Issue date: 02/01/2005
From:
NRC/NRR/DLPM
To:
Gratton C, NRR/DLPM, 415-1055
Shared Package
ML050320005 List:
References
TAC MC2761
Download: ML050330157 (1)


Text

Programs and Manuals 5.5 5.5 Programs and Manuals (continued) 5.5.12 Primary Containment Leakage Rate Testing Program A program shall be established to implement the leakage rate testing of the primary containment as required by 10 CFR 50.54(o) and 10 CFR 50, Appendix J, Option B, as modified by approved exemptions. This program shall be in accordance with the guidelines contained in Regulatory Guide 1.163, "Performance-Based Containment Leak-Test Program," dated September 1995, as modified by the following exception to NEI 94-01, Rev. 0, Industry Guideline for Implementing Performance-Based Option of 10 CFR 50, Appendix J":

Section 9.2.3: The first Type A test after the November 2, 1995, Type A test shall be performed no later than November 2010.

The peak calculated primary containment internal pressure for the design basis loss of coolant accident, Pa, is 47.3 psig.

The maximum allowable primary containment leakage rate, La, at Pa is 1.2% of primary containment air weight per day.

Leakage rate acceptance criteria are:

a.

Primary containment overall leakage rate acceptance criterion is 5 1.0 La.

During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are 5 0.60 La for the combined Type B and Type C tests, and < 0.75 La for Type A tests;

b.

Air lock testing acceptance criteria are:

1)

Overall air lock leakage rate is 5 0.05 La when tested at 5 P,

2)

For each door, leakage rate is < 0.01 La when the gap between the door seals is pressurized to 2 10 psig for at least 15 minutes.

The provisions of SR 3.0.2 do not apply to the test frequencies specified in the Primary Containment Leakage Rate Testing Program.

(continued)