Tennessee Valley Authority, Post Office Box 2000, Decatur, Alabama 35609-2000 November 30, 2004 10 CFR 50.4 10 CFR 50.59 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Mail Stop:
OWFN Pl-35 Washington, D.C. 20555-0001 Gentlemen:
In the Matter of
)
Docket Nos. 50-259 Tennessee Valley Authority
)
50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN)
UNITS 1, 2, AND 3 -
SUMMARY
REPORT FOR April 1, 2003 THROUGH June 30, 2004 The enclosures to this letter provide the BFN Summary Report (SR) for April 1, 2003 through June 30, 2004. contains Units 2 and 3, 10 CFR 50.59(b)(2),
summaries which include brief descriptions of any changes, tests, and experiments with safety evaluations prepared for revisions to the Updated Final Safety Analysis Report, plant procedures (new and revised), special operating conditions, special tests, temporary alterations, and plant modifications that were field completed during this reporting period. contains Unit 1, 10 CFR 50.59 (b)(2),summaries which include brief descriptions of any changes, tests, and experiments with safety evaluations prepared for plant modifications that were field completed during this reporting period.
X L,
Pt.ed on WcyOd p
U.S. Nuclear Regulatory Commission Page 2 November 30, 2004 Since the last Summary Report, there have been six revisions to the Fire Protection Report (FPR). contains the BFN FPR, Revision 28, which includes all six revisions. includes copies of changes to the BFN Technical Specifications (TS) Bases in accordance with BFN TS Section 5.10, TS Bases Control Program for Units 1, 2,
and 3.
The changes have been incorporated for which prior NRC approval was not required. contains Section 5.1, Technical Requirements (TRM)
Control Program for Units 1, 2, and 3.
The changes have been incorporated and did not require prior NRC approval.
During this reporting period, there were no previous commitments that TVA has evaluated and revised using administrative controls that incorporate the Nuclear Energy Institute's (NEI) 99-04 "Guideline For Managing NRC Commitments" in accordance with 10 CFR 50.109(a) (7) through BFN Standard Programs and Processes (SPP)-3.3, Managing NRC Commitments.
There are no commitments contained in this letter.
If you have any questions regarding this report, please contact me at (256) 729-2636.
U.S. Nuclear Regulatory Commission Page 3 November 30, 2004 Enclosures cc (without enclosures)
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-3415 Mr. Stephen J. Cahill, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970 Margaret Chernoff, Senior Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739