Letter Sequence Other |
---|
|
|
MONTHYEARML0502600052005-04-0505 April 2005 Environmental Assessment, One-Time Exemption - Postpone Offsite Full-Participation Emergency Exercise from 2004 to 2005 Project stage: Other ML0502504302005-04-13013 April 2005 EA, Exemption from 10 CFR Part 50, Appendix E, Section IV.F.2.b & C Project stage: Approval 2005-04-13
[Table View] |
|
---|
Category:Environmental Assessment
MONTHYEARML16354A0482017-02-0909 February 2017 Environmental Assessments and Finding of No Significant Impacts to Southern Nuclear Operating Co., Inc ML1031301872010-11-19019 November 2010 Federal Register Notice - Environmental Assessment ML1031301572010-11-19019 November 2010 Environmental Assessment and Finding of No Significant Impact NRC-2009-0375, Federal Register Notice - Environmental Assessment2010-11-19019 November 2010 Federal Register Notice - Environmental Assessment ML0921705532009-08-20020 August 2009 Environmental Assessment and Finding of No Significant Impact (TAC Nos.. ME1449 and ME1450) NL-09-1134, Enclosure 3 to Southern Nuclear Operating Company Letter Dated July 31, 2009, Environmental Assessment2009-07-31031 July 2009 Enclosure 3 to Southern Nuclear Operating Company Letter Dated July 31, 2009, Environmental Assessment ML0923803282009-07-31031 July 2009 Enclosure 3 to Southern Nuclear Operating Company Letter Dated July 31, 2009, Environmental Assessment ML0602002802006-03-0202 March 2006 Environmental Assessment, Exemption to 10 CFR Part 50, Appendix R ML0521701902005-08-0505 August 2005 Environmental Assessment Related to Exemption to 10 CFR Part 50, Appendix R, Section III.G.2.c, Requirements for Fire Area 72 ML0502600052005-04-0505 April 2005 Environmental Assessment, One-Time Exemption - Postpone Offsite Full-Participation Emergency Exercise from 2004 to 2005 ML0432401682005-02-25025 February 2005 Edwin I Hatch, Units 1 and 2, Vogtle Electric Generating Plant, Units 1 and 2, Environmental Assessment, EOFs 2017-02-09
[Table view] Category:Finding of No Significant Impact
MONTHYEARML16354A0482017-02-0909 February 2017 Environmental Assessments and Finding of No Significant Impacts to Southern Nuclear Operating Co., Inc ML1031301872010-11-19019 November 2010 Federal Register Notice - Environmental Assessment NRC-2009-0375, Federal Register Notice - Environmental Assessment2010-11-19019 November 2010 Federal Register Notice - Environmental Assessment ML0921705532009-08-20020 August 2009 Environmental Assessment and Finding of No Significant Impact (TAC Nos.. ME1449 and ME1450) ML0502600052005-04-0505 April 2005 Environmental Assessment, One-Time Exemption - Postpone Offsite Full-Participation Emergency Exercise from 2004 to 2005 ML0432401682005-02-25025 February 2005 Edwin I Hatch, Units 1 and 2, Vogtle Electric Generating Plant, Units 1 and 2, Environmental Assessment, EOFs 2017-02-09
[Table view] Category:Letter
MONTHYEARNL-24-0364, Notification of Deferral of Baffle Former Bolt Inspections from Farley 1R33 to 1R342024-10-31031 October 2024 Notification of Deferral of Baffle Former Bolt Inspections from Farley 1R33 to 1R34 NL-24-0392, Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-0022024-10-28028 October 2024 Response to Requests for Additional Information Related to Proposed Alternative GEN-ISI-AL T-2024-002 NL-24-0396, Response to Request for Additional Information Related to Relief Request to Defer Charging Pump and Mini-Flow Isolation Valve Inservice Testing2024-10-25025 October 2024 Response to Request for Additional Information Related to Relief Request to Defer Charging Pump and Mini-Flow Isolation Valve Inservice Testing NL-24-0384, Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves2024-10-18018 October 2024 Request for Alternative RR-PR-04 for Inservice Testing of the 2A, 2B, and 2C Charging Pumps and Mini-Flow Isolation Valves NL-24-0320, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,.2024-09-27027 September 2024 License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3,. NL-24-0349, Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided2024-09-20020 September 2024 Units 1 and 2 - 10 CFR 26.719(c)(1) 30-Day Report Blind Performance Test Results Inconsistent with Sample Provided NL-24-0341, Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-09-10010 September 2024 Response to Request for Additional Information Related to the Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency IR 05000348/20244012024-09-10010 September 2024 Security Baseline Inspection Report 05000348-2024401 and 05000364-2024401 ML24247A1102024-09-0505 September 2024 Corporate Notification Letter Aka 210-day Letter NUREG Rev 12 NL-24-0340, Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R322024-09-0404 