December 20, 2004 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
REVISION OF SCHEDULE FOR CONDUCTING THE REVIEW OF POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION
Dear Mr. Koehl:
Enclosed is a revised schedule for review of the Point Beach Nuclear Plant, Units 1 and 2 license renewal application. This schedule has been revised to reflect the 22-month review plan.
If you have any questions on the revised review schedule, please contact me by telephone at 301-415-2232 or via electronic mail at mjm2@nrc.gov.
Sincerely,
/RA/
Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvements Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301
Enclosure:
As stated cc w/encl: See next page
December 20, 2004 Mr. Dennis L. Koehl Site Vice President Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516
SUBJECT:
REVISION OF SCHEDULE FOR CONDUCTING THE REVIEW OF POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION
Dear Mr. Koehl:
Enclosed is a revised schedule for review of the Point Beach Nuclear Plant, Units 1 and 2 license renewal application. This schedule has been revised to reflect the 22-month review plan.
If you have any questions on the revised review schedule, please contact me by telephone at 301-415-2232 or via electronic mail at mjm2@nrc.gov.
Sincerely,
/RA/
Michael J. Morgan, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvements Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-266 and 50-301
Enclosure:
As stated cc w/encl: See next page DISTRIBUTION: See next page Adams accession no.: ML043560097 Document Name: E:\\Filenet\\ML043560097.wpd OFFICE LA:RLEP PM:RLEP SC:RLEP NAME M. Jenkins M. Morgan S. Lee DATE 12/16/04 12/20/04 12/20/04 OFFICIAL RECORD COPY
DISTRIBUTION: Ltr to D. Koehl, Re: Point Beach, Units 1 and 2, Dated: December 20, 2004 ADAMS Accession No: ML HARD COPY RLEP RF M. Morgan (PM)
E-MAIL:
PUBLIC D. Matthews F. Gillespie C. Grimes RidsNrrDe E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair S. Black B. Boger D. Thatcher R. Pettis G. Galletti C. Li M. Itzkowitz R. Weisman M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff P. Lougheed, RIII J. Strasma, RIII A. Stone, RIII H. Chernoff W. Ruland C. Marco L. Raghavan T. Mensah OPA
Enclosure POINT BEACH, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Schedule Actual Receive license renewal application 02/27/04 02/26/04 Federal Register Notice (FRN) published for receipt and availability 03/05/04 03/08/04 Public Meeting - Safety review overview 03/31/04 03/31/04 FRN published for acceptance/rejection/opportunity for hearing 04/08/04 04/13/04 AMR and AMP Consistent with GALL Audit 04/26/04 04/26/04 FRN published for intent/environmental scoping meeting 05/14/04 05/14/04 AMR/ AMP Audit 06/07/04 06/07/04 Deadline for filing hearing requests and petitions for intervention 06/13/04 06/13/04 Public Meeting - Environmental scoping meeting 06/15/04 06/15/04 Environmental Audit 06/16/04 06/16/04 Scoping and Screening Methodology Audit Complete 06/21/04 06/21/04 Follow-up Technical Audit with Public Exit 07/12/04 07/15/04 Environmental scoping period ends 07/14/04 07/14/04 Environmental requests for additional information (RAIs) issued 08/06/04 08/06/04 Environmental RAIs responses received 09/22/04 09/22/04 Draft supplemental environmental impact statement (SEIS) issued 01/21/05 FRN published for availability/comment on draft SEIS 01/28/05 Regional aging management program inspection complete 02/14/05 Public Meeting to discuss draft SEIS 02/15/05 End of draft SEIS comment period 04/13/05 Regional aging management program inspection complete 04/18/05 Safety evaluation report (SER) with open items issued 05/02/05 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting on SER with open items 06/05 SER open items responses received 07/07/05 Final SEIS issued 09/02/05 FRN published for availability of final SEIS 09/09/05 SER issued 10/01/05 ACRS Full Committee meeting on SER 11/05 ACRS letter issued 11/05 Staff Recommendation to Director, NRR 12/20/05 Decision - Director, NRR (license issued, if approved) 12/27/05
Point Beach Nuclear Plant, Units 1 and 2 cc:
Jonathan Rogoff, Esquire Vice President, Counsel & Secretary Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Mr. Frederick D. Kuester President and Chief Operating Officer We Generation 231 West Michigan Street Milwaukee, WI 53201 James Connolly Manager, Regulatory Affairs Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Mr. Ken Duveneck Town Chairman Town of Two Creeks 13017 State Highway 42 Mishicot, WI 54228 Chairman Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 801 Warrenville Road Lisle, IL 60532-4351 Resident Inspector's Office U.S. Nuclear Regulatory Commission 6612 Nuclear Road Two Rivers, WI 54241 Mr. Jeffery Kitsembel Electric Division Public Service Commission of Wisconsin P.O. Box 7854 Madison, WI 53707-7854 David Weaver Nuclear Asset Manager Wisconsin Electric Power Company 231 West Michigan Street Milwaukee, WI 53201 John Paul Cowan Executive Vice President & Chief Nuclear Officer Nuclear Management Company, LLC 700 First Street Hudson, WI 54016 Douglas E. Cooper Senior Vice President - Group Operations Palisades Nuclear Plant Nuclear Management Company, LLC 27780 Blue Star Memorial Highway Covert, MI 49043 Mr. Fred Emerson Nuclear Energy Institute 1776 I Street, NW., Suite 400 Washington, DC 20006-3708 James E. Knorr License Renewal Project Point Beach Nuclear Plant Nuclear Management Company, LLC 6610 Nuclear Road Two Rivers, WI 54241 Roger A. Newton 3623 Nagawicka Shores Drive Hartland, WI 53029