ML043650267

From kanterella
Jump to navigation Jump to search
Schedule Request Letter for Perry 95003 Inspection
ML043650267
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 11/16/2004
From: Richard Anderson
FirstEnergy Nuclear Operating Co
To: Reynolds S
NRC/RGN-III
References
PY-CEI/OIE-0626L
Download: ML043650267 (1)


Text

-

FENOC FirstEnergy Nuclear Operating Company Richard L. Anderson Perry Nuclear Power Station 10 Center Road Perry, Ohio 44081 440-280-5579 Vice President-Nuclear Fax: 440-280-8029 November 16,2004 PY-CEI/OiE-0626L Mr. Steven A. Reynolds Deputy Director, Division of Reactor Projects 2443 Warrenville Road, Suite 210 Lisle, lilinois 60532-4352

Subject:

Schedule Request for 95003 Inspection

Dear Mr. Reynolds:

As stated in the NRCs August 12, 2004 Assessment Follow-Up Letter, the Perry Nuclear Power Plant (Perry) has been placed in the MultipleIRepetitive Degraded Cornerstone column of the Action Matrix.

As part of the NRC response to Perry performance, a NRC inspection per inspection Procedure 95003 will be conducted. We request that this inspection be started on May 16, 2005. This date is being requested to allow Perry to complete Refueling Outage 10 during the months of February and March of 2005 and to demonstrate progress in the implementation of the Perry Performance Improvement Initiative.

+>+ If you have any questions or require further dialogue regarding this matter, please contact Jeff Lausberg (440) 280-5940.

cc: RAS File