September 2024 Unit 1 - Inservice Inspection Program Owners Activity Report (OAR-1) for Outage 1 R32 NL-24-0259, License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes2024-09-0404 September 2024 License Amendment Request to Revise Technical Specification 3.4.14, Reactor Coolant System Pressure Isolation Valve Leakage, Surveillance Requirement 3.4.14.3 Acceptance Criteria and Miscellaneous Obsolete Changes ML24242A1332024-08-29029 August 2024 Issuance of Amendment Nos. 250 and 247, Regarding License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions (EPID L-2024-LLA-0098) - Non-Proprietary ML24233A0022024-08-27027 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request Supplement to Change Technical Specification 3.6.5, Containment Air Temperature Actions ML24240A0812024-08-27027 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Revised Completion Time IR 05000348/20240052024-08-26026 August 2024 Updated Inspection Plan for Joseph M. Farley Nuclear Plant, Units 1 and 2 - Report 05000348/2024005 and 05000364/2024005 IR 05000348/20244022024-08-26026 August 2024 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000348/2024402 and 05000364/2024402 ML24226B2112024-08-22022 August 2024 Regulatory Audit Summary in Support of License Amendment Requests to Revise Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0321, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information2024-08-16016 August 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions - Supplemental Information IR 05000348/20240022024-08-12012 August 2024 – Integrated Inspection Report 05000348-2024002 and 05000364-2024002 and Exercise of Enforcement Discretion ML24215A3772024-08-0707 August 2024 2024 Farley Requal Inspection Corporate Notification Letter ML24201A2032024-08-0101 August 2024 Request for Withholding Information from Public Disclosure for Joseph M. Farley Nuclear Plant, Units 1 and 2, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions ML24200A1392024-07-25025 July 2024 Regulatory Audit in Support of Review of the License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature ML24199A2072024-07-24024 July 2024 TS 3-6-5 LAR - Individual Notice Transmittal Letter and NSHC - Rev 1 (1) - Letter NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 NL-24-0281, License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions2024-07-18018 July 2024 License Amendment Request to Change Technical Specification 3.6.5, Containment Air Temperature Actions NL-24-0227, Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2024-07-0303 July 2024 Proposed Inservice Inspection Alternative GEN-ISI-AL T-2024-03 for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) ML24184A0452024-07-0202 July 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24178A3762024-07-0101 July 2024 Nonacceptance of Requested Licensing Action License Amendment Request to Revise Technical Specification 3.6.5, Containment Air Temperature, Using Risk-Informed Process for Evaluations NL-24-0234, Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-06-28028 June 2024 Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown NL-24-0230, License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-3602024-06-28028 June 2024 License Amendment Request for Adoption of Technical Specifications Task Force (TSTF) Traveler TSTF-500, Revision 2, DC Electrical Rewrite – Update to TSTF-360 NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in 05000348/LER-2024-002-01, Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-06-19019 June 2024 Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel NL-24-0201, Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2024-06-18018 June 2024 Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) 05000348/LER-2024-001, Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift2024-06-17017 June 2024 Pressurizer Safety Valve Lift Pressure Outside of Technical Specifications Limits Due to Setpoint Drift NL-24-0238, RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information2024-06-14014 June 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions, Supplemental Information NL-24-0229, Notice of Intent to Pursue Subsequent License Renewal2024-06-0707 June 2024 Notice of Intent to Pursue Subsequent License Renewal ML24149A0492024-06-0404 June 2024 SNC Fleet - Regulatory Audit in Support of Review of the License Amendment Request to Revise TS 1.1, Use and Application Definitions, and Add New Technical Specification 5.5.21 and 5.5.17, Online Monitoring Program, ML24143A0412024-05-28028 May 2024 Supplemental Information Needed for Using the Risk-Informed Process for Evaluation for the LAR to Change Technical Specification 3.6.5, Containment