MONTHYEARML24123A0502024-05-0202 May 2024 2023 Annual Assessment Public Meeting Summary Meeting Number 20240479 ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML22108A1382022-04-18018 April 2022 Annual Assessment Public Meeting Summary ML21280A2962021-10-22022 October 2021 Replacement of Page 2 to Letter Dated June 30, 2020, Titled License Amendment Request to Revise the Emergency Plan to Change Staffing and Extend Staff Augmentation Times for Emergency Response Organization Positions (EPID L-2020-LLA0150) ML21124A1232021-05-0404 May 2021 April 27, 2021, Public Meeting Summary Joseph M. Farley Nuclear Plant Units 1 and 2, Edwin I. Hatch Nuclear Plant Units 1 and 2, Docket No. 50-348, 50-364, 50-321, 50-366, Meeting Number ML21117A030 ML20154K7242020-06-0202 June 2020 EOC Meeting Summary ML19123A3542019-05-0202 May 2019 Public Meeting Summary - Hatch Nuclear Plant, Docket Nos. 50-321 and 50-366 ML18124A0052018-05-0404 May 2018 Summary of Public Meeting - Hatch Nuclear Plant Docket Nos. 50-321, 50-366 ML17131A1572017-05-11011 May 2017 Summary of Public Meeting Concerning Annual Assessment of Edwin I. Hatch Nuclear Plant, Units 1 and 2 ML17111A5792017-04-26026 April 2017 Request for Additional Information, Fourth 10-Year ISI Interval Relief Requests ML16071A3132016-03-14014 March 2016 Notice of Forthcoming Closed Meeting with Southern Nuclear Operating Company to Discuss the Replacement of Security Computer System at Edwin I. Hatch, Units 1 and 2 ML15121A0342015-04-30030 April 2015 Summary of Public Meeting to Discuss the 2014 Annual Performance Assessment of the Edwin I. Hatch Nuclear Plant ML14115A4102014-04-25025 April 2014 Summary of Public Meeting to Discuss Annual Assessment of Edwin I. Hatch Nuclear Plant, Units 1 and 2, in Vidalia, Georgia ML13309A0802013-12-11011 December 2013 Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors ML13277A3822013-11-0404 November 2013 Notice of Forthcoming Meeting with Southern Nuclear on Polyethylene Pipe for Hatch Service Water Systems ML12003A2272011-12-21021 December 2011 G20110883/EDATS: OEDO-2011-0800 - R. W. Borchardt Memo Re Backfit Appeal Associated with Component Design Bases Inspection at Edwin I. Hatch Nuclear Plant ML11349A0972011-12-15015 December 2011 Verbal Authorization of Inservice Inspection Program Alternative HNP-ISI-ALT-15, Version 2, Associated with Safety Relief Valve Testing ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0722200462007-08-0909 August 2007 Emergency Exercise (August 22, 2007) ML0706400412007-03-0606 March 2007 Commitment Lists for Renewed Operating License (ROL) Plants with No Commitment Appendix Attached to Its ROL Sers/Nuregs for Use with IP-71003 ML0703002272007-02-0606 February 2007 Facsimile Transmission of Draft Request for Additional Information on Emergency Action Level Revision ML0611505402006-04-25025 April 2006 Errata for Edwin I. Hatch Nuclear Power Plant Public Annual Assessment Meeting ML0602700762006-02-0202 February 2006 RAI Relief from Various Inservice Testing Requirements ML0531401152005-11-23023 November 2005 Letter MC9810, Staff Decision Regarding GL2003-01 ML0531903342005-11-14014 November 2005 Notice of Meeting with Southern Nuclear Operating Co, Inc., Regarding Control Room In-leakage Testing at Hatch, Units 1 and 2 ML0524903452005-09-0101 September 2005 Memo MC7543, ISI Summary Reports ML0511602262005-04-27027 April 2005 Memo, Facsimile Transmission of Draft RAI MC3875 ML0511602702005-04-27027 April 2005 Memo, Facsimile Transmission of Draft Request for Additional Information ML0511602532005-04-27027 April 2005 Memo, Facsimile Transmission of Draft RAI (TAC MC4227 & MC4228) ML0511604202005-04-26026 April 2005 Task Interface Agreement (TIA 2005-003) Related to the Operability and Validity of the Local Leak Rate Testing of the Main Steam Isolation Valves - Plant Edwin I. Hatch ML0505900312005-03-0202 March 2005 Facsimile Transmission of Draft Request for Additional Information (Tac No. MC3875, MC3876) ML0505900192005-03-0202 March 2005 Facsimile Transmission of Draft Request for Additional Information ML0434802572004-12-15015 December 2004 Updated Analysis of Core Shroud Vertical Welds ML0430804962004-11-0505 November 2004 Memorandum, Facsimile Transmission of Draft Request for Additional Information. TAC Nos. MC3615 and MC3616 ML0415302092004-06-0101 June 2004 Docketing of Questions and Responses Transmitted Electronically or by Facsimile ML0411700102004-04-22022 April 2004 4/22/04, Hatch, Units 1 & 2, Memo, Bases Revisions for 2003 ML0405606052004-02-20020 February 2004 Memo, Correction of License Authority Files, Amendment Nos. 228, 170 and 174 ML0331604772003-11-12012 November 2003 Email on EOF Relocation ML0327205272003-10-21021 October 2003 Plan and Schedule for Implementation of Staff Position on the Station Blackout (SBO) Issue ML0311800572003-04-25025 April 2003 Results of the Edwin I. Hatch Generating Station Units 1 and 2 SDP Phase 2 Notebook Benchmarking Visit ML0300802552003-01-0808 January 2003 Report on Status of Open TIAs Assigned to NRR ML0231700712002-11-13013 November 2002 Report on the Status of Open TIAs Assigned to NRR NRC Generic Letter 1989-111989-06-30030 June 1989 NRC Generic Letter 1989-011: Resolution of Generic Issue 101 Boiling Water Reactor Water Level Redundancy 2024-05-02
[Table view] |
Text
December 15, 2004 MEMORANDUM TO: John Nakoski, Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Christopher Gratton, Sr. Project Manager, Section 1 /RA/
Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT 1, UPDATED ANALYSIS OF CORE SHROUD VERTICAL WELDS (TAC NOS. MC1322 AND MC5246)
By letter dated November 14, 2003, Southern Nuclear Operating Company (SNC) provided to the Nuclear Regulatory Commission (NRC) the calculation and description of the methodology of the updated flaw analysis of the Edwin I. Hatch, Unit 1 flawed core shroud vertical welds. In a subsequent letter dated January 30, 2004, SNC provided the related fluence calculation and methodology.
The purpose of this memo is to inform you that by letter dated December 3, 2004, SNC provided an updated core shroud vertical welds analysis based on a reexamination of the welds during the Spring 2004 refueling outage using ultrasonic techniques. The licensee stated that the revised analysis supercedes the analysis provided in SNCs November 14, 2004, letter. As a result, the NRC staff will close the review (TAC NO. MC1322) of the November 14, 2004, core shroud vertical welds analysis and begin a new evaluation (TAC NO. MC5246) of the information provided in the December 3, 2004, letter to the NRC staff.
Docket No. 50-321
December 15, 2004 MEMORANDUM TO: John Nakoski, Chief, Section 1 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: Christopher Gratton, Sr. Project Manager, Section 1 /RA/
Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
EDWIN I. HATCH NUCLEAR PLANT, UNIT 1, UPDATED ANALYSIS OF CORE SHROUD VERTICAL WELDS (TAC NOS. MC1322 AND MC5246)
By letter dated November 14, 2003, Southern Nuclear Operating Company (SNC) provided to the Nuclear Regulatory Commission (NRC) the calculation and description of the methodology of the updated flaw analysis of the Edwin I. Hatch, Unit 1 flawed core shroud vertical welds. In a subsequent letter dated January 30, 2004, SNC provided the related fluence calculation and methodology.
The purpose of this memo is to inform you that by letter dated December 3, 2004, SNC provided an updated core shroud vertical welds analysis based on a reexamination of the welds during the Spring 2004 refueling outage using ultrasonic techniques. The licensee stated that the revised analysis supercedes the analysis provided in SNCs November 14, 2004, letter. As a result, the NRC staff will close the review (TAC NO. MC1322) of the November 14, 2004, core shroud vertical welds analysis and begin a new evaluation (TAC NO. MC5246) of the information provided in the December 3, 2004, letter to the NRC staff.
Docket No. 50-321 DISTRIBUTION:
PUBLIC PDII-1 R/F EHackett JNakoski CGratton CHawes ADAMS Accession Number: ML043480257 NRR-106 OFFICE PM/PDII-1 LA/PDII-1 NAME CGratton CHawes DATE 12/15/04 12/15/04 OFFICIAL RECORD COPY