Nuclear Operating Company December 13, 2004 NOC-AE-04001828 File No.: G02 1 OCFR50.71 STI: 31818998 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Monthly Operating Reports for November 2004 Pursuant to 10CFR50.71(a) and South Texas Project Electric Generating Station (STPEGS) Technical Specification 6.9.1.5, attached are the Monthly Operating Reports for November 2004.
If you should have any questions on this matter, please contact R.L. Hill at (361) 972-7667.
F.H. Mallen General Manager, Financial Support Attachments: 1)
STPEGS Unit 1 Monthly Operating Report - November 2004
- 2)
STPEGS Unit 2 Monthly Operating Report - November 2004
NOE-AE-04001828 Page 2 of 2 cc:
(paper copy)
(electronic copy)
Bruce S. Mallett Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 Richard A. Ratliff Bureau of Radiation Control Texas Department of Health 1100 West 49th Street Austin, TX 78756-3189 Jeffrey Cruz U. S. Nuclear Regulatory Commission P. O. Box 289, Mail Code: MN116 Wadsworth, TX 77483 A. H. Gutterman, Esquire Morgan, Lewis & Bockius LLP L. D. Blaylock City Public Service Michael K. Webb U. S. Nuclear Regulatory Commission R. L. Balcom Texas Genco, LP A. Ramirez City of Austin C. A. Johnson AEP Texas Central Company Jon C. Wood Matthews & Branscomb C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704
SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT I MONTHLY OPERATING REPORT NOVEMBER 2004 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50498 LICENSE NO. NPF-76 Approved By:
kAJA°4l 124uA/w G.L. PaKE Date
MONTHLY
SUMMARY
South Texas Project Unit 1 operated during the reporting period at full power with no unit shutdowns or significant power reductions.
OPERATING DATA REPORT.
DOCKET NO.
50-498 UNIT I
DATE Dec. 7. 2004 COMPLETED BY R.L. Hill TELEPHONE 361-972-7667 OPERATING STATUS
- 1.
REPORTING PERIOD: 11/1/04 - 11/30/04 GROSS HOURS IN REPORTING PERIOD:720
- 2.
CURRENTLY AUTHORIZED POWER LEVEL (Mwt): 3.853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1.250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1.250.6
- 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
- 4.
REASONS FOR RESTRICTION (IF ANY): N/A
- 5.
NUMBER OF HOURS REACTOR CRITICAL
- 6.
REACTOR RESERVE SHUTDOWN HOURS
- 7.
HOURS GENERATOR ON LINE
- 8.
UNIT RESERVE SHUTDOWN HOURS
- 9.
GROSS THERMAL ENERGY GENERATED (MWH)
- 10.
NET ELECTRICAL ENERGY GENERATED (MWH)
- 11.
REACTOR SERVICE FACTOR (%)
- 12.
REACTOR AVAILABILITY FACTOR (%o)
- 13.
UNIT SERVICE FACTOR (% )
- 14.
UNIT AVAILABILITY FACTOR (%/)
- 15.
UNIT CAPACITY FACTOR - Using MDC (%)
- 16.
UNIT CAPACITY FACTOR - Using DER (%)
- 17. UNIT FORCED OUTAGE RATE (%)
THIS MONTH 720.0 0
720.0 0
2.785.921 924,382 100.0 100.0 100.0 100.0 102.7 102.7 0.0 YR TO DATE 7.984.9 0
7.968.8 0
30.797.505 10.182,415 99.3 99.3 99.1 99.1 101.3 101.3 0.9 CUMULATIVE 112.000.4 0
110.296.3 0
413.764.962 135.257.252 78.5 78.5 77.3 77.3 75.8 75.8 13.8
- 18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH):
Scheduled 30-day outage to allow scheduled refueling to begin on March 9, 2005.
- 19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: NIA
AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50498 UNIT I
DATE Dec. 7 2004 COMPLETED BY R.L. Hill TELEPHONE 361-972-7667 MONTH NOVEMBER DAY AVERAGE DAILY POWER LEVEL (MWe-Net)
DAY I
2 3
4 5
6 7
8 9
10 11 12 13 14 15 16 1279 1280 1283 1286 1287 1285 1286 1283 1283 1284 1282 1282 1278 1284 1283 1282 17 18 19 20 21 22 23 24 25 26 27 28 29 30 AVERAGE DAILY POWER LEVEL (MWe-Net) 1282 1284 1286 1284 1289 1284 1280 1286 1287 1286 1286 1287 1284 1286
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
50-498 UNIT I
DATE Dec. 7 2004 COMPLETED BY R.L. Hill TELEPHONE 361-972-7667 REPORT MONTH NOVEMBER 1
2 3
4 5
No.
Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours)
Shutting Event Code Code Down Report #
Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD I
I I
I I
I I
I I
F: Forced S: Scheduled 2
Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3 Method:
1-Manual 2-Manual Scram 3-Automatic Scram 4-Cont. of Existing Outage 5-Reduction 9-Other 4
PORVS AND SAFETY VALVE
SUMMARY
There were no PORV or Safety Valves challenged during the reporting period.
SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 2 MONTHLY OPERATING REPORT NOVEMBER 2004 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-499 LICENSE NO. NPF-80 G.L. PARKEY Date Approved By:
MONTHLY
SUMMARY
South Texas Project Unit 2 operated during the reporting period with no unit shutdowns or significant power reductions.
OPERATING DATA REPORT DOCKETNO.
50-499 UNIT 2
DATE Dec.7, 2004 COMPLETED BY R.L. Hill TELEPHONE 361-972-7667 OPERATING STATUS
- 1.
REPORTING PERIOD: 11/1/04 -11/30/04 GROSS HOURS IN REPORTING PERIOD: 720
- 2.
CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3,853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1.250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1,250.6
- 3.
POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
- 4.
REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
- 5.
NUMBER OF HOURS REACTOR CRITICAL
- 6.
REACTOR RESERVE SHUTDOWN HOURS
- 7.
HOURS GENERATOR ON LINE
- 8.
UNIT RESERVE SHUTDOWN HOURS
- 9.
GROSS THERMAL ENERGY GENERATED (MWH)
- 10.
NET ELECTRICAL ENERGY GENERATED (MWH)
- 11.
REACTOR SERVICE FACTOR (%s)
- 12.
REACTOR AVAILABILITY FACTOR (%)
- 13.
UNIT SERVICE FACTOR (%)
- 14.
UNIT AVAILABILITY FACTOR (%)
- 15.
UNIT CAPACITY FACTOR - Using MDC (%)
- 16.
UNIT CAPACITY FACTOR - Using DER (%)
- 17.
UNIT FORCED OUTAGE RATE (as) 720.0 0
720.0 0
2.786.199 923,039 100.0 100.0 100.0 100.0 102.5 102.5 0.0 7,394.9 7.377.5 28,429J152 9.348,914 92.0 92.0 91.8 91.8 93.0 93.0 0.5 109.099.4 0
130,447,091 80.5 80.5 78.8 78.8 77.0 77.0 13.1
- 18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH): N/A
- 19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
AVERAGE DAILY UNIT POWER LEVEL DOCKETNO.
50-499 UNIT 2
DATE Dec. 7 2004 COMPLETED BY R.L. Hill TELEPHONE 361-972-7667 MONTH NOVEMBER DAY 1
2 3
4 5
6 7
8 9
10 12 13 14 15 16 AVERAGE DAILY POWER LEVEL (MWe-Net) 1276 1276 1278 1280 1282 1283 1282 1283 1279 1284 1284 1285 1280 1286 1284 1284 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 17 1283 18 1283 19 1283 20 1281 21 1281 22 1281 23 1280 24 1282 25 1284 26 1282 27 1283 28 1284 29 1282 30 1283
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE 50-499 2
Dec. 7. 2004 R.L. Hill 361-972-7667 REPORT MONTH NOVEMBER 12 3
4 5
No.
Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours)
Shutting Event Code Code Down Report #
Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD l
l l
l l
l I
1 F: Forced S: Scheduled 2
Reason:
A-Equipment Failure (Explain)
B-Maintenance or Test C-Refueling D-Regulatory Restriction E-Operator Training & License Exam F-Administrative G-Operational Error (Explain)
H-Other (Explain) 3 Method:
1-Manual 2-Manual Scram 3-Automatic Scram 4-Cont. of Existing Outage 5-Reduction 9-Other 4
PORVS AND SAFETY VALVE
SUMMARY
There were no PORV or Safety Valves challenged during the reporting period.