Air Temperature, Actions NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0188, Cycle 33 Core Operating Limits Report2024-05-0101 May 2024 Cycle 33 Core Operating Limits Report NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 IR 05000348/20240012024-04-24024 April 2024 Integrated Inspection Report 05000348/2024001 and 05000364/2024001 NL-24-0137, RIPE License Amendment Request to Change Containment Air Temperature Actions2024-04-19019 April 2024 RIPE License Amendment Request to Change Containment Air Temperature Actions IR 05000348/20240102024-04-16016 April 2024 NRC Inspection Report 05000348/2024010 and 05000364/2024010 05000364/LER-2024-002, For Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel2024-04-15015 April 2024 For Manual Reactor Trip Due to Loss of Power to the 2A 125 Volt DC Distribution Panel IR 05000348/20240112024-04-12012 April 2024 Fire Protection Team Inspection Report 05000348/2024011 and 05000364/2024011 NL-24-0134, Renewed National Pollutant Discharge Elimination System (NPDES) Permit2024-04-12012 April 2024 Renewed National Pollutant Discharge Elimination System (NPDES) Permit NL-24-0088, Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency2024-04-0505 April 2024 Application to Revise Technical Specifications Regarding Change to Containment Spray Nozzle Test Frequency 2024-09-05
[Table view] |
Text
April 5, 2005 Mr. L. M. Stinson Vice President - Farley Project Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, ENVIRONMENTAL ASSESSMENT RELATED TO EXEMPTION 10 CFR PART 50, APPENDIX E, SECTION IV.F.2.b AND c (TAC NOS. MC5395 AND MC5396)
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your request for an exemption dated December 13, 2004, that would reschedule the biennial full-participation exercise from 2004 to 2005. Future full-participation exercises will resume their normal biennial exercise cycle in 2006.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Sean Peters, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364
Enclosure:
Environmental Assessment cc w/encl: See next page
April 5, 2005 Mr. L. M. Stinson Vice President - Farley Project Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295
SUBJECT:
JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, ENVIRONMENTAL ASSESSMENT RELATED TO EXEMPTION 10 CFR PART 50, APPENDIX E, SECTION IV.F.2.b AND c (TAC NOS. MC5395 AND MC5396)
Enclosed is a copy of the Environmental Assessment and Finding of No Significant Impact related to your request for an exemption dated December 13, 2004, that would reschedule the biennial full-participation exercise from 2004 to 2005. Future full-participation exercises will resume their normal biennial exercise cycle in 2006.
The assessment is being forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Sean Peters, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket Nos. 50-348 and 50-364
Enclosure:
Environmental Assessment cc w/encl: See next page DISTRIBUTION:
PUBLIC CHawes (Hard Copy) RidsRgn2MailCenter PDII-1R/F RidsAcrsAcnwMailCenter (BBonser)
RidsNrrDlpmLpdii (EHackett) RidsOgcRp RidsNrrDlpmLpdii1 (JNakoski) RidsNrrPMSPeters ADAMS Accession Number: ML050260005 NRR-048 Office PDII-1/PM PDII-1/LA RLEP OGC PDII-1/SC Name SPeters CHawes AKugler MWoods JNakoski Date 02/01/05 02/01/05 1/18 /05 1/21/05 02/02/05 OFFICIAL RECORD COPY
Joseph M. Farley Nuclear Plant, Units 1 & 2 cc:
Mr. J. R. Johnson William D. Oldfield General Manager SAER Supervisor Southern Nuclear Operating Company, Inc. Southern Nuclear Operating Company, Inc.
P.O. Box 470 P.O. Box 470 Ashford, AL 36312 Ashford, AL 36312 Mr. B. D. McKinney, Licensing Manager Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201-1295 Mr. M. Stanford Blanton Balch and Bingham Law Firm P.O. Box 306 1710 Sixth Avenue North Birmingham, AL 35201 Mr. J. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.
P.O. Box 1295 Birmingham, AL 35201 State Health Officer Alabama Department of Public Health 434 Monroe St.
Montgomery, AL 36130-1701 Chairman Houston County Commission P.O. Box 6406 Dothan, AL 36302 Resident Inspector U.S. Nuclear Regulatory Commission 7388 N. State Highway 95 Columbia, AL 36319
7590-01-P UNITED STATES NUCLEAR REGULATORY COMMISSION SOUTHERN NUCLEAR OPERATING COMPANY DOCKET NOS. 50-348 AND 50-364 JOSEPH M. FARLEY NUCLEAR POWER PLANT, UNITS 1 AND 2 ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT The U.S. Nuclear Regulatory Commission (NRC) is considering issuance of an exemption from Title 10 of the Code of Federal Regulations (10 CFR) Part 50, Appendix E,Section IV.F.2.b and c for Facility Operating License Nos. NPF-2 and NPF-8, issued to Southern Nuclear Operating Company (SNC or the licensee), for operation of the Joseph M.
Farley Nuclear Power Plant (FNP), Units 1 and 2, located in Houston County, Alabama.
Therefore, as required by 10 CFR 51.21, the NRC is issuing this environmental assessment and finding of no significant impact.
ENVIRONMENTAL ASSESSMENT Identification of the Proposed Action:
The proposed action, as described in the licensees application for a one-time exemption to the requirements of 10 CFR Part 50, Appendix E, dated December 13, 2004, would allow the licensee to postpone the offsite full-participation emergency exercise from 2004 to 2005. The licensees letter dated December 13, 2004, requested an exemption from Section IV.F.2.e of Appendix E to 10 CFR Part 50 regarding the full participation by each offsite authority having a role under the plan. The NRC staff determined that the requirements of Section IV.F.2.e are not applicable to the circumstances of the licensees request and, accordingly, no exemption from those requirements is being granted. However, the NRC staff has determined that the
requirements of Appendix E to 10 CFR Part 50, Sections IV.F.2.b and 2.c are applicable to the circumstances of the licensees request and that an exemption from those requirements is appropriate. The licensee also stated in its December 13, 2004, letter that FNP will resume its normal biennial exercise cycle in 2006.
The Need for the Proposed Action:
The proposed exemption from 10 CFR Part 50, Appendix E, Section IV.F.2.b and c is needed because the planned full-participation exercise originally scheduled for August 18, 2004, was not performed. The Federal Emergency Management Agency (FEMA), which normally participates in the evaluated full-participation exercise, and Alabama Emergency Management Agency were unable to provide the necessary resources for the exercise due to the impact of Hurricane Charley.
Environmental Impacts of the Proposed Action:
The NRC has completed its safety evaluation of the proposed action and concludes that the proposed exemption will not present an undue risk to the public health and safety. The details of the NRC staffs Safety Evaluation will be provided in the exemption that will be issued as part of the letter to the licensee approving the exemption to the regulation. The action relates to the exercising of the emergency response plan, which has no effect on the operation of the facility.
The proposed action will not significantly increase the probability or consequences of accidents. No changes are being made in the types of effluents that may be released offsite, and there is no significant increase in occupational or public radiation exposure. Therefore, there are no significant radiological environmental impacts associated with the proposed action.
With regard to potential non-radiological impacts, the proposed action does not have a potential to affect any historic sites. It does not affect non-radiological plant effluents and has
no other environmental impact. Therefore, there are no significant non-radiological environmental impacts associated with the proposed action.
Accordingly, the NRC concludes that there are no significant environmental impacts associated with the proposed action.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the staff considered denial of the proposed action (i.e., the no-action alternative). Denial of the application would result in no change in current environmental impacts. The environmental impacts of the proposed action and the alternative action are similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than those previously considered in the Final Environmental Statement related to the operation of the Joseph M.
Farley Nuclear Plant, Units 1 and 2, dated December 1974.
Agencies and Persons Consulted:
In accordance with its stated policy, on January 6, 2005, the staff consulted with the Alabama State official, Kirk Whatley of the Office of Radiation Control, Alabama Department of Public Health, regarding the environmental impact of the proposed action. The State official had no comments.
FINDING OF NO SIGNIFICANT IMPACT On the basis of the environmental assessment, the NRC concludes that the proposed action will not have a significant effect on the quality of the human environment. Accordingly, the NRC has determined not to prepare an environmental impact statement for the proposed action.
For further details with respect to the proposed action, see the licensees letter dated December 13, 2004. Documents may be examined, and/or copied for a fee, at the NRCs
Public Document Room (PDR), located at One White Flint North, Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville, Maryland. Publicly available records will be accessible electronically from the Agencywide Documents Access and Management System (ADAMS) Public Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter problems in accessing the documents located in ADAMS should contact the NRC PDR Reference staff by telephone at 1-800-397-4209 or 301-415-4737, or by e-mail to pdr@nrc.gov.
Dated at Rockville, Maryland, this 5th day of April, 2005.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Sean Peters, Project Manager, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation